Wastage analysis (analysis of process waste from current and future VSM)
| Process steps | Examples of waste | Causes | Corrective actions Generated from the Kaizen |
|---|---|---|---|
| 1. Cutting | Muri: The operator in the cutting step was working a 10-h shift to meet the demand of the other process steps while achieving just 4 h of production time Overprocessing: No jig in place operator measuring material for every cut | Lack of material organisation and storage Equipment not set up for standardised work | Standard work and an extra operator were introduced to improve the flow 5S system set up with equipment |
| 2. Grinding | Waiting: Significant production time was lost due to waiting for material from the cutting step | A bottleneck in cutting step | Standard work was implemented, and an extra operator in cutting reduced the bottleneck |
| 3. Tacking | Waiting/motion/transport: Lost production time due to lack of tools -missing jigs and clamps Defects: Wrong tools used | Lack of correct equipment Operator error | 5S system set up with new equipment. Poke Yoke introduced |
| 4. Welding | Overburdened: welder 10-h shifts High defects – scrap levels | Bottleneck More resources required | Standard work was implemented, and a new welder was added to improve the flow Poke Yoke introduced |
| 5. Cleaning | Waiting: on welding | Bottleneck from the previous station | Eliminated with the new welder |
| 6. QC check | Overprocessing – manual steps printing, writing, scanning | Not automated | A new process with standard work and an Automated scanner introduced |
| 7. Wrapping | Waiting on welding | Bottleneck | Eliminated with a new welder. Merged with QC check |
| 8. Shipping | Transport/waiting/inventory of skids | Outgoing inventory build-up/no space/delays in getting on site | A just in time (JIT) daily delivery of skids was implemented (just as required on site) |
| Process steps | Examples of waste | Causes | Corrective actions |
|---|---|---|---|
| 1. Cutting | Lack of material organisation and storage | Standard work and an extra operator were introduced to improve the flow | |
| 2. Grinding | A bottleneck in cutting step | Standard work was implemented, and an extra operator in cutting reduced the bottleneck | |
| 3. Tacking | Lack of correct equipment | 5S system set up with new equipment. | |
| 4. Welding | Bottleneck | Standard work was implemented, and a new welder was added to improve the flow | |
| 5. Cleaning | Bottleneck from the previous station | Eliminated with the new welder | |
| 6. QC check | Not automated | A new process with standard work and an Automated scanner introduced | |
| 7. Wrapping | Bottleneck | Eliminated with a new welder. Merged with QC check | |
| 8. Shipping | Outgoing inventory build-up/no space/delays in getting on site | A just in time (JIT) daily delivery of skids was implemented (just as required on site) |