Table 4.

Wastage analysis (analysis of process waste from current and future VSM)

Process stepsExamples of wasteCausesCorrective actions
Generated from the Kaizen
1. CuttingMuri: The operator in the cutting step was working a 10-h shift to meet the demand of the other process steps while achieving just 4 h of production time
Overprocessing: No jig in place operator measuring material for every cut
Lack of material organisation and storage
Equipment not set up for standardised work
Standard work and an extra operator were introduced to improve the flow
5S system set up with equipment
2. GrindingWaiting: Significant production time was lost due to waiting for material from the cutting stepA bottleneck in cutting stepStandard work was implemented, and an extra operator in cutting reduced the bottleneck
3. TackingWaiting/motion/transport:
Lost production time due to lack of tools -missing jigs and clamps
Defects: Wrong tools used
Lack of correct equipment
Operator error
5S system set up with new equipment.
Poke Yoke introduced
4. WeldingOverburdened: welder
10-h shifts
High defects – scrap levels
Bottleneck
More resources required
Standard work was implemented, and a new welder was added to improve the flow
Poke Yoke introduced
5. CleaningWaiting: on weldingBottleneck from the previous stationEliminated with the new welder
6. QC checkOverprocessing – manual steps printing, writing, scanningNot automatedA new process with standard work and an Automated scanner introduced
7. WrappingWaiting on weldingBottleneckEliminated with a new welder. Merged with QC check
8. ShippingTransport/waiting/inventory of skidsOutgoing inventory build-up/no space/delays in getting on siteA just in time (JIT) daily delivery of skids was implemented (just as required on site)
Source: Authors’ own