Table 1.

Contrasting project management approaches

AspectHard project management approachSoft project management approach
Key paradigmA project is a process of activities and tasks that needs to be completedaA project is a strategic activity which contributes to a larger business objectivea
Project manager roleDelivering the project on time and within budget, as well as adhering to defined specificationsaDelivering the project from a more holistic perspective, to create business results and valuea
Success criteriaLinked to operational/project successaLinked to strategic/organizational success, i.e. how outcomes of a project will influence the organizationa
Typically understood in terms of the “iron triangle,” i.e. project completion on time and within budget, performancea and associated with quantitative criteriacTypically understood in terms of business success, impact on customer, impact on business, long-term results, valuea and associated with qualitative criteriac
TargetsTargets are provided, by e.g. top management or clientb,d, are (preferably) clearly stated and typically predefined with a given set of resource constraintsc,dTargets evolve, from a general vision and direction rather than from clear and specific objectives at project outsetb, i.e. objectives are ambiguous and difficult to define at initiationc,d
Targets are associated with a tangible physical artefactcTargets are associated with abstract conceptc
ActivitiesActivities can be articulated, defined and plannedb, associated with narrow and clear task definitioneActivities are partly emergentb, associated with broad task definitione
Associated with the refinement of one solutioncAssociated with the simultaneous pursuit of multiple solutionsc,d
Stakeholder involvementAssociated with expert practitioner, coordinating approach with limited or no stakeholder participationcAssociated with a participative, collaborative and facilitative approach with high stakeholder involvementc
Project changesChanges are undesirable and should be limitede
Changes are associated with variation (plan deviations) and risks (stochastic, estimable changes in known project variables)b
Changes are viewed as inevitable and should be facilitatede
Changes are associated with unforeseeable uncertainty, i.e. new variables, effects and actions, which could not be anticipated at the outsetb
Sources: Shenhar and Dvir, 2007a; Lenfle and Loch, 2010b; Crawford and Pollack, 2004c; Davies and Brady, 2016d; Koppenjan et al., 2011e; Developed by author by adapting and compiling research proposing categories of project management approaches, acknowledging in particular the work by Shenhar and Dvir (2007), Lenfle and Loch (2010), Crawford and Pollack (2004), Davies and Brady (2016) and Koppenjan et al. (2011) 