Table 3

Thematic analysis of the qualitative data from human expert feedback on the responses

ThemePositive feedbackNegative feedback
ComprehensivenessR5 (V6): Risks identified from a variety of perspectives and broken down into different areas. All also identified a number of measures. At this level and with this information, a comprehensive assessment has been madeR1 (V4): The answers and analysis of risks are very limited and leave most of the potential risk factors unmentioned/unanalyzed
R7 (V13): Respondent lists the three most significant risks. I agree with these. These have not been analyzed in detail in this section, but on the other hand respondent 13 has already opened up these issues in Section 2. For example 10 sentences per riskR13 (V15): Key issues identified, but a limited response
R17 (V1): The user is well highlighted, with small things (such as information, e.g. weekly newsletters) the project can be streamlined considerably. An angry user can put the whole project in crisis. Realities taken into account, updates to plans will always come. In scheduling, consideration of the collection of planning baseline data and changes is essentialR19 (V1): Identifies the features of the project but not the risks associated with that feature
R1 (AI): Responses are comprehensive and take into account the majority of critical risks and their management in the type of site presentedR7 (AI): A broad sample of risks is a good thing in itself. Some of the risks were quite generic, it seems that a generic list of project risks was used
R3 (AI): The answer is comprehensive and I think quite goodR19 (AI): Responses at a general level. No specific characteristics of the project are identified. Comprehensive list otherwise
R5 (AI): Risks are identified from a variety of perspectives and broken down into different areas. All also identified a number of measures. At this level and with this information, a comprehensive assessment has been madeR19 (AI): Lack of identification of risks
R7 (AI): The main risks are well-listed and analyzed. Clearly the best answer to point 3R19 (AI): Did not open up the risks of the project
R13 (AI): The response lists a wide range of risk types and risks 
R17 (AI): Risks considered comprehensively from different perspectives, but at a general level 
Specificity and practicalityR7 (V13): A broad sample of risks and well-opened them. Clearly the risks have been thought through specifically for this project. Clearly the best risk coverage of the responses presentedR3 (V1): In addition, neighbors, site organization and safety should be taken into account when working in a densely populated area in Töölö
R8 (V11): Relevant risks identified, analyses in previous section but could be more comprehensiveR6 (V14): Answer confusingly in other paragraphs
R8 (V11): This was a very explicit assessment of site-specific risks based on baseline dataR7 (V4): I would have liked to have seen a more detailed analysis of the risks, now I am left with general remarks
R7 (AI): Very well opened up to more specific measures per risk. Clearly the best answer to point 4R13 (V8): The response was limited and project specificity was not taken into account
R9 (AI): In response, risk identification and analysis is broad but sufficiently focused on the project. The answers to question 2 are a bit more circular than those from V13, hence the lower score. Overall, the best answer, where the analysis is of high quality and clarifies the risks identified, followed by management measures that provide good steps based on the analysisR14 (V1): The sentences are not complete, and for the most part leave it unclear how the potential risks presented will affect the achievement of the project's objectives
R13 (AI): Critical risks are well selected and the main points are disclosedR3 (AI): A few points that are left floating in the air without concrete action, e.g. “Use a procurement strategy that ensures competitive prices and quality materials”
R17 (AI): Risks considered comprehensively from different perspectives, but at a general level (perhaps more specificity on some points?) The answers to questions 2 and 3 are general, but very concrete suggestions are given in answer 4R8 (AI): Site specificity had been taken into account, but for the most part this was a fairly general list of risks that apply to any project
 R10 (AI): Clearly knows a lot about risk management, but the concrete measures risk getting lost in the mass of text/prioritization falls by the wayside
Feasibility of implementationR17 (V8): Concise answer, not much to evaluate. Occupational safety risks good points! Essential points mentioned, such as output data risksR3 (V10): The answer is a bit off track. There is no mention in the brief of any zoning change or of the building being protected
R19 (V1): Solution-oriented and project-specificR8 (V13): A rather superficial answer
R7 (AI): Very well opened up to more specific measures per riskR3 (AI): There are certain points in the response which are extremely difficult to implement in practice
R9 (AI): Overall, the best answer, where the analysis is of high quality and clarifies the risks identified, followed by management measures that provide good steps based on the analysisR6 (AI): I would have liked to have seen some mention of proper resourcing of the site and possible double-shift working to manage the schedule risk
R13 (AI): The issues are presented well and clearly. The process for dealing with surprising isolated anomalies and incidents is not specified, but at a higher level the answers are goodR11 (AI): Respondent is not in a position to lead these projects
R19 (AI): A good attempt to prevent the risks identified. Partly describing the basic tasks, could describe the specificities of the project and the deviating measuresR15 (AI): The timetable given is so tight that it cannot be flexible – focus on advance planning and preparation
Abundance of informationR10 (V7): This is probably my favorite when you keep the answers suitably short (although not as comprehensive as respondent 17 [AI])R7 (V4): In the big picture, significant risks identified, but remained at a rather general level. I would have liked to see a broader list of risks and a slightly more defined set of risks
R10 (V14): It must be a genuine doer since he doesn't talk nonsense and the answers show the background of the constructionR19 (V9): Disruption management well identified, safety at work not. Aiming to do the job well is not a measure of risk management
R15 (V16): Right thingsR10 (AI): Clearly knows a lot about risk management, but the concrete measures risk getting lost in the mass of text/prioritization falls by the wayside
R8 (AI): Essential risks identified from a long list and concisely but well analyzedR15 (AI): I would have emphasized the specificities of renovation in terms of schedule and user cooperation, which also have an impact on the schedule, rather than quality risks
R9 (AI): Overall, the best answer, where the analysis is of high quality and clarifies the risks identified, followed by management measures that provide good steps based on the analysis 
R14 (AI): The respondent has identified in detail and in a comprehensive manner the potential challenges related to the project 