| Model | Unstandardized coefficients | Standardized coefficients | t | Sig | |
|---|---|---|---|---|---|
| B | Std. error | Beta | |||
| 1 (Constant) | 0.101 | 0.366 | 0.276 | 0.783 | |
| E1-Skilled and experienced team members | 0.191 | 0.055 | 0.177 | 3.450 | 0.001 |
| E2-Explicity defined roles of project team members | 0.077 | 0.048 | 0.087 | 1.609 | 0.108 |
| E3-Accurate work breakdown structure (WBS) | 0.131 | 0.057 | 0.112 | 2.293 | 0.022 |
| B1-Lack of standard processes | 0.269 | 0.057 | 0.246 | 4.731 | 0.000 |
| B2-Vague contract deliverables | 0.015 | 0.048 | 0.013 | 0.305 | 0.760 |
| B3-Unclear project goals | 0.231 | 0.058 | 0.176 | 3.982 | 0.000 |
| B4-Unclear project milestones | −0.031 | 0.050 | −0.031 | −0.620 | 0.536 |
| B5-Disparate control system between owner and contractor | 0.132 | 0.041 | 0.141 | 3.207 | 0.001 |
| B6-Lack of information communication | −0.022 | 0.041 | −0.028 | −0.532 | 0.595 |
| Model | Unstandardized coefficients | Standardized coefficients | Sig | ||
|---|---|---|---|---|---|
| Std. error | Beta | ||||
| 1 (Constant) | 0.101 | 0.366 | 0.276 | 0.783 | |
| E1-Skilled and experienced team members | 0.191 | 0.055 | 0.177 | 3.450 | 0.001 |
| E2-Explicity defined roles of project team members | 0.077 | 0.048 | 0.087 | 1.609 | 0.108 |
| E3-Accurate work breakdown structure (WBS) | 0.131 | 0.057 | 0.112 | 2.293 | 0.022 |
| B1-Lack of standard processes | 0.269 | 0.057 | 0.246 | 4.731 | 0.000 |
| B2-Vague contract deliverables | 0.015 | 0.048 | 0.013 | 0.305 | 0.760 |
| B3-Unclear project goals | 0.231 | 0.058 | 0.176 | 3.982 | 0.000 |
| B4-Unclear project milestones | −0.031 | 0.050 | −0.031 | −0.620 | 0.536 |
| B5-Disparate control system between owner and contractor | 0.132 | 0.041 | 0.141 | 3.207 | 0.001 |
| B6-Lack of information communication | −0.022 | 0.041 | −0.028 | −0.532 | 0.595 |
Note(s): ADependent Variable: Project Governance