ModelUnstandardized co-efficientsStandardized co-efficientstSig
BStd. errorBeta
1 (Constant)0.2850.387 0.7360.462
E1-Skilled and experienced team members0.2310.0590.2073.9320.000
E2-Explicity defined roles of project team members0.0700.0510.0761.3710.171
E3-Accurate work breakdown structure (WBS)0.0990.0600.0821.6450.101
B1-Lack of standard processes0.2410.0600.2144.0020.000
B2-Vague contract deliverables−0.0180.051−0.016−0.3620.718
B3-Unclear project goals0.2470.0610.1834.0290.000
B4-Unclear project milestones−0.0690.053−0.067−1.3130.190
B5-Disparate control system between owner and contractor0.1360.0440.1413.1240.002
B6-Lack of information communication0.0090.0430.0110.2050.838

Note(s): ADependent Variable: Resource Loaded