Table 1

List of risk factors leading to cost and time overruns in urban rail projects

IDRisk factorsRelated research
R01Sketchy and incomplete designGhosh and Jintanapakanont (2004), Zou and Li (2010), Mittal and Paul (2018), Patil et al. (2019), Tran et al. (2020), Kassa (2020), Feng et al. (2021), Karmarkar et al. (2022) 
R02Slow design approval and appraisal processHan et al. (2009), Tavassolirizi et al. (2020), Mittal and Paul (2018) 
R03Unexpected changes in the design approvedGhosh and Jintanapakanont (2004), Hua et al. (2004), Han et al. (2009), Patil et al. (2019), Tavassolirizi et al. (2020), Abdorahman (2020) 
R04ODA (Official Development Assistance) projects suffering from tight constraints of main sponsorsExperts’ opinion
R05Slowly disbursed project capitalTavassolirizi et al. (2020) 
R06Payment delaysGhosh and Jintanapakanont (2004), Zou and Li (2010), Mittal and Paul (2018), Patil et al. (2019), Tavassolirizi et al. (2020), Abdorahman (2020), Karmarkar et al. (2022) 
R07Exchange rate changeGhosh and Jintanapakanont (2004), Zou and Li (2010), Zhao et al. (2013), Feng et al. (2021), Karmarkar et al. (2022) 
R08Changes in material, labor and machinery costsHua et al. (2004), Lee (2008), Patil et al. (2019), Tran et al. (2020), Feng et al. (2021) 
R09Lack of coordination and support from government agencies at all levelsZou and Li (2010), Tavassolirizi et al. (2020), Mittal and Paul (2018), Patil et al. (2019), Tran et al. (2020) 
R10Interface problems between contractors due to lack of information and consensusTran et al. (2020) 
R11Changes in local policies and regulationsZou and Li (2010), Zhao et al. (2013), Patil et al. (2019), Tavassolirizi et al. (2020), Tran et al. (2020), Feng et al. (2021), Karmarkar et al. (2022) 
R12Lack of standards for design, construction and verification for new projects first implementedExperts’ opinion
R13Lack of mechanisms and regulations for managing EPC (engineering, procurement and construction) contract typeExperts’ opinion
R14Delays during the bidding and contractor selection from the project management unitTran et al. (2020) 
R15The project management unit’s lack capacity and experience in managing and operating complex projectsTran et al. (2020), Zhao et al. (2013), Kassa (2020) 
R16Delays in decision regarding contract changes and project adjustments from the project management unitGhosh and Jintanapakanont (2004), Tran et al. (2020) 
R17Consultants’ shortcomings during project quality supervisionTran et al. (2020) 
R18Errors, accidents and work problems at construction site due to contractors’ poor managementGhosh and Jintanapakanont (2004), Mittal and Paul (2018), Tran et al. (2020), Abdorahman (2020), Karmarkar et al. (2022) 
R19Delays in making and approving dossiers regarding plan, design, quality, acceptance documentsTavassolirizi et al. (2020), Tran et al. (2020), Abdorahman (2020), Karmarkar et al. (2022) 
R20Changes in project scopeGhosh and Jintanapakanont (2004), Hua et al. (2004), Lee (2008), Mittal and Paul (2018), Patil et al. (2019), Abdorahman (2020), Kassa (2020), Karmarkar et al. (2022) 
R21Lack of raw materials and new equipment necessitated importationTavassolirizi et al. (2020), Mittal and Paul (2018), Patil et al. (2019), Kassa (2020), Karmarkar et al. (2022) 
R22Obstacles regarding heavy traffic obstruct and the limitation of construction siteMittal and Paul (2018), Patil et al. (2019), Karmarkar et al. (2022) 
R23Lack of skilled labor and top tier professionals in field requiredHan et al. (2009), Tavassolirizi et al. (2020), Mittal and Paul (2018), Abdorahman (2020), Kassa (2020), Karmarkar et al. (2022) 
R24Delays in import and shipping goods and machineries for project implementationZhao et al. (2013), Mittal and Paul (2018) 
R25Complicated construction technologyExperts’ opinion
R26Slow land compensation and construction site clearanceZou and Li (2010), Tavassolirizi et al. (2020), Mittal and Paul (2018), Patil et al. (2019), Tran et al. (2020), Han et al. (2009), Kassa (2020), Karmarkar et al. (2022) 
R27Difficulties in relocating and protecting existing works required from local governmentsMittal and Paul (2018), Patil et al. (2019), Tran et al. (2020), Karmarkar et al. (2022) 
R28Litigation and disputes between partiesGhosh and Jintanapakanont (2004), Hua et al. (2004), Han et al. (2009), Zou and Li (2010), Zhao et al. (2013), Mittal and Paul (2018), Patil et al. (2019), Abdorahman (2020), Kassa (2020), Karmarkar et al. (2022) 
R29Unforeseen geological conditionsGhosh and Jintanapakanont (2004), Lee (2008), Zou and Li (2010), Tavassolirizi et al. (2020), Mittal and Paul (2018), Tran et al. (2020), Han et al. (2009), Abdorahman (2020), Kassa (2020), Feng et al. (2021), Karmarkar et al. (2022) 
R30Interruption of construction and associated work volume verification due to epidemicExperts’ opinion

Source(s): Table by authors