Responses to the extent in which each of the following factors influence the construction supply chain management
| Survey items – C5 | To no extent | Small extent | Moderate extent | Large extent | Very large extent | Total | |
|---|---|---|---|---|---|---|---|
| C5.1 Identification of supply chain risks in the conceptualisation stage of a project | Count | 0 | 2 | 20 | 101 | 82 | 205 |
| Row N % | 0.0% | 1.0% | 9.8% | 49.3% | 40.0% | 100.0% | |
| C5.2 Identification of supply chain risks in the planning stage of a project | Count | 0 | 3 | 19 | 103 | 80 | 205 |
| Row N % | 0.0% | 1.5% | 9.3% | 50.2% | 39.0% | 100.0% | |
| C5.3 Identification of supply chain risks in the execution stage | Count | 0 | 5 | 37 | 96 | 67 | 205 |
| Row N % | 0.0% | 2.4% | 18.0% | 46.8% | 32.7% | 100.0% | |
| C5.4 The proximity of suppliers | Count | 3 | 7 | 46 | 121 | 28 | 205 |
| Row N % | 1.5% | 3.4% | 22.4% | 59.0% | 13.7% | 100.0% | |
| C5.5 The proximity of vendors | Count | 2 | 12 | 65 | 97 | 29 | 205 |
| Row N % | 1.0% | 5.9% | 31.7% | 47.3% | 14.1% | 100.0% | |
| C5.6 The proximity of customers | Count | 3 | 21 | 68 | 98 | 15 | 205 |
| Row N % | 1.5% | 10.2% | 33.2% | 47.8% | 7.3% | 100.0% | |
| C5.7 The reconciliation of material flows of the sub-contractors with the contractors | Count | 0 | 9 | 51 | 112 | 33 | 205 |
| Row N % | 0.0% | 4.4% | 24.9% | 54.6% | 16.1% | 100.0% | |
| C5.8 Delivery reliability | Count | 0 | 3 | 29 | 132 | 41 | 205 |
| Row N % | 0.0% | 1.5% | 14.1% | 64.4% | 20.0% | 100.0% | |
| C5.9 Construction supply chain management coordination | Count | 1 | 5 | 17 | 106 | 76 | 205 |
| Row N % | 0.5% | 2.4% | 8.3% | 51.7% | 37.1% | 100.0% | |
| C5.10 Timely procurement | Count | 1 | 2 | 27 | 121 | 54 | 205 |
| Row N % | 0.5% | 1.0% | 13.2% | 59.0% | 26.3% | 100.0% | |
| C5.11 Balanced demands | Count | 0 | 2 | 39 | 122 | 42 | 205 |
| Row N % | 0.0% | 1.0% | 19.0% | 59.5% | 20.5% | 100.0% | |
| C5.12 Inventories | Count | 0 | 7 | 47 | 109 | 42 | 205 |
| Row N % | 0.0% | 3.4% | 22.9% | 53.2% | 20.5% | 100.0% | |
| C5.13 Production capabilities | Count | 1 | 3 | 29 | 121 | 51 | 205 |
| Row N % | 0.5% | 1.5% | 14.1% | 59.0% | 24.9% | 100.0% | |
| C5.14 Funding schedule | Count | 0 | 2 | 14 | 103 | 86 | 205 |
| Row N % | 0.0% | 1.0% | 6.8% | 50.2% | 42.0% | 100.0% | |
| C5.15 Predictable delivery | Count | 0 | 4 | 22 | 130 | 49 | 205 |
| Row N % | 0.0% | 2.0% | 10.7% | 63.4% | 23.9% | 100.0% | |
| Survey items – C5 | To no extent | Small extent | Moderate extent | Large extent | Very large extent | Total | |
|---|---|---|---|---|---|---|---|
| C5.1 Identification of supply chain risks in the conceptualisation stage of a project | Count | 0 | 2 | 20 | 101 | 82 | 205 |
| Row N % | 0.0% | 1.0% | 9.8% | 49.3% | 40.0% | 100.0% | |
| C5.2 Identification of supply chain risks in the planning stage of a project | Count | 0 | 3 | 19 | 103 | 80 | 205 |
| Row N % | 0.0% | 1.5% | 9.3% | 50.2% | 39.0% | 100.0% | |
| C5.3 Identification of supply chain risks in the execution stage | Count | 0 | 5 | 37 | 96 | 67 | 205 |
| Row N % | 0.0% | 2.4% | 18.0% | 46.8% | 32.7% | 100.0% | |
| C5.4 The proximity of suppliers | Count | 3 | 7 | 46 | 121 | 28 | 205 |
| Row N % | 1.5% | 3.4% | 22.4% | 59.0% | 13.7% | 100.0% | |
| C5.5 The proximity of vendors | Count | 2 | 12 | 65 | 97 | 29 | 205 |
| Row N % | 1.0% | 5.9% | 31.7% | 47.3% | 14.1% | 100.0% | |
| C5.6 The proximity of customers | Count | 3 | 21 | 68 | 98 | 15 | 205 |
| Row N % | 1.5% | 10.2% | 33.2% | 47.8% | 7.3% | 100.0% | |
| C5.7 The reconciliation of material flows of the sub-contractors with the contractors | Count | 0 | 9 | 51 | 112 | 33 | 205 |
| Row N % | 0.0% | 4.4% | 24.9% | 54.6% | 16.1% | 100.0% | |
| C5.8 Delivery reliability | Count | 0 | 3 | 29 | 132 | 41 | 205 |
| Row N % | 0.0% | 1.5% | 14.1% | 64.4% | 20.0% | 100.0% | |
| C5.9 Construction supply chain management coordination | Count | 1 | 5 | 17 | 106 | 76 | 205 |
| Row N % | 0.5% | 2.4% | 8.3% | 51.7% | 37.1% | 100.0% | |
| C5.10 Timely procurement | Count | 1 | 2 | 27 | 121 | 54 | 205 |
| Row N % | 0.5% | 1.0% | 13.2% | 59.0% | 26.3% | 100.0% | |
| C5.11 Balanced demands | Count | 0 | 2 | 39 | 122 | 42 | 205 |
| Row N % | 0.0% | 1.0% | 19.0% | 59.5% | 20.5% | 100.0% | |
| C5.12 Inventories | Count | 0 | 7 | 47 | 109 | 42 | 205 |
| Row N % | 0.0% | 3.4% | 22.9% | 53.2% | 20.5% | 100.0% | |
| C5.13 Production capabilities | Count | 1 | 3 | 29 | 121 | 51 | 205 |
| Row N % | 0.5% | 1.5% | 14.1% | 59.0% | 24.9% | 100.0% | |
| C5.14 Funding schedule | Count | 0 | 2 | 14 | 103 | 86 | 205 |
| Row N % | 0.0% | 1.0% | 6.8% | 50.2% | 42.0% | 100.0% | |
| C5.15 Predictable delivery | Count | 0 | 4 | 22 | 130 | 49 | 205 |
| Row N % | 0.0% | 2.0% | 10.7% | 63.4% | 23.9% | 100.0% | |