The costs and revenues of the proposed waste-to-energy facility under the FiT
| Revenues | Costs | ||||
|---|---|---|---|---|---|
| Electricity to the Grid | 1.4 L.E per kwh | $15,723,077 per year | Investment Costs | $644 per ton | $205,100,000 In the Construction year |
| Metal Recovery | $250 per ton | $1,592,725 per year | Operating and Maintenance Costs | $33.1 per ton | $10,500,000 per year |
| Bottom Ash | $6 per ton | $109,898 per year | |||
| Total Revenues | $17,425,700 | ||||
| Revenues | Costs | ||||
|---|---|---|---|---|---|
| 1.4 L.E per kwh | $15,723,077 per year | $644 per ton | $205,100,000 | ||
| $250 per ton | $1,592,725 per year | $33.1 per ton | $10,500,000 per year | ||
| $6 per ton | $109,898 per year | ||||
Source(s): Table developed by the authors