Overview of interviews and informants
| Function categorization | Number of interviews | Informant IDs | Duration (hours) |
|---|---|---|---|
| Technical management | 5 | 1, 2, 6, 12, 15 | 4.0 |
| Manufacturing planning and control | 3 | 5, 7, 8 | 2.5 |
| Manufacturing team leaders | 4 | 4, 9, 16, 18 | 3.6 |
| Quality management | 2 | 3, 17 | 1.7 |
| Business adm., controllers, HR | 4 | 10, 11a, 11b, 13, 14 | 3.0 |
| Tot. 5 Function categories | Tot. 18 interviews | Tot. 19 informants | Tot. 14.8 h |
| Function categorization | Number of interviews | Informant IDs | Duration (hours) |
|---|---|---|---|
| 5 | 1, 2, 6, 12, 15 | 4.0 | |
| 3 | 5, 7, 8 | 2.5 | |
| 4 | 4, 9, 16, 18 | 3.6 | |
| 2 | 3, 17 | 1.7 | |
| 4 | 10, 11a, 11b, 13, 14 | 3.0 | |
Source(s): Created by the authors