Factors affecting dynamic scheduling, code, polarity and author count
| S/N | Factors category | Code | Factors influencing dynamic scheduling | Effect on DS | Authors count |
|---|---|---|---|---|---|
| 1 | Cultural | CE-P01 | Cultural heritage management | Positive | 1 |
| 2 | CE-P02 | Cultural identity and togetherness | Positive | 1 | |
| 3 | CE-P03 | Diverse cultural heritage | Positive | 1 | |
| 4 | CE-P04 | Place attachment | Positive | 1 | |
| 5 | Design | DN-N01 | complexity of construction site layouts | Negative | 2 |
| 6 | DN-N02 | Incomplete drawings and specifications/incomplete project information | Negative | 1 | |
| 7 | DN-N03 | design parameters | Negative | 1 | |
| 8 | DN-N04 | canyon aspect ratio | Negative | 1 | |
| 9 | DN-N05 | window properties | Negative | 1 | |
| 10 | DN-N06 | albedo | Negative | 1 | |
| 11 | DN-N07 | Design error | Negative | 1 | |
| 12 | DN-P01 | Computational design | Positive | 1 | |
| 13 | DN-P02 | construction site layout design | Positive | 1 | |
| 14 | Economic/Legal | EC-N01 | increased transport costs | Negative | 2 |
| 15 | EC-N02 | Shortage of construction materials in the market | Negative | 1 | |
| 16 | EC-N03 | Changes in government regulations/laws | Negative | 1 | |
| 17 | EC-N04 | Legal disputes between various parties | Negative | 1 | |
| 18 | EC-N05 | Delay in payment by the owner | Negative | 1 | |
| 19 | EC-N06 | lack of work permits | Negative | 1 | |
| 20 | EC-N07 | dynamic economic emission dispatch problems | Negative | 1 | |
| 21 | EC-P01 | Climate adaptation policy | Positive | 1 | |
| 22 | EC-P02 | Climate policy | Positive | 1 | |
| 23 | EC-P03 | Economic benefits | Positive | 1 | |
| 24 | EC-P04 | Economic diversification | Positive | 1 | |
| 25 | EC-P05 | National cultural heritage policy | Positive | 1 | |
| 26 | EC-P06 | construction cost | Positive | 1 | |
| 27 | EC-P07 | construction investment | Positive | 1 | |
| 28 | Environment | ET-N01 | Inaccessibility of site/Required accessible workspaces/Indoor space of building/limited site space/limited workspace | Negative | 5 |
| 29 | ET-N02 | Effect of subsurface conditions (water table, hard rock)/Geotechnical data issues/natural geological conditions | Negative | 3 | |
| 30 | ET-N03 | Dynamic changes of the internal space of a building in the operation and maintenance stage/changes in spatial state on construction sites | Negative | 2 | |
| 31 | ET-N04 | temporary facilities allocation/inconvenient location of the storage area | Negative | 2 | |
| 32 | ET-N05 | topographic changes over time/Construction site steep slopes | Negative | 2 | |
| 33 | ET-N06 | Events issues/different dynamic disturbance events | Negative | 2 | |
| 34 | ET-N07 | Ambient conditions | Negative | 1 | |
| 35 | ET-N08 | Generation and allocation of workspaces | Negative | 1 | |
| 36 | ET-N09 | Keeping enough cool air in the plenums | Negative | 1 | |
| 37 | ET-N10 | Lack of explicit feedback of airflow and temperatures | Negative | 1 | |
| 38 | ET-N11 | Site congestions identification | Negative | 1 | |
| 39 | ET-N12 | Strict space pressure control | Negative | 1 | |
| 40 | ET-N13 | Traffic congestion | Negative | 1 | |
| 41 | ET-N14 | Unavailability of utilities at site (water, electricity) | Negative | 1 | |
| 42 | ET-N15 | Curse-of-dimensionality for large-scale instances | Negative | 1 | |
| 43 | ET-N16 | Detection of physical conflicts between the site workspaces | Negative | 1 | |
| 44 | ET-N17 | construction noise | Negative | 1 | |
| 45 | ET-N18 | limitation of autonomous excavators' movement in a construction site | Negative | 1 | |
| 46 | ET-N19 | uncontrolled environmental conditions | Negative | 1 | |
| 47 | ET-N20 | Disaster issues | Negative | 1 | |
| 48 | ET-N21 | Pandemic issues | Negative | 1 | |
| 49 | ET-N22 | Crowded environment | Negative | 1 | |
| 50 | ET-N23 | greenhouse gas (GHG) emissions | Negative | 1 | |
| 51 | ET-N24 | acidifying gas emissions | Negative | 1 | |
| 52 | ET-N25 | construction sector emissions | Negative | 1 | |
| 53 | ET-N26 | urbanisation rate | Negative | 1 | |
| 54 | ET-N27 | pollution load | Negative | 1 | |
| 55 | ET-N28 | land-use change | Negative | 1 | |
| 56 | ET-N29 | complex and changeable environment | Negative | 1 | |
| 57 | ET-P01 | Spatial development/Assembly workspace/Logistics workspace/Production workspace/Spatial information | Positive | 5 | |
| 58 | ET-P02 | Reduced air pollution | Positive | 1 | |
| 59 | ET-P03 | Reduced noise | Positive | 1 | |
| 60 | ET-P04 | Reduced vibration | Positive | 1 | |
| 61 | ET-P05 | Ensure that the facilities do not overlap with one another or with the buildings | Positive | 1 | |
| 62 | ET-P06 | Environmental management | Positive | 1 | |
| 63 | ET-P07 | Reducing carbon footprint by retrofitting historic buildings | Positive | 1 | |
| 64 | ET-P08 | Reusing existing materials will help to achieve decarbonisation | Positive | 1 | |
| 65 | ET-P09 | Use of renewable energy | Positive | 1 | |
| 66 | ET-P10 | sustainable utilisation of urban underground space | Positive | 1 | |
| 67 | ET-P11 | topological structure | Positive | 1 | |
| 68 | ET-P12 | appropriate site locations | Positive | 1 | |
| 69 | ET-P13 | Relocation of a construction site | Positive | 1 | |
| 70 | Management | MT-N01 | Logistics system | Negative | 1 |
| 71 | MT-N02 | Poor interactivity | Negative | 1 | |
| 72 | MT-N03 | Poor interoperability | Negative | 1 | |
| 73 | MT-N04 | Problems in shipment and site inventory | Negative | 1 | |
| 74 | MT-N05 | untimely and inaccurate transportation | Negative | 1 | |
| 75 | MT-N06 | uncompleted quality control | Negative | 1 | |
| 76 | MT-P01 | Construction site layout | Positive | 1 | |
| 77 | MT-P02 | ensemble construction methods | Positive | 1 | |
| 78 | MT-P03 | lean solutions | Positive | 1 | |
| 79 | MT-P04 | act fast on decision-making and collaborative working using available information and knowledge | Positive | 1 | |
| 80 | MT-P05 | Modular Construction | Positive | 1 | |
| 81 | Planning/Scheduling | SG-N01 | Detection of schedule conflict, which means the detection of a temporal overlap between tasks | Negative | 1 |
| 82 | SG-N02 | stochastic activity durations | Negative | 1 | |
| 83 | SG-N03 | schedule changes of other related operations | Negative | 1 | |
| 84 | SG-N04 | uncertain time of land acquisition | Negative | 1 | |
| 85 | SG-N05 | Job Scheduling Problem | Negative | 1 | |
| 86 | SG-N06 | Poor planning | Negative | 1 | |
| 87 | SG-N07 | increase in non-productive time | Negative | 1 | |
| 88 | SG-N08 | resource-constrained project scheduling problem (RCPSP) | Negative | 1 | |
| 89 | SG-P01 | maximum slack priority rule (shortest latest start time) | Positive | 1 | |
| 90 | SG-P02 | Applications of resource-constrained project scheduling | Positive | 1 | |
| 91 | SG-P03 | Hoisting facility layout planning | Positive | 1 | |
| 92 | SG-P04 | BIM-based construction schedules | Positive | 1 | |
| 93 | SG-P05 | baseline schedule | Positive | 1 | |
| 94 | SG-P06 | periodic progress data | Positive | 1 | |
| 95 | SG-P07 | top-down control methodology | Positive | 1 | |
| 96 | SG-P08 | risk analysis | Positive | 1 | |
| 97 | SG-P09 | project control | Positive | 1 | |
| 98 | SG-P10 | Top-down control strategy | Positive | 1 | |
| 99 | SG-P11 | Bottom-up control strategy | Positive | 1 | |
| 100 | SG-P12 | Crashing corrective actions | Positive | 1 | |
| 101 | SG-P13 | Variability corrective actions | Positive | 1 | |
| 102 | SG-P14 | Fast-tracking corrective actions | Positive | 1 | |
| 103 | SG-P15 | Sensitive activity selection | Positive | 1 | |
| 104 | SG-P16 | Critical activity selection | Positive | 1 | |
| 105 | SG-P17 | Analytical sensitivity | Positive | 1 | |
| 106 | SG-P18 | Simulation sensitivity | Positive | 1 | |
| 107 | SG-P19 | Analysis sensitivity | Positive | 1 | |
| 108 | SG-P20 | Threshold methodology | Positive | 1 | |
| 109 | SG-P21 | Set methodology | Positive | 1 | |
| 110 | SG-P22 | serial/parallel indicator network topology | Positive | 1 | |
| 111 | SG-P23 | spatial planning | Positive | 1 | |
| 112 | Resources | RC-N01 | Resource unavailability/resource constraints/unstable resource availability | Negative | 7 |
| 113 | RC-N02 | Unavailability of materials/unavailability of prefabricated products/Material availability | Negative | 2 | |
| 114 | RC-N03 | Unavailability of equipment and tools/Equipment breakdown/Equipment shortage | Negative | 3 | |
| 115 | RC-N04 | time-varying resource demands | Negative | 1 | |
| 116 | RC-N05 | shortage of temporary structures | Negative | 1 | |
| 117 | RC-N06 | unskilled operators | Negative | 1 | |
| 118 | RC-N07 | Project productivity issue | Negative | 1 | |
| 119 | RC-N08 | inefficient use of resources | Negative | 1 | |
| 120 | RC-N09 | spatial variability of human activities | Negative | 1 | |
| 121 | RC-N10 | equipment assembly process | Negative | 1 | |
| 122 | RC-P01 | efficient construction productivity | Positive | 1 | |
| 123 | RC-P02 | dynamic facilities allocation | Positive | 1 | |
| 124 | RC-P03 | cross-domain knowledge | Positive | 1 | |
| 125 | RC-P04 | dynamic distribution of labour resources | Positive | 1 | |
| 126 | Safety | SY-N01 | Accidents during construction | Negative | 1 |
| 127 | SY-N02 | unidentified safety and hazard issues | Negative | 1 | |
| 128 | SY-P01 | construction safety | Positive | 1 | |
| 129 | SY-P02 | enhancing safety in the pre-construction phase | Positive | 1 | |
| 130 | SY-P03 | noise barriers | Positive | 1 | |
| 131 | Social and Human | SL-N01 | Deficiency for interior personnel to understand the indoor layout | Negative | 1 |
| 132 | SL-N02 | Delay in giving instructions | Negative | 1 | |
| 133 | SL-N03 | Human factors | Negative | 1 | |
| 134 | SL-N04 | Inadequate experience of consultant | Negative | 1 | |
| 135 | SL-N05 | Poor communication of owner with contractor | Negative | 1 | |
| 136 | SL-N06 | Risk aversion in the delivery and operation of buildings | Negative | 1 | |
| 137 | SL-N07 | Slow decision-making by the owner | Negative | 1 | |
| 138 | SL-N08 | Stakeholder’s loss aversion | Negative | 1 | |
| 139 | SL-N09 | Suspension of work by owner | Negative | 1 | |
| 140 | SL-P01 | Social benefits | Positive | 1 | |
| 141 | SL-P02 | Social cohesion and integrity | Positive | 1 | |
| 142 | SL-P03 | parallel rule collaboration (PRC) | Positive | 1 | |
| 143 | Technology | TY-N01 | incomplete BIM models | Negative | 1 |
| 144 | TY-P01 | Building information modelling (BIM)/Building Information Modelling (BIM) 5D construction duration-cost optimisation model/BIM-based integrated scheduling methodology for building projects under resource constraints/BIM-based rule-checking systems/Linked-data and constraint-checking/Linked-data based constraint-checking architecture/Ontology for linked-data based dynamic constraint-checking | Positive | 10 | |
| 145 | TY-P02 | Modelling scheduling constraints using Shapes Constraint Language (SHACL)/Prototype web application/Processing web application/Storage/Data/Prototype evaluation/automatic progress tracking technology | Positive | 7 | |
| 146 | TY-P03 | optimisation of robot motion path planning/Multi-construction robots/Tracking tasks/robot kinematic optimisation principle/mobile platform planning/path control strategy | Positive | 1 | |
| 147 | TY-P04 | Dynamic scheduling coordination technology | Positive | 1 | |
| 148 | TY-P05 | Mobile robots | Positive | 1 | |
| 149 | TY-P06 | The multi-stage stochastic programming model for identifying the optimal supply chain configuration | Positive | 1 | |
| 150 | TY-P07 | Navigating spatial data dynamically | Positive | 1 | |
| 151 | TY-P08 | reinforcement learning model | Positive | 1 | |
| 152 | TY-P09 | earthwork allocation planning | Positive | 1 | |
| 153 | TY-P10 | ant colony optimisation | Positive | 1 | |
| 154 | TY-P11 | network’s reliability | Positive | 1 | |
| 155 | TY-P12 | Dynamic programming algorithm | Positive | 1 | |
| 156 | TY-P13 | Genetic algorithm for assembly sequence planning in precast concrete buildings | Positive | 1 | |
| 157 | TY-P14 | dynamic planning model (DPM) using Digital Twin | Positive | 1 | |
| 158 | TY-P15 | optimisation of the task planning algorithm | Positive | 1 | |
| 159 | TY-P16 | dynamic planning optimisation model using a Genetic Algorithm | Positive | 1 | |
| 160 | TY-P17 | input-adaptive particle swarm optimisation (iRC-APSO) algorithm | Positive | 1 | |
| 161 | TY-P18 | heuristic algorithms | Positive | 1 | |
| 162 | TY-P19 | intelligent algorithms | Positive | 1 | |
| 163 | TY-P20 | graph-based model | Positive | 1 | |
| 164 | TY-P21 | Binary Pareto-Optimal Particle Swarm Optimisation (BP-PSO) algorithm | Positive | 1 | |
| 165 | TY-P22 | Holonic Management System (HMS) | Positive | 1 | |
| 166 | TY-P23 | Discrete event simulation | Positive | 1 | |
| 167 | TY-P24 | system dynamics | Positive | 1 | |
| 168 | TY-P25 | on-line planning | Positive | 1 | |
| 169 | TY-P26 | linked-data-based constraint-checking (LDCC) method | Positive | 1 | |
| 170 | TY-P27 | Geospatial information system (GIS) | Positive | 1 | |
| 171 | TY-P28 | Data mining (DM) | Positive | 1 | |
| 172 | TY-P29 | genetic algorithm (GA) | Positive | 1 | |
| 173 | TY-P30 | new intelligent environmental evaluation method to optimally and dynamically schedule the resource, production and inventory activities | Positive | 1 | |
| 174 | Weather/Climate | WR-N01 | Adverse weather condition | Negative | 5 |
| 175 | WR-N02 | Climate change | Negative | 2 | |
| 176 | WR-P01 | Climate change mitigation and adaptation | Positive | 1 |
| S/N | Factors category | Code | Factors influencing dynamic scheduling | Effect on DS | Authors count |
|---|---|---|---|---|---|
| 1 | Cultural | CE-P01 | Cultural heritage management | Positive | 1 |
| 2 | CE-P02 | Cultural identity and togetherness | Positive | 1 | |
| 3 | CE-P03 | Diverse cultural heritage | Positive | 1 | |
| 4 | CE-P04 | Place attachment | Positive | 1 | |
| 5 | Design | DN-N01 | complexity of construction site layouts | Negative | 2 |
| 6 | DN-N02 | Incomplete drawings and specifications/incomplete project information | Negative | 1 | |
| 7 | DN-N03 | design parameters | Negative | 1 | |
| 8 | DN-N04 | canyon aspect ratio | Negative | 1 | |
| 9 | DN-N05 | window properties | Negative | 1 | |
| 10 | DN-N06 | albedo | Negative | 1 | |
| 11 | DN-N07 | Design error | Negative | 1 | |
| 12 | DN-P01 | Computational design | Positive | 1 | |
| 13 | DN-P02 | construction site layout design | Positive | 1 | |
| 14 | Economic/Legal | EC-N01 | increased transport costs | Negative | 2 |
| 15 | EC-N02 | Shortage of construction materials in the market | Negative | 1 | |
| 16 | EC-N03 | Changes in government regulations/laws | Negative | 1 | |
| 17 | EC-N04 | Legal disputes between various parties | Negative | 1 | |
| 18 | EC-N05 | Delay in payment by the owner | Negative | 1 | |
| 19 | EC-N06 | lack of work permits | Negative | 1 | |
| 20 | EC-N07 | dynamic economic emission dispatch problems | Negative | 1 | |
| 21 | EC-P01 | Climate adaptation policy | Positive | 1 | |
| 22 | EC-P02 | Climate policy | Positive | 1 | |
| 23 | EC-P03 | Economic benefits | Positive | 1 | |
| 24 | EC-P04 | Economic diversification | Positive | 1 | |
| 25 | EC-P05 | National cultural heritage policy | Positive | 1 | |
| 26 | EC-P06 | construction cost | Positive | 1 | |
| 27 | EC-P07 | construction investment | Positive | 1 | |
| 28 | Environment | ET-N01 | Inaccessibility of site/Required accessible workspaces/Indoor space of building/limited site space/limited workspace | Negative | 5 |
| 29 | ET-N02 | Effect of subsurface conditions (water table, hard rock)/Geotechnical data issues/natural geological conditions | Negative | 3 | |
| 30 | ET-N03 | Dynamic changes of the internal space of a building in the operation and maintenance stage/changes in spatial state on construction sites | Negative | 2 | |
| 31 | ET-N04 | temporary facilities allocation/inconvenient location of the storage area | Negative | 2 | |
| 32 | ET-N05 | topographic changes over time/Construction site steep slopes | Negative | 2 | |
| 33 | ET-N06 | Events issues/different dynamic disturbance events | Negative | 2 | |
| 34 | ET-N07 | Ambient conditions | Negative | 1 | |
| 35 | ET-N08 | Generation and allocation of workspaces | Negative | 1 | |
| 36 | ET-N09 | Keeping enough cool air in the plenums | Negative | 1 | |
| 37 | ET-N10 | Lack of explicit feedback of airflow and temperatures | Negative | 1 | |
| 38 | ET-N11 | Site congestions identification | Negative | 1 | |
| 39 | ET-N12 | Strict space pressure control | Negative | 1 | |
| 40 | ET-N13 | Traffic congestion | Negative | 1 | |
| 41 | ET-N14 | Unavailability of utilities at site (water, electricity) | Negative | 1 | |
| 42 | ET-N15 | Curse-of-dimensionality for large-scale instances | Negative | 1 | |
| 43 | ET-N16 | Detection of physical conflicts between the site workspaces | Negative | 1 | |
| 44 | ET-N17 | construction noise | Negative | 1 | |
| 45 | ET-N18 | limitation of autonomous excavators' movement in a construction site | Negative | 1 | |
| 46 | ET-N19 | uncontrolled environmental conditions | Negative | 1 | |
| 47 | ET-N20 | Disaster issues | Negative | 1 | |
| 48 | ET-N21 | Pandemic issues | Negative | 1 | |
| 49 | ET-N22 | Crowded environment | Negative | 1 | |
| 50 | ET-N23 | greenhouse gas (GHG) emissions | Negative | 1 | |
| 51 | ET-N24 | acidifying gas emissions | Negative | 1 | |
| 52 | ET-N25 | construction sector emissions | Negative | 1 | |
| 53 | ET-N26 | urbanisation rate | Negative | 1 | |
| 54 | ET-N27 | pollution load | Negative | 1 | |
| 55 | ET-N28 | land-use change | Negative | 1 | |
| 56 | ET-N29 | complex and changeable environment | Negative | 1 | |
| 57 | ET-P01 | Spatial development/Assembly workspace/Logistics workspace/Production workspace/Spatial information | Positive | 5 | |
| 58 | ET-P02 | Reduced air pollution | Positive | 1 | |
| 59 | ET-P03 | Reduced noise | Positive | 1 | |
| 60 | ET-P04 | Reduced vibration | Positive | 1 | |
| 61 | ET-P05 | Ensure that the facilities do not overlap with one another or with the buildings | Positive | 1 | |
| 62 | ET-P06 | Environmental management | Positive | 1 | |
| 63 | ET-P07 | Reducing carbon footprint by retrofitting historic buildings | Positive | 1 | |
| 64 | ET-P08 | Reusing existing materials will help to achieve decarbonisation | Positive | 1 | |
| 65 | ET-P09 | Use of renewable energy | Positive | 1 | |
| 66 | ET-P10 | sustainable utilisation of urban underground space | Positive | 1 | |
| 67 | ET-P11 | topological structure | Positive | 1 | |
| 68 | ET-P12 | appropriate site locations | Positive | 1 | |
| 69 | ET-P13 | Relocation of a construction site | Positive | 1 | |
| 70 | Management | MT-N01 | Logistics system | Negative | 1 |
| 71 | MT-N02 | Poor interactivity | Negative | 1 | |
| 72 | MT-N03 | Poor interoperability | Negative | 1 | |
| 73 | MT-N04 | Problems in shipment and site inventory | Negative | 1 | |
| 74 | MT-N05 | untimely and inaccurate transportation | Negative | 1 | |
| 75 | MT-N06 | uncompleted quality control | Negative | 1 | |
| 76 | MT-P01 | Construction site layout | Positive | 1 | |
| 77 | MT-P02 | ensemble construction methods | Positive | 1 | |
| 78 | MT-P03 | lean solutions | Positive | 1 | |
| 79 | MT-P04 | act fast on decision-making and collaborative working using available information and knowledge | Positive | 1 | |
| 80 | MT-P05 | Modular Construction | Positive | 1 | |
| 81 | Planning/Scheduling | SG-N01 | Detection of schedule conflict, which means the detection of a temporal overlap between tasks | Negative | 1 |
| 82 | SG-N02 | stochastic activity durations | Negative | 1 | |
| 83 | SG-N03 | schedule changes of other related operations | Negative | 1 | |
| 84 | SG-N04 | uncertain time of land acquisition | Negative | 1 | |
| 85 | SG-N05 | Job Scheduling Problem | Negative | 1 | |
| 86 | SG-N06 | Poor planning | Negative | 1 | |
| 87 | SG-N07 | increase in non-productive time | Negative | 1 | |
| 88 | SG-N08 | resource-constrained project scheduling problem (RCPSP) | Negative | 1 | |
| 89 | SG-P01 | maximum slack priority rule (shortest latest start time) | Positive | 1 | |
| 90 | SG-P02 | Applications of resource-constrained project scheduling | Positive | 1 | |
| 91 | SG-P03 | Hoisting facility layout planning | Positive | 1 | |
| 92 | SG-P04 | BIM-based construction schedules | Positive | 1 | |
| 93 | SG-P05 | baseline schedule | Positive | 1 | |
| 94 | SG-P06 | periodic progress data | Positive | 1 | |
| 95 | SG-P07 | top-down control methodology | Positive | 1 | |
| 96 | SG-P08 | risk analysis | Positive | 1 | |
| 97 | SG-P09 | project control | Positive | 1 | |
| 98 | SG-P10 | Top-down control strategy | Positive | 1 | |
| 99 | SG-P11 | Bottom-up control strategy | Positive | 1 | |
| 100 | SG-P12 | Crashing corrective actions | Positive | 1 | |
| 101 | SG-P13 | Variability corrective actions | Positive | 1 | |
| 102 | SG-P14 | Fast-tracking corrective actions | Positive | 1 | |
| 103 | SG-P15 | Sensitive activity selection | Positive | 1 | |
| 104 | SG-P16 | Critical activity selection | Positive | 1 | |
| 105 | SG-P17 | Analytical sensitivity | Positive | 1 | |
| 106 | SG-P18 | Simulation sensitivity | Positive | 1 | |
| 107 | SG-P19 | Analysis sensitivity | Positive | 1 | |
| 108 | SG-P20 | Threshold methodology | Positive | 1 | |
| 109 | SG-P21 | Set methodology | Positive | 1 | |
| 110 | SG-P22 | serial/parallel indicator network topology | Positive | 1 | |
| 111 | SG-P23 | spatial planning | Positive | 1 | |
| 112 | Resources | RC-N01 | Resource unavailability/resource constraints/unstable resource availability | Negative | 7 |
| 113 | RC-N02 | Unavailability of materials/unavailability of prefabricated products/Material availability | Negative | 2 | |
| 114 | RC-N03 | Unavailability of equipment and tools/Equipment breakdown/Equipment shortage | Negative | 3 | |
| 115 | RC-N04 | time-varying resource demands | Negative | 1 | |
| 116 | RC-N05 | shortage of temporary structures | Negative | 1 | |
| 117 | RC-N06 | unskilled operators | Negative | 1 | |
| 118 | RC-N07 | Project productivity issue | Negative | 1 | |
| 119 | RC-N08 | inefficient use of resources | Negative | 1 | |
| 120 | RC-N09 | spatial variability of human activities | Negative | 1 | |
| 121 | RC-N10 | equipment assembly process | Negative | 1 | |
| 122 | RC-P01 | efficient construction productivity | Positive | 1 | |
| 123 | RC-P02 | dynamic facilities allocation | Positive | 1 | |
| 124 | RC-P03 | cross-domain knowledge | Positive | 1 | |
| 125 | RC-P04 | dynamic distribution of labour resources | Positive | 1 | |
| 126 | Safety | SY-N01 | Accidents during construction | Negative | 1 |
| 127 | SY-N02 | unidentified safety and hazard issues | Negative | 1 | |
| 128 | SY-P01 | construction safety | Positive | 1 | |
| 129 | SY-P02 | enhancing safety in the pre-construction phase | Positive | 1 | |
| 130 | SY-P03 | noise barriers | Positive | 1 | |
| 131 | Social and Human | SL-N01 | Deficiency for interior personnel to understand the indoor layout | Negative | 1 |
| 132 | SL-N02 | Delay in giving instructions | Negative | 1 | |
| 133 | SL-N03 | Human factors | Negative | 1 | |
| 134 | SL-N04 | Inadequate experience of consultant | Negative | 1 | |
| 135 | SL-N05 | Poor communication of owner with contractor | Negative | 1 | |
| 136 | SL-N06 | Risk aversion in the delivery and operation of buildings | Negative | 1 | |
| 137 | SL-N07 | Slow decision-making by the owner | Negative | 1 | |
| 138 | SL-N08 | Stakeholder’s loss aversion | Negative | 1 | |
| 139 | SL-N09 | Suspension of work by owner | Negative | 1 | |
| 140 | SL-P01 | Social benefits | Positive | 1 | |
| 141 | SL-P02 | Social cohesion and integrity | Positive | 1 | |
| 142 | SL-P03 | parallel rule collaboration (PRC) | Positive | 1 | |
| 143 | Technology | TY-N01 | incomplete BIM models | Negative | 1 |
| 144 | TY-P01 | Building information modelling (BIM)/Building Information Modelling (BIM) 5D construction duration-cost optimisation model/BIM-based integrated scheduling methodology for building projects under resource constraints/BIM-based rule-checking systems/Linked-data and constraint-checking/Linked-data based constraint-checking architecture/Ontology for linked-data based dynamic constraint-checking | Positive | 10 | |
| 145 | TY-P02 | Modelling scheduling constraints using Shapes Constraint Language (SHACL)/Prototype web application/Processing web application/Storage/Data/Prototype evaluation/automatic progress tracking technology | Positive | 7 | |
| 146 | TY-P03 | optimisation of robot motion path planning/Multi-construction robots/Tracking tasks/robot kinematic optimisation principle/mobile platform planning/path control strategy | Positive | 1 | |
| 147 | TY-P04 | Dynamic scheduling coordination technology | Positive | 1 | |
| 148 | TY-P05 | Mobile robots | Positive | 1 | |
| 149 | TY-P06 | The multi-stage stochastic programming model for identifying the optimal supply chain configuration | Positive | 1 | |
| 150 | TY-P07 | Navigating spatial data dynamically | Positive | 1 | |
| 151 | TY-P08 | reinforcement learning model | Positive | 1 | |
| 152 | TY-P09 | earthwork allocation planning | Positive | 1 | |
| 153 | TY-P10 | ant colony optimisation | Positive | 1 | |
| 154 | TY-P11 | network’s reliability | Positive | 1 | |
| 155 | TY-P12 | Dynamic programming algorithm | Positive | 1 | |
| 156 | TY-P13 | Genetic algorithm for assembly sequence planning in precast concrete buildings | Positive | 1 | |
| 157 | TY-P14 | dynamic planning model (DPM) using Digital Twin | Positive | 1 | |
| 158 | TY-P15 | optimisation of the task planning algorithm | Positive | 1 | |
| 159 | TY-P16 | dynamic planning optimisation model using a Genetic Algorithm | Positive | 1 | |
| 160 | TY-P17 | input-adaptive particle swarm optimisation (iRC-APSO) algorithm | Positive | 1 | |
| 161 | TY-P18 | heuristic algorithms | Positive | 1 | |
| 162 | TY-P19 | intelligent algorithms | Positive | 1 | |
| 163 | TY-P20 | graph-based model | Positive | 1 | |
| 164 | TY-P21 | Binary Pareto-Optimal Particle Swarm Optimisation (BP-PSO) algorithm | Positive | 1 | |
| 165 | TY-P22 | Holonic Management System (HMS) | Positive | 1 | |
| 166 | TY-P23 | Discrete event simulation | Positive | 1 | |
| 167 | TY-P24 | system dynamics | Positive | 1 | |
| 168 | TY-P25 | on-line planning | Positive | 1 | |
| 169 | TY-P26 | linked-data-based constraint-checking (LDCC) method | Positive | 1 | |
| 170 | TY-P27 | Geospatial information system (GIS) | Positive | 1 | |
| 171 | TY-P28 | Data mining (DM) | Positive | 1 | |
| 172 | TY-P29 | genetic algorithm (GA) | Positive | 1 | |
| 173 | TY-P30 | new intelligent environmental evaluation method to optimally and dynamically schedule the resource, production and inventory activities | Positive | 1 | |
| 174 | Weather/Climate | WR-N01 | Adverse weather condition | Negative | 5 |
| 175 | WR-N02 | Climate change | Negative | 2 | |
| 176 | WR-P01 | Climate change mitigation and adaptation | Positive | 1 |
Source(s): Authors’ own work