Major improvements after the initial configurator launch
| Measure | Before configurator development | After the initial configurator launch | Benefit |
|---|---|---|---|
| Typical preparation time of a work order | 10–30 min | 1–5 min | 88% reduction of average preparation time |
| Number of maintenance activity descriptions | 23,667 non-standardized descriptions | 66 standardized descriptions | 99.7% reduction of variants |
| Measure | Before configurator development | After the initial configurator launch | Benefit |
|---|---|---|---|
| Typical preparation time of a work order | 10–30 min | 1–5 min | 88% reduction of average preparation time |
| Number of maintenance activity descriptions | 23,667 non-standardized descriptions | 66 standardized descriptions | 99.7% reduction of variants |
Source(s): Authors’ own creation/work