Table 6

Effects of the configurator project throughout development

Performance dimensionMeasureResults
Before configurator developmentAfter the initial configurator launch, without continuous improvement enabled by the proposed approachAfter the final configurator launch, with continuous improvement enabled by the proposed approach
User adoptionNumber of active configurator users per monthN/A38
User adoptionConfigured work as a percentage of total work per monthN/A15.3%26.2%
EffectivenessSubsequent material-change rate6.1%0.9%0.6%
EffectivenessPercentage of work orders executed on the first scheduling attempt51.1%73.5%86.1%
EfficiencyConfiguration sessions completed within five minutesN/A84.7%88.2%
EfficiencyPercentage of work orders from pending to processed within 14 days48.5%74.0%72.1%
Process complianceNumber of maintenance activity descriptions23,6676666

Source(s): Authors’ own creation/work