Discussion on Paper 7
-
Published:1979
J. C. Holt, 1979. "Discussion on Paper 7", Overseas contracts: conception to completion
Download citation file:
The first key area for discussion was the problem of finding
the right man for the job. This was an extremely complex
problem due to the conflicting requirements of the various
parties involved in an overseas contract, the employer, the
employee and the client to name but three. The client
would often nominate an individual rather than seek the best
man to fit the specification in the job description. This
desire was perfectly understandable but it could cause
problems. Between the time of tendering and the contract
starting a nominated individual could well have moved on to
another contract.
A prime requirement was for a clear J. y defined job descript-