Lightweight fill in dam remediation – a case study
-
Published:2006
K. M. H. Barr, 2006. "Lightweight fill in dam remediation – a case study", Improvements in reservoir construction, operation and maintenance: Proceedings of the 14th Conference of the British Dam Society at the University of Durham from 6 to 9 September 2006, Henry Hewlett
Download citation file:
Synopsis
The east dam at Millbuies Loch was reconstructed following observations of crest settlement. Investigations found the embankment was founded on a layer of peat. It was concluded that there was significant potential for further settlement of the peat foundation if additional soil were added to make up the freeboard. The embankment was reconstructed using a combination of existing fill and new expanded polystyrene lightweight block fill.
Introduction
Flood Damage and Investigations
Remedial Works Options
Construction
Conclusion