Environmental risks (ERs) are critical to any highway construction project (HCP). One of the main contracting parties responsible for ERs is the contractor. Hence, it has been crucial to look into ways to control ERs in HCPs from the contractor’s perspective. This study aims to investigate how ERs can be managed in HCP in Sri Lanka.

Design/methodology/approach

A quantitative research approach with three rounds of Delphi was used. Statistical techniques were used to analyse and validate the ERs, the parties to whom the risks were to be allocated, and risk management measures identified from the empirical data collection.

Findings

The study reveals the 11 most significant ERs for HCP. Further, the most significant ERs in HCP were mainly found to be the responsibility of contractors in Sri Lanka. Twenty-four most appropriate risk response measures were determined; 13 were found to be common measures that could be used to manage two or more risks, while the remaining 11 were unique to specific risks.

Originality/value

Overall, this research determines the most significant ERs in HCP, the best risk allocation among the parties and appropriate risk-handling strategies and measures for each significant ERs. Additionally, the study addresses the demand for ERs management in HCP.

Licensed re-use rights only
You do not currently have access to this content.
Don't already have an account? Register

Purchased this content as a guest? Enter your email address to restore access.

Pay-Per-View Access
$39.00
Rental

or Create an Account

Close subscription notice
Close access options