Purpose

This paper aims to investigate the operational mechanism, project performance, motives behind, benefits, difficulties and success factors of adopting the guaranteed maximum price (GMP) scheme based on a real‐life case study of Chater House, an international Grade A private office project in Hong Kong.

Design/methodology/approach

The case project was analysed by means of the related project documentation and a series of face‐to‐face interviews with the relevant senior project representatives.

Findings

All the interviewed key project stakeholders perceived that the GMP contract helped achieve competitive price, value for money and superior quality of products as well as provided stronger incentives to innovation and cost saving. The case study revealed that the overall success of this GMP project was underpinned by several key attributes.

Originality/value

The paper provides solid groundwork for client bodies and contracting organisations to develop a best practice framework for implementing successful GMP schemes in future construction.

You do not currently have access to this content.
Don't already have an account? Register

Purchased this content as a guest? Enter your email address to restore access.

Pay-Per-View Access
$41.00
Rental

or Create an Account

Close Modal
Close Modal