Standard value/cost flow models (often referred to as S‐curves) are widely used in cash flow forecasting, particularly at the tender stage. A substantial amount of research has concentrated on improving the accuracy of these curves. Categorizing construction projects into groups and subgroups has helped, but the fact remains that different construction projects possess different profiles of cost flow. This paper is an attempt at assessing the extent of influence of planning and programming the work on the cost flow curves. One real project was used as a case study and four planners were independently asked to produce programmes for executing the project. These programmes were analysed and converted to cost flow curves using one database of productivity and unit cost rates. Results confirmed that the variations in programmes produced less variations in cost flow curves than the errors to be expected from the use of average curves derived from project groups (mean SDY 2.88 compared to previous studies of 5.5, 8.5 and 10.67). The results suggest, taking due account of the limitations of the scope of the study, that further effort at the categorisation of projects into subgroups will result in a reasonable improvement in accuracy.
Article navigation
1 February 2003
Case Report|
February 01 2003
The effects of the variability of project planning on cost commitment curves: a case study
A.P. Kaka;
A.P. Kaka
A.P. Kaka is based at Department of Building Engineering and Surveying, Heriot Watt University, Edinburgh, UK.
Search for other works by this author on:
J. Lewis;
J. Lewis
J. Lewis is based at the School of Architecture and Building Engineering, University of Liverpool, Liverpool, UK
Search for other works by this author on:
H. Petros
H. Petros
H. Petros is based at the School of Architecture and Building Engineering, University of Liverpool, Liverpool, UK
Search for other works by this author on:
Publisher: Emerald Publishing
Online ISSN: 1365-232X
Print ISSN: 0969-9988
© MCB UP Limited
2003
Engineering, Construction and Architectural Management (2003) 10 (1): 15–26.
Citation
Kaka A, Lewis J, Petros H (2003), "The effects of the variability of project planning on cost commitment curves: a case study". Engineering, Construction and Architectural Management, Vol. 10 No. 1 pp. 15–26, doi: https://doi.org/10.1108/09699980310466514
Download citation file:
New and popular articles
Suggested Reading
Resource levelling optimization model considering float loss impact
Engineering, Construction and Architectural Management (July,2018)
Job‐shop Operations Reform: Strategies for Achieving Queueless Work Flow
International Journal of Operations & Production Management (July,1991)
Delay analysis in construction projects with no updated work schedules
Engineering, Construction and Architectural Management (May,2020)
A taxonomy of planning and scheduling methods to support their more efficient use in construction project management
Journal of Engineering, Design and Technology (July,2016)
Estimating the economic value of library benefits
Performance Measurement and Metrics (April,2003)
Related Chapters
A multiple objective approach to assigning classes for an executive MBA program
Applications of Management Science
Chinese Tourists and the Sun: Implications for Designing Experiences
Delivering Tourism Intelligence: From Analysis to Action
A Machine Learning–Based Buffer Estimation for Construction Schedules Under Uncertainty
The Role of Artificial Intelligence Applications in Business
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.