Delays are an endemic feature of the construction industry. Typically, when a delay occurs in a project, the project manager often expedites progress through activity‐crashing with respect to available float and time‐cost relationships. An accelerated schedule is thus obtained either by prescribing overtime working hours or by procuring additional resources or a combination of both. However, excessively prolonged overtime work can generate quality problems, such as rework, and additional resources. With this in mind, there is a need for a model to assist project managers with understanding the complex nature of attaining a trade‐off between overtime working and the procurement of additional resources. Thus, using system dynamics modelling, the effects of prolonged overtime work on project cost and quality are examined. To overcome project delays, several options representing various combinations of prescribing over‐time work and injecting additional resources are analysed. Utility theory is then applied to determine the most appropriate solution for mitigating project delays. The modelling approach offered in this paper should be particularly useful for large projects and for projects on confined sites where potential cost savings and improved quality standards are likely to be the most significant.
Article navigation
1 March 2000
Review Article|
March 01 2000
Effects of overtime work and additional resources on project cost and quality
H. LI;
H. LI
Department of Building and Real Estate, Hong Kong Polytechnic University, Hung Horn, Kowloon, Hong Kong
Search for other works by this author on:
P.E.D. LOVE;
P.E.D. LOVE
School of Architecture and Building, Deakin University, Geelong, Victoria 3217, Australia
Search for other works by this author on:
D.S. DREW
D.S. DREW
Department of Building and Real Estate, Hong Kong Polytechnic University, Hung Horn, Kowloon, Hong Kong
Search for other works by this author on:
Publisher: Emerald Publishing
Online ISSN: 1365-232X
Print ISSN: 0969-9988
© MCB UP Limited
2000
Engineering, Construction and Architectural Management (2000) 7 (3): 211–220.
Citation
LI H, LOVE P, DREW D (2000), "Effects of overtime work and additional resources on project cost and quality". Engineering, Construction and Architectural Management, Vol. 7 No. 3 pp. 211–220, doi: https://doi.org/10.1108/eb021146
Download citation file:
New and popular articles
Suggested Reading
A grey mathematical model for crashing of projects by considering time, cost, quality, risk and law of diminishing returns
Grey Systems: Theory and Application (May,2018)
What is the Iron Triangle, and how has it changed?
International Journal of Managing Projects in Business (April,2018)
Applicability of drywall technologies for disaster-induced housing reconstruction
International Journal of Disaster Resilience in the Built Environment (July,2021)
The propagation of rework benchmark metrics for construction
International Journal of Quality & Reliability Management (October,1999)
Controlling fast-track construction method variables (time, cost and quality)
Infrastructure Asset Management (April,2023)
Related Chapters
Are Operations Management Dimensions Necessary For Firm Performance?: A Necessary Condition Analysis
Amplifying Management Research for the Common Good: Lessons for Curious Individuals and Organizations—Insights From Practitioners in the Field
THE DESIGN AND CONSTRUCTION OF LARGE RCC DAMS
Application of Codes, Design and Regulations: Proceedings of the International Conference held at the University of Dundee, Scotland, UK on 5–7 July 2005
A Readiness Decision Model for Canceling Navy Ship Maintenance Availabilities
Applications of Management Science
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.