Sandwich construction is a relatively simple structural form which offers a high strength-to-weight ratio, this efficiency being exemplified by its widespread use in the aerospace industry. The concept was utilised by the Wolfson Bridge Unit at the University of Dundee in the 1970s, in conjunction with emerging structural adhesive technology, in the form of steel/concrete open sandwich panels for bridge decks. Potential cost savings of the order of 10% in comparison with conventional reinforced concrete were demonstrated. Short- and medium-term proof of the concept was demonstrated as a result of over ten years of research utilising beams, slabs and model bridge decks subject to static, fatigue and sustained loading regimes together with accelerated durability testing. However, before the industry was prepared to accept structural adhesive connections in prime load-bearing connections in new construction, it was recognised that a long trial in an actual bridge structure was required. To this end, Tayside Regional Council agreed to the construction of the 6 m span Wester Duntanlich Bridge in Perthshire in 1984. This paper summarises the early research into open sandwich construction. It then describes the design, construction and load trials on the completed bridge which demonstrated that the technique can be successfully and practically applied to full-scale bridge deck construction. Moreover, its subsequent satisfactory performance in service for 20 years will boost confidence in the potential durability of steel/concrete elements incorporating structural adhesive connections.
Article navigation
June 2005
Research Article|
June 01 2005
Open sandwich bridge deck construction—20 years on
G. C. Mays, BSc, PhD, CEng, FICE, MIStructE, ILTM;
G. C. Mays, BSc, PhD, CEng, FICE, MIStructE, ILTM
Professor of Civil Engineering
Cranfield University and Deputy Principal, Royal Military College of Science, Defence Academy of the UK
Swindon, Wiltshire
Search for other works by this author on:
J. J. Dakers, MSc, CEng, MICE
J. J. Dakers, MSc, CEng, MICE
Senior Engineer
Planning and Transportation, Perth and Kinross Council
Perth, Scotland
Search for other works by this author on:
Publisher: Emerald Publishing
Received:
May 13 2004
Accepted:
January 24 2005
Online ISSN: 1751-7664
Print ISSN: 1478-4637
© 2005 Thomas Telford Ltd
2005
Proceedings of the Institution of Civil Engineers - Bridge Engineering (2005) 158 (2): 81–89.
Article history
Received:
May 13 2004
Accepted:
January 24 2005
Citation
Mays GC, Dakers JJ (2005), "Open sandwich bridge deck construction—20 years on". Proceedings of the Institution of Civil Engineers - Bridge Engineering, Vol. 158 No. 2 pp. 81–89, doi: https://doi.org/10.1680/bren.2005.158.2.81
Download citation file:
Suggested Reading
Analyses of a composite bowstring truss with tension stiffening
Proceedings of the Institution of Civil Engineers - Bridge Engineering (June,2003)
An integral composite bridge of high skew
Proceedings of the Institution of Civil Engineers - Bridge Engineering (December,2003)
Briefing: Innovative design of semi-integral bridges on the new A428
Proceedings of the Institution of Civil Engineers - Bridge Engineering (December,2008)
Design and construction of a launched cable-stayed bridge in China
Proceedings of the Institution of Civil Engineers - Civil Engineering (December,2018)
Examples of cable-stayed bridges designed in Finland
Proceedings of the Institution of Civil Engineers - Bridge Engineering (December,2012)
Related Chapters
USE OF COMPOSITE STRUCTURES IN A BUILDING ABOVE A METRO STATION
Innovations and Developments In Concrete Materials And Construction: Proceedings of the International Conference held at the University of Dundee, Scotland, UK on 9–11 September 2002
Tension cables in suspension bridges. A case of form-finding
Tension Structures: Form and behaviour
Introduction
Bridge Construction Equipment
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.