It is common practice to transport heavy equipment via highway bridges. However, their strength may be insufficient in some situations and at present there are limited solutions applicable to long-span arch bridges. A matching load technique was thus developed by which vehicles with heavy cargo can pass over bridges by carefully placing calculated supplementary loads on the structures instead of applying strengthening. In this work, the relation between the strength of an arch section and the deviation of the thrust line from the neutral axis was analysed. It was found that arches have great reserves of strength if the deviation is minimised. Then, the crucial role that the eccentricity of the thrust on a section plays in current strength calculation algorithms was investigated. As a consequence, a criterion employed to examine qualitatively whether the section has adequate strength was established. Based on these analyses, the matching load technique was developed. The technique was validated on a 130 m long single-span arch bridge and was shown to provide a passage scheme to allow the safe transportation of a 400 t load.
Article navigation
June 2017
Research Article|
February 13 2017
Heavy-cargo passage on arch bridges by matching attached loads
Liu Simeng, MSc;
Liu Simeng, MSc
Associate Professor and PhD Candidate
State Key Laboratory Breeding Base of Mountain Bridge and Tunnel Engineering, Chongqing Jiaotong University, Chongqing, PR China; School of Civil Engineering, Chongqing Jiaotong University, Chongqing, PR China; Cardiff School of Engineering, Cardiff University, Cardiff, UK (corresponding author: simengliu@163.com)
Search for other works by this author on:
Zeng-shun Chen, MSc
Zeng-shun Chen, MSc
PhD Candidate
Department of Civil and Environmental Engineering, The Hong Kong University of Science and Technology, Kowloon, Hong Kong, PR China
Search for other works by this author on:
Publisher: Emerald Publishing
Received:
April 01 2016
Accepted:
November 02 2016
Online ISSN: 1751-7664
Print ISSN: 1478-4637
ICE Publishing: All rights reserved
2017
Proceedings of the Institution of Civil Engineers - Bridge Engineering (2017) 170 (2): 147–156.
Article history
Received:
April 01 2016
Accepted:
November 02 2016
Citation
Simeng L, Chen Z (2017), "Heavy-cargo passage on arch bridges by matching attached loads". Proceedings of the Institution of Civil Engineers - Bridge Engineering, Vol. 170 No. 2 pp. 147–156, doi: https://doi.org/10.1680/jbren.16.00019
Download citation file:
New and popular articles
Suggested Reading
Administration of abnormal vehicles in Ireland
Proceedings of the Institution of Civil Engineers - Bridge Engineering (May,2017)
Recent structural interventions to the eighteenth-century Greatham Bridge, UK
Proceedings of the Institution of Civil Engineers - Engineering History and Heritage (February,2020)
Using anonymous probe-vehicle data for a performance indicator of bridge service
Infrastructure Asset Management (April,2018)
Pendel bearing replacement at A9 Kessock Bridge, Scotland
Proceedings of the Institution of Civil Engineers - Bridge Engineering (December,2007)
Transforming gender relations in Nepal's trail bridge programme: policies and practice
Proceedings of the Institution of Civil Engineers - Transport (December,2019)
Related Chapters
Definitions
Prestressed Concrete Bridges: Design and Construction
Symbols and notation used
Prestressed Concrete Bridges: Design and Construction
General
Prestressed Concrete Bridges: Design and Construction
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.