As a result of leakage along the downstream face of the dam, a section 10 inspection carried out in February 2006 contained a recommendation for a study to be undertaken into the uplift pressures and stability of the concrete gravity dam impounding Llyn Alaw reservoir. The study was subsequently carried out and showed the dam to have inadequate factors of safety for stability during an extreme seismic event. Dwr Cymru Welsh Water awarded a contract to undertake the design and supervision of works to ensure the stability of the structure. The selected method of stabilising the structure was to install 44 no. post-tensioned strand anchors along the length of the dam, vertically through the crest and into the bedrock foundation. This paper describes the stages of the project from feasibility studies and design through to construction of the scheme, which was completed in mid-2013.
Article navigation
September 2013
Research Article|
September 01 2013
Llyn Alaw reservoir post-tensioned anchor installation
Christopher Henryk Vyse, MEng, CEng, MICE, Supervising Engineer
Christopher Henryk Vyse, MEng, CEng, MICE, Supervising Engineer
Geotechnical Engineer, BAM Ritchies, Kilsyth, UK
Search for other works by this author on:
Publisher: Emerald Publishing
Online ISSN: 1756-8404
Print ISSN: 1368-1494
ICE Publishing: All rights reserved
2013
Dams and Reservoirs (2013) 23 (3-4): 134–142.
Citation
Vyse CH (2013), "Llyn Alaw reservoir post-tensioned anchor installation". Dams and Reservoirs, Vol. 23 No. 3-4 pp. 134–142, doi: https://doi.org/10.1680/dare.14.00006
Download citation file:
205
Views
Suggested Reading
Queensferry Crossing, UK: towers, piers and abutments – design and construction
Proceedings of the Institution of Civil Engineers - Bridge Engineering (July,2018)
Numerical analysis of bridge falsework Cuplok systems
Proceedings of the Institution of Civil Engineers - Structures and Buildings (March,2018)
Development over London Underground tunnels: No. 1 Grafton Street
Proceedings of the Institution of Civil Engineers - Structures and Buildings (December,2014)
Benefits of pre-loading temporary props for braced excavations
Geotechnical Research (October,2017)
Temporary propping at Crossrail Paddington station
Geotechnical Research (March,2016)
Related Chapters
Influence of self-compacting concrete on the lateral pressure on formwork
ICE Themes Self-Compacting Concrete
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.