Improvement works to the bywash channel at Slaithwaite reservoir were undertaken in early 2022. An assessment, design and subsequent minor construction works were required to satisfy a measure in the interests of safety relating to the capacity of the bywash channel and its use in the context of an emergency at the dam. The on-site plan was revised and re-certified as a result of changes made including outline designs to enable reservoir inflows to be diverted into the bywash.
Keywords:
dams, barrages & reservoirs
Emerald Publishing Limited: All rights reserved
2024
You do not currently have access to this content.