Power system expansion planning has traditionally been conducted in two phases: optimisation of the future generation system to satisfy forecast demands, followed by that of a complementary transmission system. However, it is now computationally realistic to optimise both aspects simultaneously, even for large and complex systems. At the same time, the range of candidate generation plant types to be considered has widened considerably, with the technical and economic characteristics of wind, solar and biomass plants now having to be compared with those of conventional thermal and hydro plants. It is also becoming increasingly important to take explicit account, within the planning process, of the so-called ‘externalities’ such as emission limits, budget constraints and demand-management measures, in addition to the environmental costs and secondary benefits associated with individual projects. This paper describes the results of a study to demonstrate the feasibility of explicitly considering a range of externalities when mathematically optimising integrated generation and transmission system expansion plans, using the Vietnamese power system as an example.
Article navigation
July 2024
Research Article|
November 09 2023
Incorporating externalities when optimising power system expansion plans Available to Purchase
Timothy Wyatt, BSc
Timothy Wyatt, BSc
AMICE, Power & Water Systems Consultants, Château-d'Oex, Switzerland (timwyatt@pwsc.co.uk)
Search for other works by this author on:
Publisher: Emerald Publishing
Received:
September 15 2022
Accepted:
September 13 2023
Online ISSN: 1751-4231
Print ISSN: 1751-4223
Emerald Publishing Limited: All rights reserved
2023
Proceedings of the Institution of Civil Engineers - Energy (2024) 177 (3): 149–157.
Article history
Received:
September 15 2022
Accepted:
September 13 2023
Citation
Wyatt T (2024), "Incorporating externalities when optimising power system expansion plans". Proceedings of the Institution of Civil Engineers - Energy, Vol. 177 No. 3 pp. 149–157, doi: https://doi.org/10.1680/jener.22.00066
Download citation file:
416
Views
Suggested Reading
Allocating scarce financial resources effectively through function analysis in social housing projects
Built Environment Project and Asset Management (April,2021)
Polarization of universities in the Central Federal District of Russia under reform
Journal of Applied Research in Higher Education (July,2018)
Distributed assembly permutation flow-shop scheduling problem with non-identical factories and considering budget constraints
Kybernetes (January,2022)
Modelling of a hybrid system through differential predicate transition Petri nets model and proof tree
Aircraft Engineering and Aerospace Technology: An International Journal (May,2007)
Minimal positive realizations for discrete‐time systems with state time‐delays
COMPEL (October,2006)
Related Chapters
Reducing Bias in Hierarchical Forecasting
Advances in Business and Management Forecasting
A Methodology for Combining Biased Demand Forecasts
Advances in Business and Management Forecasting
Intercollegiate Athletics Efficiency: A Two-Stage DEA Approach
Applications of Management Science
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.