The project to modify Glenfarg water treatment works by Scottish Water, working in conjunction with its partners Black and Veatch Ltd and Scottish Water Solutions, received a gold award and ‘the ultimate accolade’ of ‘The Most Considerate Site 2009’ at the considerate constructors scheme (CCS) awards. Although previous projects undertaken by Scottish Water have achieved high considerate constructor scores, Glenfarg exceeded previous projects' standards. This level of performance was delivered across the eight categories of the scheme: considerate, environment, cleanliness, good neighbour, respectful, safe, responsible and accountable. The steps the project team took under each of these categories to deliver the project are reviewed in this paper. The paper also outlines some of the challenges the project team faced while delivering such a high level of performance. Furthermore, the paper makes particular reference to ‘soft’ management skills and the development of a project organisational culture that emphasised pride and passion through engagement of the workforce. Overall, the paper presents valuable insights into how performing beyond the CCS requirements remains a dynamic and ongoing activity for all parties involved with the scheme.
Article navigation
March 2011
Research Article|
March 01 2011
Considerate constructors scheme: Glenfarg water treatment works
Mike Murray, MSc, PhD, MCIOB;
Mike Murray, MSc, PhD, MCIOB
1
Lecturer in Construction Management (and part time CCS monitor), Department of Civil Engineering, University of Strathclyde
Glasgow
Scotland
Search for other works by this author on:
Doug Forbes, MEng (Hons), PhD;
Doug Forbes, MEng (Hons), PhD
2
Demonstration Projects Coordinator, Scottish Construction Centre, University of Dundee
Dundee
Scotland
Search for other works by this author on:
Steve Mason, BEng (Hons), Civil Eng
Steve Mason, BEng (Hons), Civil Eng
3
Project Manager, Black & Veatch Ltd
Falkirk
Scotland
Search for other works by this author on:
Publisher: Emerald Publishing
Received:
May 09 2010
Accepted:
October 12 2010
Online ISSN: 1751-7680
Print ISSN: 1478-4629
© 2011 The authors and the Institution of Civil Engineers
2011
Proceedings of the Institution of Civil Engineers - Engineering Sustainability (2011) 164 (1): 49–57.
Article history
Received:
May 09 2010
Accepted:
October 12 2010
Citation
Murray M, Forbes D, Mason S (2011), "Considerate constructors scheme: Glenfarg water treatment works". Proceedings of the Institution of Civil Engineers - Engineering Sustainability, Vol. 164 No. 1 pp. 49–57, doi: https://doi.org/10.1680/ensu.2011.164.1.49
Download citation file:
New and popular articles
Suggested Reading
Sustainability factors affecting local infrastructure project: The case of water resource, water supply, and local market projects in Thai communities
Facilities (February,2015)
Hydraulic conditioning to manage potable water discolouration
Proceedings of the Institution of Civil Engineers - Water Management (October,2017)
Refreshing Kolkata’s 110-year-old, record-breaking elevated water reservoir
Proceedings of the Institution of Civil Engineers - Civil Engineering (April,2019)
Future management of water resources
Proceedings of the Institution of Civil Engineers - Water and Maritime Engineering (September,2002)
Reservoir outlet works for water supply
Proceedings of the Institution of Civil Engineers - Water and Maritime Engineering (December,2000)
Related Chapters
Case studies
Programme Management in Construction
The Role of Operations in a Mega Project
Crossrail Project: Infrastructure Design and Construction
Civil engineering projects
Civil Engineering Procedure
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.