The normal way of dealing with damages for delay in a construction contract is to use a Liquidated and Ascertained Damages clause. Such clauses specify a preset sum to be due to the client for every day, week or month by which the contractor fails to meet the works completion date. However, the greater part of the value of construction work is actually carried out by subcontractors, and there is little or no published evidence as to how their contractual responsibilities for delays are determined and pursued. Theoretically, there are a number of possibilities (none of which is entirely satisfactory to both parties) and the logic and implications of each is discussed. A survey was conducted to discover the methods that are actually used, their incidence, and whether it was possible to relate the different approaches to the attributes of particular subcontractors or to specific situations. The most commonly encountered approach was for subcontract damages to be based upon a proportion of those set under the main contract. Interestingly, this is neither the approach incorporated within industry‐standard subcontract conditions, nor is it the one preferred by subcontractors. Furthermore, this method places considerable risks on the main contractor due to the possibilities of under‐recovery and the creation of secondary risks. This method, indeed all the methods that were encountered, seems to be the result of a rather uneasy compromise between the parties, the outcome of which may be related to their relative bargaining power.
Article navigation
1 August 2005
Research Article|
August 01 2005
Subcontractors’ liability for project delay
David Greenwood;
David Greenwood
School of the Built Environment, Northumbria University, Ellison Place, Newcastle‐upon‐Tyne
Search for other works by this author on:
Keith Hogg;
Keith Hogg
School of the Built Environment, Northumbria University, Ellison Place, Newcastle‐upon‐Tyne
Search for other works by this author on:
Stanley Kan
Stanley Kan
School of the Built Environment, Northumbria University, Ellison Place, Newcastle‐upon‐Tyne
Search for other works by this author on:
Publisher: Emerald Publishing
Online ISSN: 1759-8443
Print ISSN: 1366-4387
© Emerald Group Publishing Limited
2005
Journal of Financial Management of Property and Construction (2005) 10 (2): 107–114.
Citation
Greenwood D, Hogg K, Kan S (2005), "Subcontractors’ liability for project delay". Journal of Financial Management of Property and Construction, Vol. 10 No. 2 pp. 107–114, doi: https://doi.org/10.1108/13664380580001068
Download citation file:
New and popular articles
Suggested Reading
Extensions of time and liquidated damages in construction contracts in England and Wales
International Journal of Law in the Built Environment (April,2012)
Sub‐Contracting Distribution
Management Research News (March,1987)
The liability for employers for the conduct of their employees – when does an employee’s conduct fall within the “the course of employment”?
Human Resource Management International Digest (October,2016)
Expectancy disconfirmation: Effects of deviation from expected delay duration on service evaluation in the airline industry
Asia Pacific Journal of Marketing and Logistics (February,2019)
Auditor switching and audit fee discounting: the Iranian experience
Asian Review of Accounting (September,2017)
Related Chapters
Bargaining game and LDCs' commercial bank debt restructuring outcomes
The Impact of the Global Financial Crisis on Emerging Financial Markets
Strategy, roles and procurement
Essentials of Digital Construction: Lessons learned from digital transformation
Noname Nightmare: Resolving Customer Complaints in Hospitality
Management
Trade Tales: Decoding Customers' Stories
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.