– The purpose of this paper is to compare the performance of the genetic algorithm (GA), simulate annealing (SA) and shuffled frog-leaping algorithm (SFLA) in solving discrete versus continuous-variable optimization problems of the finance-based scheduling. This involves the minimization of the project duration and consequently the time-related cost components of construction contractors including overheads, finance costs and delay penalties.
– The meta-heuristics of the GA, SA and SFLA have been implemented to solve non-deterministic polynomial-time hard (NP-hard) finance-based scheduling problem employing the objective of minimizing the project duration. The traditional problem of generating unfeasible solutions in scheduling problems is adequately tackled in the implementations of the meta-heuristics in this paper.
– The obtained results indicated that the SA outperformed the SFLA and GA in terms of the quality of solutions as well as the computational cost based on the small-size networks of 30 activities, whereas it exhibited the least total duration based on the large-size networks of 120 and 210 activities after prolonged processing time.
– From researchers’ perspective, finance-based scheduling is one of the few domain problems which can be formulated as discrete and continuous-variable optimization problems and, thus, can be used by researchers as a test bed to give more insight into the performance of new developments of meta-heuristics in solving discrete and continuous-variable optimization problems.
– Finance-based scheduling discrete-variable optimization problem is of high relevance to the practitioners, as it allows schedulers to devise finance-feasible schedules of minimum duration. The minimization of project duration is focal for the minimization of time-related cost components of construction contractors including overheads, finance costs and delay penalties. Moreover, planning for the expedient project completion is a major time-management aspect of construction contractors towards the achievement of the objective of client satisfaction through the expedient delivery of the completed project for clients to start reaping the anticipated benefits.
– Planning for the expedient project completion is a major time-management aspect of construction contractors towards the achievement of the objective of client satisfaction.
– SFLA represents a relatively recent meta-heuristic that proved to be promising, based on its limited number of applications in the literature. This paper is to implement SFLA to solve the discrete-variable optimization problem of the finance-based scheduling and assess its performance by comparing its results against those of the GA and SA.