The Feather River Bridge on Route 20 in Northern California, USA, was damaged by scour during a relatively modest flow event in March 2011. The scour created a hole around the foundation which was nearly 30 feet (9·14 m) deep and which permanently reduced the pile capacity at the main channel pier, requiring an emergency contract to repair the damaged structure. Following the event, several studies were made to help explain the causes of the scour event, including a geomorphological survey of the bank erosion history causing the high degree of misalignment of the flow, a laboratory flume study to examine the evolution of the scour hole and three-dimensional computational fluid dynamics experiments for studying the decay and magnitude of the erosion forces for various scour depths. An additional goal of the modelling was to investigate why the scour ceased at 30 feet and to estimate the erosion forces in the scour hole at that depth.
Article navigation
7 November 2019
Research Article|
August 22 2019
A hybrid approach to forensic study of bridge scour
Kornel Kerenyi;
FHWA Turner-Fairbank Highway Research Center, McLean, VA, USA
(corresponding author: kornel.kerenyi@dot.gov)
Search for other works by this author on:
Kevin Flora
Kevin Flora
Senior Bridge Engineer
Hydraulics Branch, Structure Maintenance and Investigation, California Department of Transportation, Sacramento, CA, USA
Search for other works by this author on:
(corresponding author: kornel.kerenyi@dot.gov)
Publisher: Emerald Publishing
Received:
December 31 2018
Accepted:
July 03 2019
Online ISSN: 2043-9911
Print ISSN: 2043-9903
ICE Publishing: All rights reserved
2019
Proceedings of the Institution of Civil Engineers - Forensic Engineering (2019) 172 (1): 27–38.
Article history
Received:
December 31 2018
Accepted:
July 03 2019
Citation
Kerenyi K, Flora K (2019), "A hybrid approach to forensic study of bridge scour". Proceedings of the Institution of Civil Engineers - Forensic Engineering, Vol. 172 No. 1 pp. 27–38, doi: https://doi.org/10.1680/jfoen.19.00001
Download citation file:
New and popular articles
Suggested Reading
Efficient lightweight design of FRP bridge deck
Proceedings of the Institution of Civil Engineers - Structures and Buildings (August,2015)
Efficient lightweight design of FRP bridge deck
Proceedings of the Institution of Civil Engineers - Structures and Buildings (August,2015)
Numerical modelling of three-dimensional masonry arch bridge structures
Proceedings of the Institution of Civil Engineers - Engineering and Computational Mechanics (June,2021)
Progressive cracking of masonry arch bridges
Proceedings of the Institution of Civil Engineers - Bridge Engineering (October,2015)
Lateral stress profiles on integral bridge abutments
Proceedings of the Institution of Civil Engineers - Bridge Engineering (May,2018)
Related Chapters
Case studies
Railway Bridge Maintenance
Introduction
Bridge Construction Equipment
Lord Hill’s Bridge Mitigation Works
Crossrail Project: Infrastructure Design and Construction
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.