ABSTRACT: This paper focuses on increasing the efficiency in accelerating the rate of consolidation of prefabricated vertical drains (PVDs) in improved soft Bangkok clay using vacuum and heat preloading. Laboratory model tests were performed in new, large-scale consolidometers with PVD-improved reconstituted specimens using the following four schemes: surcharge preloading (PVD only), surcharge combined with vacuum pressure preloading (vacuum-PVD), surcharge combined with heat (thermo-PVD), and surcharge combined with heat and vacuum pressure (thermo-vacuum-PVD). Subsequently, the flow parameters in terms of the horizontal coefficient of consolidation (Ch) and the ratio between the horizontal hydraulic conductivity in the undisturbed zone (kh) to the horizontal hydraulic conductivity in the smear zone (ks), based on Hansbo's method. were investigated by back-calculation. The results show that the values of Ch were 1.93 m2/yr, 2.23 m2/yr, 4.17 m2/yr and 4.37 m2/yr for the PVD, vacuum-PVD, thermo-PVD and thermo-vacuum-PVD, respectively, with corresponding kh/ks values of 3.0, 2.7, 1.4 and 1.1, respectively. On the other hand, the increase in Ch of reconstituted specimens using the vacuum-PVD, thermo-PVD and thermo-vacuum-PVD were 15.54%, 116.06% and 126.42%, and the increases in kh/ks were 10.00%, 53.33% and 63.33%, respectively. Thus the vacuum-PVD can increase the horizontal coefficient of consolidation, Ch, resulting in a faster rate of settlement at the same magnitudes of settlement, compared with the PVD. The thermo-PVD and thermo-vacuum-PVD can further increase the coefficient of horizontal consolidation, Ch, with associated reduction of kh/ks values, by reducing the drainage retardation effects in the smear zone around the PVD, and consequently faster rates of consolidation were obtained. However, higher magnitudes of settlement were obtained upon application of heat owing to the associated collapse of the clay structure, similar to the results of previous investigations.
Article navigation
February 2011
Research Article|
February 01 2011
Enhancement of efficiency of prefabricated vertical drains using surcharge, vacuum and heat preloading Available to Purchase
S. Artidteang;
S. Artidteang
1
Doctoral Candidate, School of Civil Engineering, Asian Institute of Technology, P.O. Box 4, Khlong Luang, Pathumthani, 12120, Thailand, Telephone: +662 524 5523, Telefax: +662 524 6050, E-mail: st109658@ait.ac.th
Search for other works by this author on:
D.T. Bergado;
D.T. Bergado
2
Professor, School of Civil Engineering, Asian Institute of Technology, P.O. Box 4, Khlong Luang, Pathumthani, 12120, Thailand, Telephone: +662 524 5512, Telefax: +662 524 6050, E-mail: bergado@ait.ac.th
Search for other works by this author on:
J. Saowapakpiboon;
J. Saowapakpiboon
3
Civil Engineer, Bureau of Standards and Evaluation, Department of Highways, Phayathai, Ratchathevi, Bangkok, 10400, Thailand, Telephone: +662 354 6414, Telefax: +662 354 6413, E-mail: jtrsnum@gmail.com
Search for other works by this author on:
N. Teerachaikulpanich;
N. Teerachaikulpanich
4
Geotechnical Engineer, Maruyama Industry Co. Ltd, 58/1 Wangtonglang, Bangkok 10310, Thailand, Tel: +66(0) 81 614 6020; Telefax: +662 741 3531, E-mail: nilma2@hotmail.com
Search for other works by this author on:
A. Kumar
A. Kumar
5
Associate Professor, Department of Civil Engineering, Mehran University of Engineering and Technology, Jamshoro, Sindh, Pakistan, Telephone: +92 33 3277 7945, Telefax: +92 22 277 1382, E-mail: aneel4u@hotmail.com
Search for other works by this author on:
Publisher: Emerald Publishing
Received:
December 16 2009
Revision Received:
October 15 2010
Accepted:
November 24 2010
Online ISSN: 1751-7613
Print ISSN: 1072-6349
© 2011 Thomas Telford Ltd
2011
Geosynthetics International (2011) 18 (1): 35–47.
Article history
Received:
December 16 2009
Revision Received:
October 15 2010
Accepted:
November 24 2010
Citation
Artidteang S, Bergado D, Saowapakpiboon J, Teerachaikulpanich N, Kumar A (2011), "Enhancement of efficiency of prefabricated vertical drains using surcharge, vacuum and heat preloading". Geosynthetics International, Vol. 18 No. 1 pp. 35–47, doi: https://doi.org/10.1680/gein.2011.18.1.35
Download citation file:
Suggested Reading
Assessing the performance of prefabricated vertical drain with vacuum and heat preloading
Geosynthetics International (October,2009)
Interaction mechanisms in small-scale model MSE walls under the strip footing load
Geosynthetics International (January,2021)
Vacuum melting plant commissioned
Aircraft Engineering and Aerospace Technology: An International Journal (February,2002)
New Festo vacuum cup
Industrial Robot (June,2002)
Siemens replacement pick and place vacuum nozzles introduced
Industrial Robot (June,2000)
Related Chapters
Paved roads
Handbook of Geosynthetic Engineering: Geosynthetics and their applications
Make Thinking Explicit to Support Student Learning
Decision-Based Learning: An Innovative Pedagogy that Unpacks Expert Knowledge for the Novice Learner
The Materiality Determination Process
Materiality in Financial Reporting: An Integrative Perspective
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.