Mechanised tunnel excavation in soils causes over-excavations, potentially leading to large amounts of spoil and settlements at ground level. An accurate estimation of over-excavations is crucial in the pre-design phase for assessing costs, determining the appropriate excavation method and choosing the muck management strategy. Currently, the estimation is based on experience and data from similar projects, but this becomes difficult when project conditions are heterogeneous. As an alternative, finite-element analyses are time-consuming and not suitable for early design stages; therefore, simplified tools are needed. In this paper, the authors present a simplified approach putting in relation face extrusion with estimated spoil mass and face volume loss. This approach, conceived for deep tunnels, is the extension to the case of mechanised tunnelling of a hydro-mechanical coupled meta-model derived from finite-element numerical analyses for tunnels in clayey soils excavated by using conventional techniques (i.e. without any use of tunnel-boring machines). The model has been validated against field data relative to a case study. The approach can be used in the early design process to identify tunnel-boring machine characteristics and provide preliminary cost estimates. In addition, during the construction phase, the method can be employed to interpret monitoring data and pre-design mitigation measures for unforeseen soil profile variations.
Article navigation
April 2025
Research Article|
March 25 2024
Mechanised deep tunnel excavation in saturated clayey soils: a pre-design hydro-mechanically coupled method for the assessment of both spoil and face volume loss
Luca Flessati;
Luca Flessati
* Faculty of Civil Engineering and Geoscience, Delft University of Technology, Delft, the Netherlands.
Search for other works by this author on:
Claudio Di Prisco
Claudio Di Prisco
† Department of Civil and Environmental Engineering, Politecnico di Milano, Milan, Italy.
Search for other works by this author on:
Publisher: Emerald Publishing
Received:
September 11 2023
Accepted:
March 12 2024
Online ISSN: 1751-7656
Print ISSN: 0016-8505
© 2025 Emerald Publishing Limited
2025
Geotechnique (2025) 75 (4): 515–528.
Article history
Received:
September 11 2023
Accepted:
March 12 2024
Citation
Flessati L, Di Prisco C (2025), "Mechanised deep tunnel excavation in saturated clayey soils: a pre-design hydro-mechanically coupled method for the assessment of both spoil and face volume loss". Geotechnique, Vol. 75 No. 4 pp. 515–528, doi: https://doi.org/10.1680/jgeot.23.00294
Download citation file:
New and popular articles
Suggested Reading
A systems model of organizational change
Journal of Organizational Change Management (November,2019)
Partner selection as a control mechanism in inter-organizational relationships: a meta-model approach
Journal of Accounting & Organizational Change (July,2022)
Can vague brand slogans promote desirable consumer responses?
Journal of Product & Brand Management (August,2014)
Intrapreneurship: outside the project box and into the unknown
Journal of Business Strategy (December,2019)
Construction of a deep shaft for Crossrail
Proceedings of the Institution of Civil Engineers - Geotechnical Engineering (December,2008)
Related Chapters
Ground and rock fragmentation – drilling and blasting
Civil Excavations and Tunnelling: A practical guide
Earth movers, excavators and open-cut excavations
Civil Excavations and Tunnelling: A practical guide
Raising, sinking and large subsurface excavations
Civil Excavations and Tunnelling: A practical guide
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.