Tendering plays a very important role in a project’s life cycle and the outcome of the tendering process will have a direct impact on the overall project cost. It should be clear that in evaluating tenders, it is not just the bid price that counts. The quality of the selected contractor will in many ways affect the success of the project; that is delivery on time, within budget and to the required quality. The selection of a ‘wrong’ contractor could easily lead to late completion or over expenditure. Unfortunately, uncertainties of events and unpredictability of their outcome do exist at the tendering stage, the effect of which could be costly in some circumstances. To manage the risks associated with such uncertainties, the introduction of risk assessment as an explicit dimension in the tender evaluation process is proposed. In this approach, decision makers will be made aware of high-risk elements upfront so that more informed decisions can be made. With more supportive information in a complex decision-making process, it is hoped that project risks and, in turn, costs can be lowered as far as practicable.
Article navigation
August 2009
Research Article|
August 01 2009
Risk assessment as an explicit dimension for tender evaluation*
E. C. S. Kwok, PhD, DIC, CEng, FBCS, FIET, FIMechE;
E. C. S. Kwok, PhD, DIC, CEng, FBCS, FIET, FIMechE
Engineering Manager – Systems
MTR Corporation Limited
Hong Kong, PR China
Search for other works by this author on:
S. H. S. Ng, PhD, CEng, MIET;
S. H. S. Ng, PhD, CEng, MIET
Principal Consultant
Atkins China Limited
Hong Kong, PR China
Search for other works by this author on:
J. C. L. Tam, MBA, FRICS, FHKIS, MHKIE, MCIOB, RPS(QS)
J. C. L. Tam, MBA, FRICS, FHKIS, MHKIE, MCIOB, RPS(QS)
Contracts Administration Manager
MTR Corporation Limited
Hong Kong, PR China
Search for other works by this author on:
Publisher: Emerald Publishing
Received:
January 26 2007
Accepted:
January 23 2009
Online ISSN: 1751-4312
Print ISSN: 1751-4304
© 2009 Thomas Telford Ltd
2009
Proceedings of the Institution of Civil Engineers - Management, Procurement and Law (2009) 162 (3): 117–120.
Article history
Received:
January 26 2007
Accepted:
January 23 2009
Connected Content
A commentary has been published:
Discussion: Risk assessment as an explicit dimension for tender evaluation
See also
Citation
Kwok ECS, Ng SHS, Tam JCL (2009), "Risk assessment as an explicit dimension for tender evaluation*". Proceedings of the Institution of Civil Engineers - Management, Procurement and Law, Vol. 162 No. 3 pp. 117–120, doi: https://doi.org/10.1680/mpal.2009.162.3.117
Download citation file:
New and popular articles
Suggested Reading
Briefing: Impact of low-cost bidding
Proceedings of the Institution of Civil Engineers - Management, Procurement and Law (June,2015)
The evolution of tender contracts
Proceedings of the Institution of Civil Engineers - Management, Procurement and Law (November,2009)
Sickness in government science: case, cause and cure
Proceedings of the Institution of Civil Engineers - Municipal Engineer (September,2006)
Individuals and enterprise: winning business in the new millennium
Industrial and Commercial Training (February,2000)
A model for designing the tendering process in public–private partnerships
Proceedings of the Institution of Civil Engineers - Management, Procurement and Law (June,2015)
Related Chapters
Tendering in Stealth Construction
Stealth Construction: Integrating Practices for Resilience and Sustainability
‘Community Wealth Building’ and ‘Clever Tendering’ for an Inclusive Local Economy
Reimagining Public Sector Management: A New Age of Renewal and Renaissance?
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.