This paper takes a retrospective view of the Hong Kong government’s now-completed NEC pilot contract for Fuk Man Road nullah. It describes the detailed preparation and trial use of an amended NEC3 Engineering and Construction Contract option C (target cost with activity schedule) to procure contract DC/2008/02 for the Drainage Services Department between 2006 and 2012. The HK$72 million (£7 million) pilot proved successful at introducing contractual partnering on a Hong Kong public works project, resulting in NEC contracts becoming widely adopted by the government’s works departments. The pilot also identified a number of areas for improvement in the way the NEC was amended and implemented. This paper sets out the lessons learnt for future users of NEC in Hong Kong.
Article navigation
1 December 2016
Research Article|
September 23 2016
Hong Kong’s first public sector NEC contract: lessons learnt
Yan Chun Li, BEng(Civil), LLB, MHKIE, MHKIVM;
Black & Veatch Hong Kong Limited, Kowloon, Hong Kong, China
(corresponding author: liyc@bv.com)
Search for other works by this author on:
Wai Hung Luk, BSc (Eng), MPA, MHKIE;
Wai Hung Luk, BSc (Eng), MPA, MHKIE
NEC3 ECC Accredited Project Manager
Drainage Services Department, Hong Kong, China
Search for other works by this author on:
Ellen Cheng, BASc, (Hons), MEng (Hons), MICE, MHKIE
Ellen Cheng, BASc, (Hons), MEng (Hons), MICE, MHKIE
Beam Pro, Drainage Services Department, Hong Kong, China
Search for other works by this author on:
(corresponding author: liyc@bv.com)
Publisher: Emerald Publishing
Received:
October 27 2015
Accepted:
September 02 2016
Online ISSN: 1751-4312
Print ISSN: 1751-4304
ICE Publishing: All rights reserved
2016
Proceedings of the Institution of Civil Engineers - Management, Procurement and Law (2016) 169 (6): 231–237.
Article history
Received:
October 27 2015
Accepted:
September 02 2016
Citation
Li YC, Luk WH, Cheng E (2016), "Hong Kong’s first public sector NEC contract: lessons learnt". Proceedings of the Institution of Civil Engineers - Management, Procurement and Law, Vol. 169 No. 6 pp. 231–237, doi: https://doi.org/10.1680/jmapl.15.00051
Download citation file:
New and popular articles
Suggested Reading
Managing uncertainty in fast-track construction projects: case study from South Africa
Proceedings of the Institution of Civil Engineers - Management, Procurement and Law (March,2020)
A cognitive approach to trust management in construction
Proceedings of the Institution of Civil Engineers - Management, Procurement and Law (October,2013)
Enhancing off-site manufacturing through early contractor involvement (ECI) in New Zealand
Proceedings of the Institution of Civil Engineers - Management, Procurement and Law (January,2018)
Comparison of two infrastructure project implementation models in a developing country
Proceedings of the Institution of Civil Engineers - Management, Procurement and Law (February,2018)
Innovative construction procurement at Wits University
Proceedings of the Institution of Civil Engineers - Management, Procurement and Law (October,2014)
Related Chapters
Early Contractor Involvement Models: Their Pros and Cons and When to Use Them
Early Contractor Involvement: Improving the Management of Contract Risk
Public Procurement Process
Early Contractor Involvement: Improving the Management of Contract Risk
Managing Costs Escalation on a Cost Reimbursable Contract
Early Contractor Involvement: Improving the Management of Contract Risk
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.