Purpose

The purpose of this paper is to describe a study of the successful application of the theory of constraints (TOC) to a manufacturing plant operations problem. The TOC application required the identification of a bottleneck constraint in the manufacturing process which limited through‐put and thus negatively affected plant productivity and efficiency.

Design/methodology/approach

The methodology used was a detailed case study of the bottleneck in the manufacturing process. The bottleneck in this case was the mold‐changing operations, consisting of a plastic injection process for heavy‐duty truck‐lighting systems components.

Findings

It was found that to eliminate the bottleneck four separate solution approaches were applied to the problem, and these four solutions collectively eliminated the bottleneck constraint.

Research limitations/implications

The limitation of this approach is that the application of the TOC method is highly specific to the particular operation.

Originality/value

On completion of the study the mold‐changing process improvements resulted in increased through‐put and concomitant improvements in productivity and efficiency in the heavy‐duty truck‐lighting systems plant.

You do not currently have access to this content.
Don't already have an account? Register

Purchased this content as a guest? Enter your email address to restore access.

Please enter valid email address.
Email address must be 94 characters or fewer.
Pay-Per-View Access
$41.00
Rental

or Create an Account

Close Modal
Close Modal