In recent years, the construction industry has been faced with several issues such as mass migration across national borders, increasingly complex environments with respect to safety/environmentally friendly designs and intense competition for projects. Stipulated completion periods filled with uncertainties and factories being built in foreign countries require the mobilisation of personnel, equipment transportation and in addition capital turnover challenges. Operational delays are also major challenges for decision makers. Therefore, professional decision-making tools play a significant role in assisting decision makers to manage uncertainty. This study applies decision trees to analyse the practice of construction acceleration to overcome delays in the building of multinational factories. The shadow price obtained from linear programming optimisation and the float time computed by the scheduling-path method are integrated and analysed using decision trees. The results indicate the most effective alternatives for acceleration and provide references for decision makers. In a specific case study, the target project value was fixed at 8490·8 RMB (Renminbi) ($1241·06), and it was therefore important to find a delivery method to keep costs below this sum and within the programme timelines.
Article navigation
March 2020
Research Article|
October 19 2018
Project management of constructive acceleration in building multinational factories
Jeng-Wen Lin, PhD
;
Jeng-Wen Lin, PhD
Professor, Department of Civil Engineering, Feng Chia University, Taichung, Taiwan (corresponding author: jwlin@fcu.edu.tw)
Search for other works by this author on:
Pu Fun Shen, PhD;
Pu Fun Shen, PhD
Construction Management Engineer, T.Y. Lin Taiwan Consulting Engineers, Inc., Taipei, Taiwan
Search for other works by this author on:
Chih-Wei Huang, PhD
Chih-Wei Huang, PhD
Research Assistant Professor, Institute of Water Resources Development, Feng Chia University, Taichung, Taiwan
Search for other works by this author on:
Publisher: Emerald Publishing
Received:
February 17 2018
Accepted:
September 04 2018
Online ISSN: 1751-7699
Print ISSN: 0965-0903
ICE Publishing: All rights reserved
2018
Proceedings of the Institution of Civil Engineers - Municipal Engineer (2020) 173 (1): 36–48.
Article history
Received:
February 17 2018
Accepted:
September 04 2018
Citation
Lin J, Shen PF, Huang C (2020), "Project management of constructive acceleration in building multinational factories". Proceedings of the Institution of Civil Engineers - Municipal Engineer, Vol. 173 No. 1 pp. 36–48, doi: https://doi.org/10.1680/jmuen.18.00010
Download citation file:
New and popular articles
Suggested Reading
Changes in land value due to road development
Proceedings of the Institution of Civil Engineers - Transport (November,2017)
Cross-cultural leadership for global construction projects
Proceedings of the Institution of Civil Engineers - Management, Procurement and Law (October,2013)
A multivariate delay estimation model proposal for public construction projects
Proceedings of the Institution of Civil Engineers - Municipal Engineer (February,2019)
STATS: Take a Quantitative Leap
Reference Reviews (January,2015)
Statistics of soil particle strength
Geotechnique (December,2001)
Related Chapters
On horizontal variability in lime-cement columns in deep mixing
Risk and Variability in Geotechnical Engineering
Partial factors calibration based on reliability analyses for square footings on granular soils
Risk and Variability in Geotechnical Engineering
Reliability-based design applied to retaining walls
Risk and Variability in Geotechnical Engineering
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.