This paper considers and discusses analytically the optimal preventive maintenance (PM) policies of aged plants such as fossil‐fired power plants.

Design/methodology/approach

Shocks are assumed to occur at a nonhomogeneous Poisson process and the total damage due to each shock is additive. The system undergoes the PM at a certain time or the total damage exceeds a managerial level. The expected cost rate until PM is derived and optimal policies which minimizes it are discussed.

Findings

There exists a unique optimal time (T*) or managerial level (k*) which minimizes the expected cost rate. But there does not exist a positive pair (T*, k*), simultaneously.

Research limitations/implications

The damage occurrence distribution is assumed to be nonhomogeneous Poisson one.

Practical implications

Useful methods to consider the optimal PM policies for power plant engineers.

Originality/value

This paper contributes to users of aged power plants economically and practically.

You do not currently have access to this content.
Don't already have an account? Register

Purchased this content as a guest? Enter your email address to restore access.

Pay-Per-View Access
$41.00
Rental

or Create an Account

Close Modal
Close Modal