Purpose

The aim of this study is to establish a framework with which process plants can evaluate the performance of their turnaround maintenance (TAM) projects at the end of the event without making reference to previous events.

Design/methodology/approach

This is a case study. The study involved the case studies of six process plants in the UK. Three sources of evidence were used in this study including; interviews, direct observation and official documents.

Findings

The case studies show that TAM projects can be evaluated by assessment of the management performance and the resultant benefits realised. The uses of generic project success measures are not very adequate for TAM.

Practical Implications

The study developed success measurement criteria for TAM projects. Instead of comparing performance of TAM projects with previous ones to assess how successful the outcome is, organisations can evaluate their TAM project's performance based on the current TAM using the criteria developed in the framework. In addition, these success criteria will enable the organisation to evaluate the benefits expected from the TAM project outcome at hand‐over of the plant from the TAM project management to the operations management.

Originality/value

Operators of process plants and hence engineering facilities still measure the outcome of TAM using measures that are generic for EPC projects. Considering the peculiar nature of TAM, this study has developed success measurement criteria for TAM projects specifically.

You do not currently have access to this content.
Don't already have an account? Register

Purchased this content as a guest? Enter your email address to restore access.

Please enter valid email address.
Email address must be 94 characters or fewer.
Pay-Per-View Access
$41.00
Rental

or Create an Account

Close Modal
Close Modal