A quantitative approach for managing construction pollution control that is based on construction resource leveling is presented. The parameters of construction pollution index, hazard magnitude are treated as a pseudo resource and integrated with a project’s construction schedule. When the level of pollution for site operations exceeds the permissible limit identified by a regulatory body, a genetic algorithm (GA) enhanced leveling technique is used to re‐schedule project activities so that the level of pollution can be re‐distributed and thus reduced. The GA enhanced resource leveling technique is demonstrated using 20 on‐site construction activities in a project. Experimental results indicate that proposed GA enhanced resource leveling method performs better than the traditional resource leveling method used in MS Project© The proposed method is an effective tool that can be used by project managers to reduce the level of pollution at a particular period of time; when other control methods fail.
Article navigation
1 May 2002
This article was originally published in
Environmental Management and Health
Technical Paper|
May 01 2002
Integrating construction pollution control with construction schedule: an experimental approach
Zhen Chen;
Zhen Chen
Department of Building and Real Estate, Hong Kong Polytechnic University, Kowloon, Hong Kong
Search for other works by this author on:
Heng Li;
Heng Li
Department of Building and Real Estate, Hong Kong Polytechnic University, Kowloon, Hong Kong
Search for other works by this author on:
Conrad T.C. Wong;
Conrad T.C. Wong
Yau Lee Construction Co Ltd, Kowloon Bay, Kowloon, Hong Kong
Search for other works by this author on:
Peter E.D. Love
Peter E.D. Love
Management Information Systems, Edith Cowan University, Perth, Australia
Search for other works by this author on:
Publisher: Emerald Publishing
Online ISSN: 1758-7085
Print ISSN: 0956-6163
© MCB UP Limited
2002
Environmental Management and Health (2002) 13 (2): 142–151.
Citation
Chen Z, Li H, Wong CT, Love PE (2002), "Integrating construction pollution control with construction schedule: an experimental approach". Environmental Management and Health, Vol. 13 No. 2 pp. 142–151, doi: https://doi.org/10.1108/09566160210424572
Download citation file:
810
Views
New and popular articles
Suggested Reading
Implementation of a parallel 4D‐variational chemistry data‐assimilation scheme
Environmental Management and Health (October,1999)
Combinatory effects of microplastics and emerging contaminants on alga Chlamydomonas reinhardtii
Journal of Environmental Engineering and Science (April,2023)
Numerical study of clustered reactive media cylinders for remediating contaminated groundwater
Proceedings of the Institution of Civil Engineers - Waste and Resource Management (November,2025)
An Overview of Water, Water Pollution and Control in China
Environmental Management and Health (March,1992)
Crop residue burning emissions and cleaner alternatives for air quality in India
Journal of Environmental Engineering and Science (May,2026)
Related Chapters
Construction
Sustainable Infrastructure: Principles into Practice
Water pollution
Environmental Law for Sustainable Construction: A guide for construction, engineering and architecture professionals
Fisher Street crossover: construction of the secondary lining
Crossrail Project: Infrastructure design and construction
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.