Purpose

This study proposes a guideline for integrating Building Information Modelling (BIM) technology and lean construction practices to address the construction industry’s challenges in transitioning to environmentally friendly developments.

Design/methodology/approach

This study employs a qualitative research method, integrating and validating lean principles with BIM tools by extensively analysing previous studies. Subject matter expert interviews were conducted to validate the findings and create conceptual maps. Thematic and content analyses were performed to develop the proposed guidelines and recommendations.

Findings

The study highlights the potential of integrating BIM and lean construction practices to enhance productivity and reduce waste. The proposed guidelines provide practical recommendations for improving the implementation of BIM and lean practices, offering a structured approach for stakeholders to address critical challenges.

Research limitations/implications

While this study provides valuable insights, it primarily focuses on the New Zealand (NZ) context. Future research could explore the applicability of the proposed guidelines in different regions and consider quantitative validation methods to strengthen the findings.

Originality/value

This research contributes to the field by providing a novel guideline for integrating BIM and lean construction practices, addressing critical implementation challenges. The study offers valuable insights for global construction practices aiming to adopt advanced management approaches.

Traditional delivery methods used in the construction industry can result in project issues like cost overruns, time overruns, disagreements and delays. As a result, it can be challenging to maintain coordination and cooperation throughout the process, which is crucial (Shoar et al., 2023). The development of Information and Communication Technology (ICT.) and its advantages have been employed in response to the complex nature of the construction industry and its implications on productivity and performance (Omrany et al., 2023). BIM and lean construction, including Last Planner, a lean-based approach for collaborative project scheduling and production planning, are examples of how ICT. for the construction sector is growing (Succar, 2009).

BIM models present design and construction information, enhancing project participants' ability to communicate and work together (Koo and Fischer, 2000). For instance, 4D modelling aids in improving understanding and communication of the construction plan among project participants (Kuo et al., 2011; McKinney and Fischer, 1998). Lean construction eliminates waste throughout the building process, whereas BIM aims to enhance cooperation among project teams during a project’s design and construction phases. The project delivery method is another effective process encompassing the cycle of design and construction aspects, such as activity sequence, roles and responsibilities, material cost and labour (Demirkesen and Ozorhon, 2017). The integration of BIM functionalities and lean principles is crucial for developing the new BIM–lean and Integrated Project Delivery (IPD) concepts, a collaborative project approach bringing all stakeholders together to optimise project outcomes (Evans and Farrell, 2023).

BIM and lean are gaining popularity in practice and research (Evans et al., 2021); however, with a few exceptions, the scientific community treats both lean and BIM approaches independently (Schimanski et al., 2020). Although BIM and lean construction principles have shown substantial benefits individually, their combined application is still underutilised. The primary barriers to this integration include cultural resistance, a lack of knowledge and insufficient support from senior management. These issues prevent the construction industry from fully harnessing the potential of BIM and lean principles to drive sustainable and efficient project outcomes (Likita et al., 2024; El-Diraby et al., 2017).

The case studies on integrating BIM and lean principles show improved global construction project efficiency, collaboration and outcomes. For instance, the Istanbul Grand Airport (IGA) project highlighted how BIM’s visualisation capabilities facilitated collaborative planning and progress tracking, resulting in significant time and cost savings. Integrating lean principles ensured efficient resource utilisation and minimised waste, contributing to the project’s timely and on-budget completion (Koseoglu et al., 2018). In Malaysia, a qualitative study identified vital factors driving lean–BIM implementation, showing potential to address local industry needs and enhance overall construction efficiency (Aziz and Zainon, 2023).

Additional case studies underscore the practical benefits of these integrated approaches. For example, a case study in Egypt demonstrated the use of BIM as a lean management tool, reducing waste and improving efficiency in construction processes, thus avoiding an 11% increase in the total contract price and a 25% increase from the original contract time (Eldeep et al., 2022). This study showcases BIM’s role as a lean management tool, effectively reducing waste and avoiding high cost and schedule overruns, demonstrating the potential of BIM–lean integration to address barriers like waste management challenges. However, limited studies are exploring the practical integration of these tools, especially with clear adoption strategies and possible challenges such as resistance to change processes. The study clearly outlines the need for coordination for adoption amongst stakeholders, especially main contractors and subcontractors, and highlights the need for a framework to address the realistic challenges that firms face when adopting lean and BIM (Eldeep et al., 2022). The University of Alicante, Spain case study conducted by Andújar-Montoya et al. (2020), also reflects the challenges noted in interviews, such as resistance to change and fragmented supply chains, reinforcing the need for better lean training and understanding. The study provides evidence for addressing resistance through leadership and incentivised training programmes.

A study from China on BIM and lean construction for enhanced disassembly and reuse highlighted sustainability benefits, such as resource optimisation and reduced environmental impact (Hei et al., 2024). It emphasises expanding BIM–lean integration beyond traditional construction phases to support circular economy principles, particularly during construction. A community hospital project case study from the USA validated that BIM can be used to achieve lean principles, successfully integrated the two to develop construction safety, reduce inventory, rework and avoid construction clashes (Zhang et al., 2018). The case underscores the importance of addressing operational challenges, such as on-site clashes and inventory control, which are critical to project success and efficiency. However, such practices lack proper record-keeping and practical guidelines. Another study found that combining BIM functions with lean principles improves construction execution, with 4D visualisation boosting labour productivity (Karatas and Budak, 2023). It highlights the need to address knowledge gaps in BIM functionalities and provide actionable training, necessitating further development of strategies and guidelines. Integrating BIM and lean paradigms in a public construction project at the University of Alicante reduced architectural conflicts and improved coordination. However, while it also lessened facility systems issues, notable conflicts and budget deviations persisted. Despite improvements, challenges remained in managing costs and facilities (Andújar-Montoya et al., 2020). The processes involved can be refined using BIM–lean integration, and higher efficiency and profitability can be achieved in residential projects (Pérez et al., 2024). Quantitative analysis shows significant positive interactions between lean construction and BIM, enhancing project outcomes and providing empirical support for their integration (Arayici et al., 2023). The reviewed case studies validate the feasibility and advantages of BIM–lean integration while exposing gaps that must be addressed in the NZ context. Collectively, these studies provide empirical evidence supporting the positive impacts of combining BIM and lean principles on project management, efficiency, sustainability and stakeholder collaboration, offering valuable insights for researchers and practitioners in the construction industry.

Many countries have implemented reforms to conduct projects using lean and BIM, and others have made renderings necessary for public procurement, such as the Architecture Engineering Construction Owners Operators (AECOO) continue their efforts for their value added to countries' economies, employability, failures and poor reputation (Bradley et al., 2016). Frameworks in construction provide a standardised approach to implementing modern methods, ensuring consistent quality and efficient knowledge transfer and facilitating the adoption of innovative technologies and best practices, enhancing project outcomes (Rashidi et al., 2024; Siriwardhana and Moehler, 2024). A BIM–lean model was developed through an analytic network process (ANP) and provides a framework for enhancing lean/BIM integration in the construction industry (Bayhan et al., 2023). It focused on three main clusters: communication, production and visualisation, with 17 nodes representing factor groups from the LC and BIM literature. Barkokebas et al. (2021) examine how BIM and lean principles can enhance premanufacturing processes in off-site construction. The study highlights the underutilisation of digital tools and the lack of focus on early phases, providing detailed steps for evaluation and improvement through quantitative and qualitative assessments. Sbiti et al. (2021) created a BIM–lean framework and identified the reliance on manual processes as a critical obstacle to effective BIM–LPS integration.

Similarly, an integrative literature review devised a conceptual model for BIM–LPS integration to provide an overview and develop a conceptual integration model (Schimanski et al., 2020, 2021). In the original BIM–lean interaction matrix developed by Maraqa et al. (2021), some identified interactions were declared “not mature technology” at the time. For example, visualising process status via reliable technology further motivates the development of a new BIM–lean integrating information system.

In previous studies, cultural resistance, lack of knowledge, lack of understanding, resistance to change and lack of support from senior staff in NZ organisations have been identified as barriers slowing the integrated uptake of BIM–lean technologies (Likita et al., 2022). Hence, there is a specific need for a unique guideline for NZ which ensures the practical relevance and applicability of BIM and lean integration. As these have matured independently, combining the two parallel streams is necessary to reap more excellent benefits for the industry (El Mounla et al., 2023). While there have been attempts to demonstrate the overlap between BIM and lean concepts (Dave et al., 2016; Forbes and Ahmed, 2010; Likita et al., 2020), a BIM lean integration guideline for the NZ construction sector has not been developed or reported. The fragmented nature of current construction practices exacerbates these challenges, highlighting the need for a cohesive guide for implementing BIM and lean construction effectively.

Based on the literature identifying the knowledge gap, this study aims to develop a comprehensive guideline for integrating BIM and lean construction practices, addressing the critical barriers to their adoption and utilisation. The specific objectives are to analyse the current state of BIM and lean construction integration in the NZ construction industry, identify key challenges and opportunities, create a guideline illustrating the interactions between BIM tools and lean principles throughout the construction phase, validate the proposed guideline through expert interviews, and provide actionable guidelines and recommendations for construction managers and practitioners.

The study comprises a four-stage methodology to capture and validate the complex nature of the problem. Figure 1 illustrates the different stages of the methodology and their linkage. The four stages are described in detail in the following subsections.

Figure 1

Methodology stages and mapping

Figure 1

Methodology stages and mapping

Close modal

The first stage involved semi-structured interviews to explore potential concepts, practices and processes for a comprehensive guideline for implementing BIM and lean construction management practices in NZ (Doan et al., 2021). The interviews were semi-structured to allow flexibility in the process and to discuss fresh ideas (Stage 1 in Figure 1). The interviews were performed until theoretical saturation was reached, with data collection ceasing once no new insights were gained (Babaeian Jelodar and Shu, 2021; Jelodar et al., 2014). For each research question, visual diagrams, called conceptual maps, are created to connect related concepts and ideas around a central theme for better understanding.

Based on the literature review of the construction projects, case studies and frameworks comprising BIM and lean philosophies, interview questions for guideline development are formulated. This approach will highlight the issues with BIM and lean implementation (Gerber et al., 2010; Ghosh et al., 2013; Lapinski et al., 2006) and helps identify examples of lean BIM interaction from past studies. The following questions were generated for the semi-structured interview:

  • What issues influence lean implementation in modern construction practices in NZ?

  • What are the factors influencing/affecting lean implementation in an organisation?

  • What strategies are created/planned to improve lean implementation in construction organisations in case of failure?

  • What lean philosophies are used in construction organisations?

  • How can BIM enhance lean construction?

  • How can BIM and lean integrated practices be improved in the construction sector?

Interviews help to gain broader and deeper perspectives of interview participants on a topic. The data collection stage involved two sets of interview questions. The first set was an exploratory interview, and the second set was conducted for industry feedback on the developed guideline (Stage 2 of Figure 1). For optimum tangibility and comprehension of responses, interviews were designed with key questions accompanied by follow-up questions (Chen and Partington, 2004). The interviewees' selection criteria included related work experience (at least five years) and a diverse group of practitioners. The second set of interviews, used to gather industry feedback as part of the validation process, involved expert elicitation. This method collects experts' insights, opinions and judgments to support decision-making, validate findings or refine guidelines, especially when data or evidence is limited (Das et al., 2023).

The first set of interview participants was recruited through invitation via LinkedIn and using the chain referral method. The snowball sampling strategy was used to identify subsequent participants during interviews, effectively accessing hard-to-reach niche groups and experts.

Before the interview, an interview guide was given to each interviewee. Before recording interviews, the researcher briefly summarised the study’s background and primary goals. The anonymity of the participants was assured by using pseudonyms (PE1–PE15). After reviewing each interview script several times, several themes from the respondents' common ideas and points of view were identified. Based on the replies, the codes used to create the themes were created, enabling analysis and the synthesis of facts to create a theme relevant to the given questions.

Based on the exploratory nature of this stage of the methodology, respondents’ roles and experiences were critical. Every participant was qualified, held a prominent role and possessed more than five years of experience in BIM and lean construction management practices. Consequently, all informants have in-depth knowledge and experience in BIM and lean construction management practices. Information on the research participants, with whom semi-structured online interviews at various management levels were conducted, is provided in Table 1. Participants had diverse roles and levels of experience. Though based in NZ, experts brought international experience from various locations.

Table 1

Profile of participants involved in guideline design

No.PseudonymsWorking experience (years)Position
1PE110Engineer
2PE210Facility Manager
3PE322Project Supervisor
4PE420Director
5PE520Structural engineers
6PE620Process Engineer
7PE711Developer
8PE88Site Engineer
9PE95Project Manager
10PE1015Software Engineer
11PE1115Project Manager
12PE1213Asset Manager
13PE1324Civil Engineer
14PE1423Site Engineer
15PE1515Chartered Civil Engineer

Source(s): Authors’ own creation

The number of interviewees was determined by achieving theoretical saturation, where further interviews cease to provide additional insights for the specific purpose of a study (Glaser and Strauss, 2017). As data collection progressed, each subsequent interview contributed to a richer understanding of the identified themes. By the 12th interview, no significant new themes emerged, suggesting that key categories had been thoroughly captured. After an iterative data collection and analysis process, theoretical saturation was achieved through 15 in-depth, semi-structured interviews. The subsequent three interviews reinforced existing patterns without adding new insights, signalling that additional data collection was unlikely to yield further information. Interviews were meticulously coded, allowing for the identification of emerging themes and patterns related to the research topic.

The literature review outcomes, alongside the theoretical replication logic provided through the analysis of the expert interviews, have provided a triangulation of knowledge and a measure of internal validity. To confirm saturation, data analysis employed constant comparison methods, where each new piece of data was compared against existing codes to ensure consistency and completeness. This approach verified that the core categories and subcategories had sufficient depth and variability. Therefore, theoretical and methodological considerations supported the decision to conclude data collection at 15 interviews.

The data obtained for this experiment was stored, interpreted and evaluated using the ATLAS.ti 9 software (Chang and Hsieh, 2020). ATLAS.ti is an advanced data analysis software that extracts valuable insights from qualitative data. It is highly regarded as a powerful tool for qualitative analysis, especially when dealing with large volumes of textual and graphical information. Thematic and content analysis, which involved categorising major themes and systematic analyses of critical concepts, was performed to identify patterns and trends from the transcribed interview data (Amirtash et al., 2021; Jelodar and Yiu, 2012; Dauda et al., 2024). After an initial study of textual data, the qualitative data from the participants and the interview were put into the ATLAS.ti 9 programme. ATLAS.ti 9 software package helped identify many words, phrases and other keywords connected to this article or topic of interest (Friese et al., 2018). Descriptive coding was used to organise the collected data and create codes from the interview transcripts (Rasanjali et al., 2024). The authors then employed pattern coding to analyse the first cycle codes, looking for similarities and patterns to address objectives. The emerging themes are depicted through diagrams and illustrations for each interview question (Stage 3 of Figure 1). A pictorial representation was created for clarity using the Atlast.ti9 software (Chang and Hsieh, 2020).

In addressing the detailed explanations of individual participants' viewpoints, emphasis will be on key insights derived from the diagrams and incorporate general insights from expert opinions. The findings from the literature review and observations are then combined with experts' opinions from the NZ construction industry to develop a BIM-based guideline for lean and BIM integration.

The developed guideline is then communicated and disseminated to construction industry professionals and experts through a formal expert elicitation process. The process involves conducting semi-structured interviews to obtain their perspective on it and find areas for improvement (Ren et al., 2024). The validation process consists of two phases. First, experts reviewed the draft guideline, which included findings from the literature review, interviews and thematic analysis, assessing its clarity, applicability and industry alignment. Next, semi-structured interviews gathered detailed feedback on the framework’s practicality, relevance and clarity, enabling experts to identify improvements and suggest enhancements (Stage 4 of Figure 1).

Subject matter experts (SMEs) were contacted via individual emails, and interviews were scheduled at mutually convenient times upon their acceptance. Participants were highly experienced construction professionals, with expertise ranging from 8 to 47 years. The selection involved background screening to ensure experience with BIM and lean applications for guideline validation. Interviews were conducted to test the study’s findings, and each participant was anonymised with a code (e.g. SME 1 to SME 8) as listed in Table 2.

Table 2

Profile of participants involved in the validation

Participant profileYears of experience
SME 1 Planning and scheduling/cost control18
SME 2 Facility management expert10
SME 3 Project supervisor/council planner22
SME 4 Director, reinforcing company20
SME 5 Structural engineer20
SME 6 Process engineer/plasterboard manufacturer47
SME 7 Developer11
SME 8 Construction manager8

Source(s): Authors’ own creation

This section presents the interview findings, structured across six key areas: issues influencing lean implementation in modern construction practices in NZ; factors affecting organisational lean implementation; strategies to improve lean implementation in construction organisations; lean philosophies in construction; the role of BIM in enhancing lean construction; and BIM tools used in organisations. Insights were gathered from fifteen experienced BIM and lean construction management professionals recruited via LinkedIn and chain referrals.

Figure 2 summarises the key identified issues affecting implementing lean practices within modern construction practices. At the core are various interconnected issues that collectively influence the adoption and efficacy of lean methods.

Figure 2

Issues influencing lean implementation in modern construction practices

Figure 2

Issues influencing lean implementation in modern construction practices

Close modal

The complexity of construction projects in NZ poses significant challenges to lean implementation. Key issues include difficulties in coordinating resources, schedules and activities, along with management challenges that disrupt the consistent application of lean principles across project phases. Effective information management, a cornerstone of lean, is hindered by the lack of standardisation and the difficulty in sharing data among stakeholders, affecting the smooth flow of critical information for efficient execution. Additionally, the absence of industry-wide standardisation impairs consistency and reproducibility across projects. This is further compounded by resistance to change, as traditional practices remain deeply entrenched, limiting the acceptance of lean approaches in the NZ construction sector.

Coordination challenges within and between organisations create further inefficiencies, increasing the potential for rework and delays. The costs associated with implementing lean practices can also be prohibitive for some organisations, especially in a market where limited competition among subcontractors limits options and flexibility. Cultural and mindset barriers further complicate lean adoption, as shifting to lean requires a collective industry-wide change towards prioritising waste reduction and efficiency. This cultural shift is difficult to achieve in a traditionally conservative industry. Additionally, the shortage of skilled labour poses a major challenge, as implementing lean practices depends on a workforce well-versed in lean methods and processes.

Legal and contractual issues also pose challenges to lean implementation. Contracts often do not incentivise or support lean practices, and legal constraints, combined with the minor, fragmented nature of NZ’s construction industry, make it challenging to leverage lean techniques fully. Experts underscore the synergy between lean principles and BIM tools to enhance lean construction, which can support waste reduction, process efficiency and continuous improvement. BIM’s visualisation, coordination and simulation capabilities complement lean’s focus on efficiency. Integrating BIM’s 3D modelling and clash detection features with a lean strategy like just-in-time (JIT) delivery and visualisation and optimisation tools like value stream mapping can significantly improve project planning, execution and workflow efficiency while reducing rework. Addressing these challenges in lean implementation will require coordinated efforts in training, improved management practices, and fostering a culture that values lean principles.

Figure 3 presents a range of factors influencing the implementation of lean practices within organisations. These elements collectively impact the effectiveness of lean integration, with each factor uniquely shaping organisational readiness and adaptability to lean methodologies.

Figure 3

Factors that influence lean implementation

Figure 3

Factors that influence lean implementation

Close modal

Successful lean implementation in construction relies on effective leadership and a supportive organisational culture. Leaders who actively endorse lean principles and promote a culture of continuous improvement lay the groundwork for success. Without strong leadership and a culture prioritising innovation and efficiency, lean initiatives risk losing momentum or failing to sustain over time. Skilled, well-trained employees actively involved in lean processes foster ownership and reduce resistance, while inadequate training can leave them unprepared and disconnected, hindering adoption. Resource allocation and market conditions also influence lean’s success. Sufficient budget, time and personnel must be dedicated to lean practices, while external pressures like customer demands and competitive forces often drive the need for efficiency. Without these resources or market drivers, lean may be deprioritised, hindering its full potential.

Clear, effective communication across teams and departments is crucial, ensuring alignment and preventing misunderstandings that can impede lean’s objectives. Poor communication risks creating inefficiencies that counteract lean goals. Process complexity and project uniqueness within the construction industry present challenges for standardising lean practices. While lean relies on consistent processes, the variability in construction projects makes a uniform approach difficult. Striving to standardise where possible and adapting lean practices to each project’s needs can improve consistency and effectiveness. Integrating the supply chain is critical for lean’s success in construction, where supply chains are often fragmented. Close, continuous collaboration between suppliers, contractors and stakeholders is essential to ensure smooth material and information flows throughout the project lifecycle. Customer demands and project requirements drive organisations to adopt lean to achieve quality within budgetary and time constraints. However, the diverse needs of projects require organisations to adapt lean practices to meet specific client expectations and project goals.

In summary, the successful adoption of lean in construction is influenced by strong leadership, supportive organisational culture, employee engagement, adequate resources, clear communication, streamlined supply chain integration and responsiveness to customer demands. Addressing these factors enhances lean adoption, leading to greater efficiency, reduced waste and successful project outcomes.

Strategies focusing on leadership, training and technology integration have been developed to enhance lean implementation within organisations. Management is central in guiding senior and junior employees towards continuous improvement. A major challenge identified is the limited adoption of lean construction practices in NZ, prompting a shift in training approaches. Traditionally, training focused on lean practices without addressing specific organisational problems. This ineffective approach led to a revised strategy where problem identification comes first. Participants now prepare problem statements before training, focusing on solving real-world issues and measuring outcomes rather than just teaching tools. Figure 4 illustrates strategies to improve lean implementation, which are effective in case of emerging signs of project failure.

Figure 4

Strategies to improve lean implementation

Figure 4

Strategies to improve lean implementation

Close modal

Beyond training, some organisations have established communities of practice to encourage ongoing learning and implementation of lean principles in both work and personal settings. Social media platforms have also been introduced to share success stories, fostering broader engagement and promoting lean techniques. To further encourage lean adoption, some organisations have linked training to career progression, making it a requirement for promotions or internal transfers.

Training plays a crucial role in boosting confidence and enhancing performance. Offering incentives, such as promotions for completing lean training, motivates employees to engage actively and build a culture of continuous improvement within the organisation. BIM is mainly used in the planning phase, and its integration with lean principles remains underdeveloped. To fully leverage BIM’s potential in supporting lean construction, a more modular system or collaboration with external providers may be needed to extend its use throughout the project lifecycle. Data management also plays a crucial role in lean implementation. Organisations have adopted consolidated data models to streamline workflows, reduce errors and ensure projects are delivered according to client specifications. These systems centralise key project data, such as procurement and vendor information, to improve accuracy and efficiency.

In conclusion, strategies to enhance lean implementation focus on practical, problem-based training, continuous learning and better use of technology like BIM and centralised data systems to improve project outcomes and reduce waste.

Lean principles are increasingly adopted in the construction sector to improve efficiency, reduce waste and enhance project management. The Last Planner System (LPS) is commonly used in production, planning and scheduling, and it, combined with 3D modelling, provides visualisation for project operational stages (Heigermoser et al., 2019). Many organisations also incorporate lean Six Sigma principles, using continuous improvement techniques such as Kaizen, Fishbone diagrams, five whys and process mapping. Failure mode and effects analysis (FMEA) is employed to address operational problems effectively for complex issues. Figure 5 maps the current application of lean philosophy in the construction organisation.

Figure 5

Lean philosophy in construction

Figure 5

Lean philosophy in construction

Close modal

While LPS is widely used, it is not the only tool; another standard tool used is value stream mapping (VSM), and waste removal is also an essential tool in lean construction, helping to identify inefficiencies and streamline processes (Ramani and KSD, 2021). VSM enables organisations to visualise material and information flows, while waste removal focuses on eliminating non-value-adding activities (Rosenbaum et al., 2014). Despite these tools being widely implemented, challenges remain in fully standardising lean workflows. A lack of in-depth understanding of lean principles beyond tools like LPS limits its full integration. Nevertheless, organisations continue to apply these lean philosophies, contributing to better project outcomes and fostering continuous improvement within the sector.

BIM and lean construction principles are increasingly seen as complementary approaches to improve project outcomes. Figure 6 demonstrates how this is carried out in current construction practices. Both focus on reducing costs, enhancing transparency and boosting overall performance, making them a natural fit when integrated. By aligning their objectives of reducing waste and improving efficiency, the combination of BIM and lean can drive significant benefits throughout the construction process. BIM enhances lean construction by improving design and planning, providing a clear project view before construction. This early visualisation identifies conflicts, reduces costly revisions and aligns with lean’s goal of minimising waste and maximising value.

Figure 6

How BIM enhances lean construction

Figure 6

How BIM enhances lean construction

Close modal

BIM also enhances stakeholder collaboration by providing a shared platform that improves communication and coordination, which is essential for lean implementation. Better data sharing and visualisation help projects run smoothly, reducing delays and disruptions. However, the adoption of BIM in NZ is still limited. While increasingly used for asset management, many organisations do not fully utilise BIM during construction due to high costs and limited expertise (Moyo and Chigara, 2023).

In summary, BIM can provide valuable platforms for enhancing lean construction by improving productivity, reducing waste and supporting better project outcomes. When strategically applied, BIM and lean can work together to increase efficiency and optimise performance in construction projects.

Figure 7 illustrates some of the identified BIM tools used in construction organisations. BIM tools such as Synchro and Primavera are increasingly utilised in construction planning and facilities management to enhance efficiency and project outcomes. Synchro stands out for its ability to create detailed 3D models that help visualise the construction process, identify potential issues and improve sequencing. While Primavera is also used, Synchro is often preferred for its more comprehensive planning capabilities. In facilities management, BIM’s 3D models play a key role in asset identification and the development of maintenance plans. These models support more informed decision-making and improve the efficiency of ongoing building management tasks. However, while 3D modelling is widely used in maintenance, its application in construction planning is still evolving, with challenges such as high costs and limited expertise hindering broader adoption.

Figure 7

BIM tools used in construction organisations

Figure 7

BIM tools used in construction organisations

Close modal

Integrating BIM with lean construction principles offers significant potential for enhancing project outcomes. BIM supports lean’s objectives by improving transparency, reducing waste and identifying inefficiencies early in the project. Although BIM adoption faces barriers, particularly in terms of cost and skilled professionals, its strategic implementation can streamline processes and contribute to more efficient, value-driven construction projects. Combining BIM and lean principles can improve project performance and deliver greater value across the construction lifecycle.

The interviews found consensus viewpoints regarding the transformative potential of combining BIM and lean construction practices on NZ projects. The interview findings highlight critical insights into integrating lean practices and BIM in NZ’s construction industry and how BIM and lean-integrated practices can be improved in the construction sector. Figure 8 summarises the key findings of the interviews as a comprehensive mapping of BIM and lean construction practices. These findings are further developed into a guideline in the next section.

Figure 8

Comprehensive mapping of BIM-lean integration practices in construction

Figure 8

Comprehensive mapping of BIM-lean integration practices in construction

Close modal

Key challenges in lean implementation include coordination difficulties, resistance to change and a fragmented industry, further exacerbated by resource constraints, cultural inertia and a lack of standardised processes. Despite these obstacles, BIM is a crucial enabler of lean practices, offering tools like 3D modelling and clash detection that align with lean’s focus on reducing waste and improving efficiency. A study in Turkey highlighted how 4D BIM enhances labour productivity by integrating lean principles, particularly in scheduling and labour management. These findings echo interview observations about BIM’s transformative potential and underscore the need for expanded BIM training and integration into project management workflows (Karatas and Budak, 2023). Despite its potential, BIM adoption remains limited, with most organisations utilising it primarily in planning stages and for asset management.

Organisations are shifting towards problem-focused lean training, fostering employee engagement through incentives and linking training to career progression. Communities of practice and using social platforms to share success stories have also gained traction. Furthermore, organisations are exploring modular BIM systems to extend their application across project lifecycles. Lean philosophies, including the Last Planner System (LPS), Value Stream Mapping and waste reduction, are commonly employed, though a lack of deeper understanding limits their full potential. Collectively, these strategies aim to enhance lean and BIM integration, driving greater efficiency, collaboration and project success in NZ’s construction sector (Figure 8).

The discussions underscored the complementary nature of lean principles and BIM, both aimed at reducing costs, improving transparency and achieving KPIs to enhance performance. Strategic integration of both can significantly improve project outcomes. However, BIM is often used for isolated tasks rather than fully integrated with lean methodologies. Organisations must establish transparent, repeatable processes to ensure a clear understanding of lean principles. The unique nature of projects and fragmented supply chains complicate continuous improvement. Therefore, standardised workflows and an integrated network optimising the flow of goods, information and services are essential for effective lean practices and a cohesive supply chain. In the study of residential construction projects, Pérez et al. (2024), also echoed the recommendation to focus on early involvement of experienced managers and standardised workflows for consistency. They also suggested applying lean tools like value stream mapping in residential projects to enhance profitability.

Training and incentivising employees are vital for fostering a culture of continuous improvement. Managers need to help senior and junior employees utilise lean principles effectively by identifying problems before training to ensure the practical application is identified. Additionally, making lean training mandatory for promotions and internal transfers can ensure widespread adoption and understanding of lean principles. This includes training and empowering employees to use lean tools and techniques like 5S, Kaizen and Poka-Yoke to measure performance and meet goals continuously.

The most used lean tools are the Last Planner System, Value Stream Mapping and Waste Removal, indicating a need for broader lean education and application (Pérez et al., 2024). Using the Last Planner system and detailed scheduling for construction projects is an effective process. However, most organisations in NZ using the Last Planner system have limited knowledge of other lean principles. This aligns with the case study research on Dammam University’s new Administrative Sciences and Computer College building conducted by Eldeep et al. in 2022 in Egypt. The study demonstrated BIM’s potential as a lean tool to reduce waste, avoid cost overruns (11% of total contract price) and minimise delays (25% of contract time). It also complements the interview findings for early conflict identification to reduce waste and improve project timelines (Eldeep et al., 2022). Another recommendation was to focus on problem identification and project management principles tailored to each stage and the design process for off-site construction despite a lack of standardised workflow. These interview findings align well with the Solar Decathlon China (SDC) project in Dezhou, Shandong province, which emphasises standardised workflows and value stream mapping, demonstrating that BIM can enhance lean’s waste minimisation and sustainability objectives (Hei et al., 2024). Some other common and effective lean six-Sigma principles used in the construction sector involve employing physical boards for activity timelines, fishbone diagrams, five whys, process mapping, FMEA and brainstorming sessions, integrating lean with project management tools to enhance efficiency. Participants highlighted that bottleneck analysis, the just-in-time approach and the systematic testing and optimising approaches like Design of Experiments (DOE.) are also useful. Also, weekly coordination meetings would be helpful to prevent interference among subcontractors (Disney et al., 2024). As cost reduction and performance enhancement are significant drivers in government construction projects, implementing lean methodology through a top-down approach has benefited (Moradi and Sormunen, 2024).

Establishing a community of practices and using social media to share success stories were also suggested to foster engagement and create a culture of continuous improvement. Sharing success stories and KPIs helps motivate staff and promote integrated uptake of BIM lean models. Hence, effective management during the early stages of construction, such as integration and early involvement of experienced management in design and scheduling, is crucial for project success.

Participants suggested that BIM is integral to the lean process, providing insights into projects before construction begins, streamlining and enhancing the design and construction process. Since BIM helps identify conflicts early in the design phase, this enhances process waste minimisation objectives, which is the focus of lean during construction activities. Considerable time savings can be achieved with early identification of problem areas. For example, ISO (International Organisation for Standardisation) systems and consolidated data models streamline project management, reduce errors, standardise work processes and ensure quality and safety. Mapping value streams and creating flow is essential for eliminating waste. Visual management tools and early clash detection through BIM can save time and money (Bhattacharya and Mathur, 2023). Meanwhile, an organisation in the early stages of lean implementation employs tools such as takt time and continuous flow, along with bottleneck analyses, to identify areas for improvement and modernise construction methods. Takt time, which aligns production pace with customer demand to ensure smooth and efficient workflows (Power et al., 2024), helps balance output with demand. Similarly, applying the principle of continuous flow is a strategy aimed at reducing inventories and streamlining the construction process, serving as a mechanism to enhance the entire production system (Avelar et al., 2020). The Martin Army Community Hospital in Georgia, USA case study by Zhang et al. (2018) also reflects interview findings on BIM’s role in improving project transparency and reducing bottlenecks. The study validated BIM’s use to achieve lean principles, reducing rework, inventory and clashes. BIM enhanced safety and operational efficiency. This also supports the promotion of lean tools like the Last Planner System and enhanced coordination through BIM in NZ’s projects (Zhang et al., 2018).

Participants highlighted that lean principles and BIM aim to reduce costs, improve transparency and meet performance goals. Organisations are adopting lean practices, refining methods and using tools like takt time and continuous flow. However, challenges in NZ, including limited BIM usage and high associated costs, hinder its widespread adoption.

This section conceptualises the integration of BIM and lean construction principles based on the feedback received from industry experts. It also validates the findings and maps the interview results and concepts identified through the previous exploratory stage. This guideline consolidates expert insights and provides practical steps for effectively integrating BIM and lean principles throughout the construction phase, emphasising the complementary nature of these methodologies. By drawing on global best practices and acknowledging the specific challenges of BIM implementation in NZ, this guideline offers prescriptive recommendations suitable for organisations at various maturity levels in BIM and lean practices.

As highlighted in key studies (Das et al., 2023; Mollasalehi et al., 2018), the current practices in NZ reveal improvement opportunities due to varying maturity levels in BIM and lean applications. Rashidian et al. (2024) further support the need for guidelines that can be adopted by organisations with different levels of BIM, Integrated Project Delivery (IPD), and lean Construction (LC) maturity. The following recommendations address these needs using a structured approach to implementing BIM–lean strategies in construction projects.

This guideline aims to facilitate a more cohesive, efficient, and sustainable construction process by leveraging the strengths of BIM and lean methodologies to address common challenges in the NZ construction sector. This guideline offers a multi-layered approach for integrating lean and BIM principles into construction project phases. It is based on current best practices and is a practical guide rather than a rigid framework. Unlike a framework, which provides a structured, often theoretical model for understanding or addressing complex systems, a guideline is a step-by-step, operational tool designed for immediate application in real-world scenarios. While a framework outlines overarching principles or strategies, a guideline provides specific instructions and roles for achieving practical objectives. The guideline shown in Table 3 acknowledges the complementary strengths of lean and BIM methodologies and provides a structured pathway to improve efficiency, productivity and sustainability. It also accommodates varying maturity levels among stakeholders, offering adaptable practices to suit different organisations. The guideline is divided into several layers to clarify responsibilities and focus areas for different stages of construction, including key participants such as clients, contractors, consultants and other stakeholders.

Table 3

Guideline for BIM and lean integration for organisations in the construction phase

LayerActionParties involvedExpected outcomeAssessment/Evaluation metrics
1. Assessment, awareness, readiness and adoptionConduct readiness assessments to evaluate organisational and project team capability for BIM–lean adoptionContractors, BIM Manager, Project ManagerBaseline understanding of organisational readiness for integrationReadiness score (using surveys or checklists) and gap analysis report
Organise workshops on BIM and lean principles and benefitsContractors, ClientsImproved stakeholder awareness and alignmentParticipation rate and post-workshop feedback scores
Develop an adoption strategy tailored to project-specific needsBIM Manager, Lean FacilitatorsStrategic alignment with organisational objectivesDocumented strategy reviewed by stakeholders
2. Training and skill developmentDeliver hands-on, problem-based training sessions focused on practical toolsHR, BIM Manager, Lean FacilitatorsWorkforce equipped with practical BIM–lean integration skillsTraining participation rate and skills assessment scores
Link skill certifications and proficiency to career advancementHR, Senior LeadershipEnhanced motivation for upskilling and engagementCertification completion rate and career progression metrics
3. Stakeholder collaborationEstablish forums and professional communities for knowledge sharingIndustry Associations, BIM ManagersStronger collaboration and shared best practices across stakeholdersNumber of forums held and documented outcomes
Implement real-time communication platforms for streamlined updatesAll Project StakeholdersImproved coordination and issue resolutionUser engagement on communication platforms and feedback scores
4. Lean implementation strategiesEmbed problem identification and resolution exercises in trainingLean Facilitators, Project ManagersProactive issue resolution and bottleneck mitigationFrequency of identified and resolved issues
Make lean training mandatory for leadership rolesSenior LeadershipConsistent lean practices across the organisationTraining compliance and leadership engagement scores
5. Lean tools applicationApply early stage lean tools (e.g. takt time, value stream mapping)Project Managers, Lean SpecialistsReduced inefficiencies and wasteReduction in waste and process cycle times
Promote comprehensive adoption of the lean tool, including Kaizen and bottleneck analysisAll Team MembersBroader lean understanding and applicationDiversity of lean tools applied and team feedback
6. BIM–lean IntegrationDevelop and implement BIM-supported lean strategiesBIM Manager, Project Manager, Lean FacilitatorEffective alignment of BIM and lean objectivesNumber of BIM–lean processes integrated and reviewed
Address challenges like interoperability and user trainingBIM Coordinators, IT TeamsSeamless BIM adoption and lean supportReduced BIM-related delays and user satisfaction rates
7. Risk managementUse BIM tools for early risk identification and mitigationBIM Coordinators, Risk Management TeamsProactive risk reduction and project stabilityNumber of risks identified and mitigated through BIM
Apply lean principles to cost optimisation strategiesCost Analysts, Project ManagersCost-effective project deliveryCost savings achieved through lean implementation
8. Scheduling and continuous improvementUse just-in-time (JIT) scheduling to optimise resource allocationProject Managers, Site SupervisorsTimely and efficient project executionSchedule adherence and reduction in delays
Embed Kaizen principles for iterative improvementsAll Team MembersEnhanced productivity and quality through continuous improvementFrequency of Kaizen initiatives and measurable improvements
9. Preconstruction visualisationUse BIM to simulate and optimise designs before constructionDesign Teams, BIM ManagersReduced errors and enhanced stakeholder alignmentNumber of identified and resolved clashes during preconstruction
10. Monitoring and evaluationEstablish feedback-driven monitoring systems using BIM dataQuality Assurance Teams, BIM CoordinatorsImproved quality control and performance trackingFrequency of monitoring updates and issue resolution rates
Use BIM visualisation to maintain accuracy and standardsBIM Managers, Quality Assurance TeamsHigh-quality outputs meeting design specificationsFrequency of quality audits and compliance rates
11. Sustainability and regulatory alignmentAlign BIM–lean integration with sustainability objectivesEnvironmental Teams, Regulatory AuthoritiesReduced environmental impact and enhanced complianceWaste reduction metrics and sustainability audit results
12. Collaboration, communication, and coordinationPromote effective multi-stakeholder collaboration through structured BIM processesContractors, BIM Managers, Supply Chain ManagersStreamlined coordination and resource allocationNumber of coordination meetings and clash resolutions
Ensure real-time communication and transparency throughout projectsAll Project StakeholdersImproved decision-making and issue resolutionResponse times and stakeholder feedback scores

Source(s): Authors’ own creation

The proposed guideline provides a practical and adaptable approach to integrating BIM and lean methodologies into construction projects, focusing on accountability, collaboration and continuous improvement. It addresses the specific challenges of the NZ construction sector while accommodating organisations at varying maturity levels in adopting BIM and lean practices.

Structured across multiple layers, the guideline begins by emphasising assessment, awareness and readiness, ensuring stakeholders understand the benefits and are prepared for integration. Training and skill development initiatives foster a knowledgeable workforce and incentivise continuous learning, while collaboration and communication layers promote alignment through professional forums and real-time platforms. The guideline also details strategies for implementing lean tools and BIM-supported workflows to optimise processes, reduce waste and improve project outcomes. Layers dedicated to risk management, scheduling and continuous improvement leverage BIM’s visualisation and data capabilities to identify risks, enhance efficiency and support iterative process enhancements.

By integrating sustainability goals and regulatory alignment, the guideline ensures that construction processes meet environmental standards and remain forward-thinking. It offers a cohesive pathway to enhance efficiency, productivity, and sustainability through actionable steps, addressing both immediate and long-term goals for construction organisations. This comprehensive framework is tailored to help stakeholders achieve effective BIM–lean integration, driving value and success across construction projects.

The proposed guideline for integrating BIM and lean methodologies was validated through a structured expert elicitation process involving draft reviews and semi-structured interviews. Eight professionals (SME1 to 8), presented in Table 2 participated in the process. Discussions focused on three key areas: evaluating organisational readiness for BIM and lean integration, enhancing sustainability and regulatory alignment, and strengthening leadership and stakeholder collaboration. The diversity of participants ensured that the guideline was rigorously assessed across multiple dimensions of construction management, providing actionable insights to enhance its practical implementation and alignment with industry needs. The validation criteria results are included in this section:

  • (1)

    Clarity:

    • Experts agreed that the guideline was well-structured and comprehensible. One expert noted, “The logical flow and clear identification of responsibilities and actions make the guideline easy to follow.”

    • Methodology Justification: Clarity is essential for ensuring the guideline is accessible to stakeholders at various organisational levels, reducing the risk of misinterpretation (Eastman, 2011).

  • (2)

    Applicability:

    • Experts emphasised the practicality of the guideline in addressing common construction challenges, such as waste reduction and process inefficiencies. A BIM coordinator remarked, “The inclusion of readiness assessments and incremental implementation steps makes this guideline highly relevant.”

    • Methodology Justification: Applicability ensures that the guideline can be effectively implemented to solve real-world problems (Azhar et al., 2012; Salem et al., 2006).

  • (3)

    Alignment with industry practices:

    • Feedback highlighted the guideline’s alignment with industry priorities, including sustainability, cost optimisation and stakeholder collaboration. A facility manager noted, “The focus on BIM for risk mitigation andleanfor process improvement aligns with best practices.”

    • Methodology Justification: Industry alignment ensures the guideline reflects contemporary standards and practices, enhancing its credibility and acceptance (Abanda et al., 2017).

  • (4)

    Adaptability:

    • The layered approach was praised for allowing phased adoption. One project supervisor stated, “The guideline’s flexibility to scale up or down is critical for organisations with varying levels of maturity.”

    • Methodology Justification: Adaptability ensures the guideline is versatile and inclusive, accommodating diverse organisational capabilities and contexts (Lu et al., 2014).

The validation process confirmed that the proposed guidelines for integrating BIM and lean methodologies are clear, applicable, aligned with industry practices and adaptable to diverse organisational contexts. Experts praised its logical structure, highlighting the inclusion of readiness assessments and incremental pathways for phased adoption as particularly valuable. The guideline effectively addresses real-world construction challenges, such as waste reduction, process inefficiencies and stakeholder collaboration, while aligning with contemporary industry priorities like sustainability and cost optimisation. Its flexibility to accommodate organisations with varying levels of BIM and lean maturity ensures broad applicability, making it a robust, practical and versatile framework for enhancing efficiency, productivity and sustainability in the construction industry.

NZ’s construction sector faces several challenges, including a lack of popularity and understanding of BIM and lean applications, especially in the early planning and design stages. Management often overlooks the importance of early-stage IT improvements. Additionally, supply chain issues, with limited subcontractors and external factors like weather and COVID-19, complicate the adoption of lean techniques. Resistance to change is a significant barrier, as traditional methods dominate site mobilisation and equipment handling. This unfamiliarity leads to hesitation in adopting lean practices, which are viewed as risky without guaranteed returns. Political issues, material scarcity and a fragmented industry structure hinder lean implementation. A significant disconnect between design and construction teams leads to inefficiencies and wasted time-resolving clashes and modifications. The consensus among participants is that the strategic integration of lean and BIM leads to improved project outcomes by increasing value, minimising waste and streamlining processes. This is also in line with previous literature available where other integration challenges were discussed (Kordestani Ghalenoei et al., 2024; Likita and Jelodar, 2019).

Additionally, traditional thinking and a disconnect between the design and construction teams hinder the efficient implementation of lean practices. Other factors include political considerations, scarcity of building materials and a lack of understanding of lean construction. To overcome these challenges, the industry must invest in training and adopt modern construction methods, such as prefabrication and BIM, to increase productivity and efficiency while reducing energy costs and ensuring safety and well-being.

The findings indicate that NZ construction industry organisations use lean construction tools and principles to improve their processes and outcomes. By addressing the specific challenges identified in NZ’s construction sector and drawing on global best practices, the proposed guideline aims to facilitate a more cohesive and efficient construction process. This section provides specific recommendations for the industry based on the identified challenges, developed guidelines and findings from the literature:

  • Training and education: Developing comprehensive training programs to enhance understanding and skills in integrating BIM and lean in practice. This includes training in methodologies such as fishbone diagram analysis, bottleneck analysis, Just-In-Time (JIT) delivery and Six-Sigma principles, as highlighted by McDermott et al. (2024). Their work underscores that effective education programs are vital for building deep knowledge and facilitating the practical integration of lean-BIM practices in construction projects.

  • Leadership and support: Ensuring strong leadership and management support to drive the implementation of an integrated approach as emphasised by Mellado and Lou (2020).

  • Collaboration and communication: Promoting a culture of collaboration and open communication between project parties to facilitate seamless integration and continuous improvement during construction as Najafi et al. (2024) emphasise the importance of building trust, fostering knowledge sharing and utilising communication tools to align project goals and drive collective success.

  • Collaborative training initiatives: Encourage cross-disciplinary collaboration among architects, engineers, contractors and project managers through specialised training sessions to enhance mutual understanding and cooperation. Develop industry-specific training programs in collaboration with educational institutions, integrating practical lean and BIM modules into construction-related courses to ensure a skilled workforce (Tezel et al., 2020).

  • Lean communities of practice: Establish lean communities of practice within organisations and at the industry level to facilitate knowledge-sharing, experiences and best practices, fostering a culture of continuous improvement (Tezel et al., 2020).

  • Incentivised lean training: Collaborate with industry associations to incentivise lean training for career advancement, motivating professionals to acquire and apply lean expertise (Aziz and Zainon, 2023).

  • Standardised BIM adoption: Promote BIM as a standard practice in construction projects globally, fostering collaboration between BIM software providers, government bodies, and construction firms to address challenges and enhance integration (Zhan et al., 2022; Evans and Farrell, 2021).

  • Government-industry collaboration: Initiate pilot programs in collaboration with government bodies to overcome specific challenges unique to the NZ context, with insights gained informing policy changes and industry-wide improvements (Likita et al., 2024), like UK, Denmark, Netherlands, Norway and Finland, that require BIM for public works (ul Hassan et al., 2023).

  • Diverse BIM-lean implementation strategies: Encourage organisations to adopt a problem-centric lean approach beyond the Last Planner System while advocating for widespread adoption and integrating lean principles into global project management practices and BIM-based projects (Polat and Demirkesen, 2024).

  • Industry-wide collaboration: Foster a culture of continuous improvement through Kaizen principles globally, emphasising standardised BIM usage for communication and engaging in industry alliances for collective problem-solving.

  • Action drivers: Action drivers refer to the key sectors or stakeholders that play a crucial role in successfully integrating lean principles and BIM during the construction phase. These action drivers include the government, the construction sector, regulatory authorities, manufacturers and insurance companies, as indicated by van der Heijden (2024).

The study highlights the significant role of lean construction and BIM in the construction industry, as reported by the participants. BIM offers a range of benefits, including better collaboration and communication, improved design and planning and better asset management. However, there are challenges associated with its implementation, such as a lack of understanding and awareness of its benefits, high implementation costs and the absence of a skill set to maintain and use it effectively. Therefore, construction organisations must carefully evaluate the trade-off between the upfront cost of BIM implementation and its potential long-term benefits.

The participants' experiences and insights indicate that adopting BIM and lean principles can significantly benefit the construction industry. Emphasising detailed planning and risk identification through BIM can improve productivity and minimise delays. BIM can also help with sustainable practices, asset management and stakeholder collaboration. However, challenges still exist, such as adopting BIM by smaller constructors and using different BIM platforms, which can pose hurdles to effective collaboration. The participants in the study shed light on various approaches to implementing new construction management tools and techniques in their organisations, such as using dashboard techniques to monitor project progress, forming working groups or hiring external consultants to provide fresh perspectives and customised guidelines for implementing new tools and creating a separate department focused on modernising construction methodology. These diverse approaches highlight the importance of continuous improvement and innovation in the construction industry to enhance efficiency, quality, and sustainability. The study emphasises the value of implementing BIM and lean principles in the construction industry to achieve better outcomes. Overall, implementing lean principles and tools in the NZ construction industry shows promise in improving the efficiency and effectiveness of construction projects. Although highly beneficial, NZ does not fully realise the full potential of combining BIM with lean.

The study also acknowledges the limited adoption of BIM in NZ due to high costs and lack of expertise, which could hinder the proposed integration with lean practices. The evolving nature of BIM and lean methodologies suggests that the findings and guidelines may require regular updates to remain relevant. The reliance on expert opinions introduces potential bias. Although rich in detail, the study’s regional focus on NZ might restrict the applicability of its findings to other regions with different industry practices, regulations and cultural contexts. Addressing these limitations in future research could improve the robustness and broader applicability of the proposed integration guideline.

Abanda
,
F.
,
Tah
,
J.
and
Cheung
,
F.
(
2017
), “
BIM in off-site manufacturing for buildings
”,
Journal of Building Engineering
, Vol. 
14
, pp. 
89
-
102
, doi: .
Amirtash
,
P.
,
Parchami Jalal
,
M.
and
Jelodar
,
M.B.
(
2021
), “
Integration of project management services for international engineering, procurement and construction projects
”,
Built Environment Project and Asset Management
, Vol. 
11
No. 
2
, pp. 
330
-
349
, doi: .
Andújar-Montoya
,
M.D.
,
Galiano-Garrigós
,
A.
,
Echarri-Iribarren
,
V.
and
Rizo-Maestre
,
C.
(
2020
), “
BIM-LEAN as a methodology to save execution costs in building construction—an experience under the Spanish framework
”,
Applied Sciences
, Vol. 
10
No. 
6
, p.
1913
, doi: .
Arayici
,
Y.
,
Tokdemir
,
O.B.
and
Kassem
,
M.
(
2023
), “
A quantitative, evidence-based analysis of correlations between lean construction and building information modelling
”,
Smart and Sustainable Built Environment
, Vol. 
12
No. 
5
, pp. 
975
-
1001
, doi: .
Avelar
,
W.
,
Meiriño
,
M.
and
Tortorella
,
G.L.
(
2020
), “
The practical relationship between continuous flow and lean construction in SMEs
”,
The TQM Journal
, Vol. 
32
No. 
2
, pp. 
362
-
380
, doi: .
Azhar
,
S.
,
Khalfan
,
M.
and
Maqsood
,
T.
(
2012
), “
Building information modeling (BIM): now and beyond
”,
Australasian Journal of Construction Economics and Building, The
, Vol. 
12
No. 
4
, pp. 
15
-
28
, doi: .
Aziz
,
N.M.
and
Zainon
,
N.
(
2023
), “
Driving factors for lean-BIM implementation in Malaysia's construction industry: qualitative interview-based study
”,
Smart and Sustainable Built Environment
, Vol. 
12
No. 
4
, pp. 
872
-
891
, doi: .
Babaeian Jelodar
,
M.
and
Shu
,
F.
(
2021
), “
Innovative use of low-cost digitisation for smart information systems in construction projects
”,
Buildings
, Vol. 
11
No. 
7
, p.
270
, doi: ,
available at:
https://www.mdpi.com/2075-5309/11/7/270
Barkokebas
,
B.
,
Khalife
,
S.
,
Al-Hussein
,
M.
and
Hamzeh
,
F.
(
2021
), “
A BIM-lean framework for digitalisation of premanufacturing phases in offsite construction
”,
Engineering, Construction and Architectural Management
, Vol. 
28
No. 
8
, pp. 
2155
-
2175
, doi: .
Bayhan
,
H.G.
,
Demirkesen
,
S.
,
Zhang
,
C.
and
Tezel
,
A.
(
2023
), “
A lean construction and BIM interaction model for the construction industry
”,
Production Planning and Control
, Vol. 
34
No. 
15
, pp. 
1447
-
1474
, doi: .
Bhattacharya
,
S.
and
Mathur
,
A.
(
2023
), “
Synergising lean objectives through BIM to enhance productivity and performance
”,
International Journal of Productivity and Performance Management
, Vol. 
72
No. 
7
, pp. 
2135
-
2154
, doi: .
Bradley
,
A.
,
Li
,
H.
,
Lark
,
R.
and
Dunn
,
S.
(
2016
), “
BIM for infrastructure: an overall review and constructor perspective
”,
Automation in Construction
, Vol. 
71
, pp. 
139
-
152
, doi: .
Chang
,
Y.-T.
and
Hsieh
,
S.-H.
(
2020
), “
A review of building information modeling research for green building design through building performance analysis
”,
Journal of Information Technology in Construction (ITcon)
, Vol. 
25
, pp. 
1
-
40
, doi: .
Chen
,
P.
and
Partington
,
D.
(
2004
), “
An interpretive comparison of Chinese and Western conceptions of relationships in construction project management work
”,
International Journal of Project Management
, Vol. 
22
No. 
5
, pp.
397
-
406
.
Das
,
P.
,
Perera
,
S.
,
Senaratne
,
S.
and
Osei-Kyei
,
R.
(
2023
), “
A smart modern construction enterprise maturity model for business scenarios leading to Industry 4.0
”,
Smart and Sustainable Built Environment
, Vol. 
14
No. 
1
, pp. 
23
-
49
, doi: .
Dauda
,
J.A.
,
Ajayi
,
S.
,
Omotayo
,
T.
,
Oladiran
,
O.O.
and
Ilori
,
O.M.
(
2024
), “
Implementation of lean for small- and medium-sized construction organisational improvement
”,
Smart and Sustainable Built Environment
, Vol. 
13
No. 
3
, pp. 
496
-
511
, doi: .
Dave
,
B.
,
Kubler
,
S.
,
Främling
,
K.
and
Koskela
,
L.
(
2016
), “
Opportunities for enhanced lean construction management using Internet of Things standards
”,
Automation in Construction
, Vol. 
61
, pp. 
86
-
97
, doi: .
Demirkesen
,
S.
and
Ozorhon
,
B.
(
2017
), “
Measuring project management performance: case of construction industry
”,
Engineering Management Journal
, Vol. 
29
No. 
4
, pp. 
258
-
277
, doi: .
Disney
,
O.
,
Roupé
,
M.
,
Johansson
,
M.
and
Domenico Leto
,
A.
(
2024
), “
Embracing BIM in its totality: a total BIM case study
”,
Smart and Sustainable Built Environment
, Vol. 
13
No. 
3
, pp. 
512
-
531
, doi: .
Doan
,
D.T.
,
GhaffarianHoseini
,
A.
,
Naismith
,
N.
,
Ghaffarianhoseini
,
A.
,
Zhang
,
T.
and
Tookey
,
J.
(
2021
), “
Examining critical perspectives on building information modelling (BIM) adoption in NZ
”,
Smart and Sustainable Built Environment
, Vol. 
10
No. 
4
, pp. 
594
-
615
, doi: .
Eastman
,
C.M.
(
2011
),
BIM Handbook: A Guide to Building Information Modeling for Owners, Managers, Designers, Engineers and Contractors
,
John Wiley and Sons
,
Hoboken, NJ
.
El-Diraby
,
T.
,
Krijnen
,
T.
and
Papagelis
,
M.
(
2017
), “
BIM-based collaborative design and socio-technical analytics of green buildings
”,
Automation in Construction
, Vol. 
82
, pp. 
59
-
74
, doi: .
El Mounla
,
K.
,
Beladjine
,
D.
,
Beddiar
,
K.
and
Mazari
,
B.
(
2023
), “
Lean-BIM approach for improving the performance of a construction project in the design phase
”,
Buildings
, Vol. 
13
No. 
3
, p.
654
, doi: .
Eldeep
,
A.M.
,
Farag
,
M.A.
and
Abd El-hafez
,
L.M.
(
2022
), “
Using BIM as a lean management tool in construction processes–a case study
”,
Ain Shams Engineering Journal
, Vol. 
13
No. 
2
, 101556, doi: .
Evans
,
M.
and
Farrell
,
P.
(
2021
), “
Barriers to integrating building information modelling (BIM) and lean construction practices on construction mega-projects: a Delphi study
”,
Benchmarking: An International Journal
, Vol. 
28
No. 
2
, pp. 
652
-
669
, doi: .
Evans
,
M.
and
Farrell
,
P.
(
2023
), “
A strategic framework managing challenges of integrating lean construction and integrated project delivery on construction megaprojects, towards global integrated delivery transformative initiatives in multinational organisations
”,
Journal of Engineering, Design and Technology
, Vol. 
21
No. 
2
, pp. 
376
-
416
, doi: .
Evans
,
M.
,
Farrell
,
P.
,
Mashali
,
A.
and
Zewein
,
W.
(
2021
), “
Critical success factors for adopting building information modelling (BIM) and lean construction practices on construction mega-projects: a Delphi survey
”,
Journal of Engineering, Design and Technology
, Vol. 
19
No. 
2
, pp. 
537
-
556
, doi: .
Forbes
,
L.H.
and
Ahmed
,
S.M.
(
2010
),
Modern Construction: Lean Project Delivery and Integrated Practices
,
CRC Press
,
Boca Raton, FL
. doi: .
Friese
,
S.
,
Soratto
,
J.
and
Pires
,
D.
(
2018
), “
Carrying out a computer-aided thematic content analysis with ATLAS.ti
”,
MMG Working Paper
, pp. 
18
-
02
,
available at:
https://hdl.handle.net/21.11116/0000-0001-364E-C
Gerber
,
D.J.
,
Becerik-Gerber
,
B.
and
Kunz
,
A.
(
2010
), “
Building information modeling and lean construction: technology, methodology and advances from practice
”,
Proceedings IGLC
,
Technion
, Vol. 
18
, pp. 
683
-
693
.
Ghosh
,
A.
,
Parrish
,
K.
and
Chasey
,
A.D.
(
2013
), “
From BIM to collaboration: a proposed integrated construction curriculum
”,
2013 ASEE Annual Conference and Exposition
,
Atlanta, Georgia
, pp. 
23.618.1
-
23.618.9
, doi: .
Glaser
,
B.G.
and
Strauss
,
A.L.
(
2017
), “Theoretical sampling”,
Sociological Methods
,
Routledge
, pp.
105
-
114
.
Hei
,
S.
,
Zhang
,
H.
,
Luo
,
S.
,
Zhang
,
R.
,
Zhou
,
C.
,
Cong
,
M.
and
Ye
,
H.
(
2024
), “
Implementing BIM and lean construction methods for the improved performance of a construction project at the disassembly and reuse stage: a case study in Dezhou, China
”,
Sustainability
, Vol. 
16
No. 
2
, p. 
656
, doi: .
Heigermoser
,
D.
,
García de Soto
,
B.
,
Abbott
,
E.L.S.
and
Chua
,
D.K.H.
(
2019
), “
BIM-based last planner system tool for improving construction project management
”,
Automation in Construction
, Vol. 
104
, pp. 
246
-
254
, doi: .
Jelodar
,
M.B.
and
Yiu
,
T.W.
(
2012
), “
Evaluation of relationship quality in construction cases using a process model of conflict and disputes in project management
”,
The 8th International Project Management Conference (IPMC2012)
,
Tehran-Iran
,
available at:
https://www.en.symposia.ir/IPMC08 (
accessed
 26 August 2007).
Jelodar
,
M.B.
,
Yiu
,
T.W.
and
Wilkinson
,
S.
(
2014
), “A multi-objective decision support system for selecting dispute resolution methods in the construction industry”, in
Computing in Civil and Building Engineering
, pp. 
1642
-
1649
, doi: .
Karatas
,
I.
and
Budak
,
A.
(
2023
), “
Investigating the impact of lean-BIM synergy on labor productivity in the construction execution phase
”,
Journal of Engineering Research
, Vol. 
11
No. 
4
, pp. 
322
-
333
, doi: .
Koo
,
B.
and
Fischer
,
M.
(
2000
), “
Feasibility study of 4D CAD in commercial construction
”,
Journal of Construction Engineering and Management
, Vol. 
126
No. 
4
, pp. 
251
-
260
, doi: .
Kordestani Ghalenoei
,
N.
,
Babaeian Jelodar
,
M.
,
Paes
,
D.
and
Sutrisna
,
M.
(
2024
), “
Challenges of offsite construction and BIM implementation: providing a framework for integration in NZ
”,
Smart and Sustainable Built Environment
, Vol. 
13
No. 
4
, pp.
780
-
808
, doi: .
Koseoglu
,
O.
,
Sakin
,
M.
and
Arayici
,
Y.
(
2018
), “
Exploring the BIM and lean synergies in the Istanbul Grand Airport construction project
”,
Engineering, Construction and Architectural Management
, Vol. 
25
No. 
10
, pp. 
1339
-
1354
, doi: .
Kuo
,
C.-H.
,
Tsai
,
M.-H.
and
Kang
,
S.-C.
(
2011
), “
A framework of information visualization for multi-system construction
”,
Automation in Construction
, Vol. 
20
No. 
3
, pp. 
247
-
262
, doi: .
Lapinski
,
A.R.
,
Horman
,
M.J.
and
Riley
,
D.R.
(
2006
), “
Lean processes for sustainable project delivery
”,
Journal of Construction Engineering and Management
, Vol. 
132
No. 
10
, pp. 
1083
-
1091
, doi: .
Likita
,
A.J.
and
Jelodar
,
M.B.
(
2019
),
An Overview Challenges of BIM and Lean Construction Implementation in NZ Construction Industry
,
The 43rd Australasian Universities Building Education Association (AUBEA)
,
Noosa
, pp. 
714
-
723
,
ISBN: 9781921047510, available at:
https://www.cqu.edu.au/__data/assets/pdf_file/0020/114635/AUBEA-Conference-2019-Program.pdf
Likita
,
A.J.
,
Jelodar
,
M.B.
and
Rotimi
,
J.
(
2020
), “
Lean philosophy and BIM for productivity in NZ construction, Massey University, NZ
”,
6th NZ Built Environment Research Symposium (NZBERS 2020)
,
Auckland, NZ
,
ISSN 2463-4905, available at:
https://nzbers.massey.ac.nz/wp-content/uploads/2020/03/Proceedings-NZBERS-Feb2020.pdf
Likita
,
A.J.
,
Jelodar
,
M.B.
,
Vishnupriya
,
V.
,
Rotimi
,
J.O.B.
and
Vilasini
,
N.
(
2022
), “
Lean and BIM implementation barriers in NZ construction practice
”,
Buildings
, Vol. 
12
No. 
10
, p.
1645
, doi: ,
available at:
https://www.mdpi.com/2075-5309/12/10/1645
Likita
,
A.J.
,
Jelodar
,
M.B.
,
Vishnupriya
,
V.
and
Rotimi
,
J.O.B.
(
2024
), “
Lean and BIM integration benefits construction management practices in NZ
”,
Construction Innovation
, Vol. 
24
No. 
1
, pp. 
106
-
133
, doi: .
Lu
,
W.
,
Fung
,
A.
,
Peng
,
Y.
,
Liang
,
C.
and
Rowlinson
,
S.
(
2014
), “
Cost-benefit analysis of building information modeling implementation in building projects through demystification of time-effort distribution curves
”,
Building and Environment
, Vol. 
82
, pp. 
317
-
327
, doi: .
Maraqa
,
M.J.
,
Sacks
,
R.
and
Spatari
,
S.
(
2021
), “
Quantitative assessment of the impacts of BIM and lean on process and operations flow in construction projects
”,
Engineering, Construction and Architectural Management
, Vol. 
28
No. 
8
, pp. 
176
-
2198
, doi: .
McDermott
,
O.
,
Odwyer
,
K.
,
Noonan
,
J.
,
Trubetskaya
,
A.
and
Rosa
,
A.
(
2024
), “
The development of a lean six sigma and BIM framework for enhancing off-site manufacturing
”,
International Journal of Lean Six Sigma
, Vol. 
15
No. 
8
, pp. 
50
-
69
, doi: .
McKinney
,
K.
and
Fischer
,
M.
(
1998
), “
Generating, evaluating and visualizing construction schedules with CAD tools
”,
Automation in Construction
, Vol. 
7
No. 
6
, pp. 
433
-
447
, doi: .
Mellado
,
F.
and
Lou
,
E.C.
(
2020
), “
Building information modelling, lean and sustainability: an integration framework to promote performance improvements in the construction industry
”,
Sustainable Cities and Society
, Vol. 
61
, 102355, doi: .
Mollasalehi
,
S.
,
Aboumoemen
,
A.A.
,
Rathnayake
,
A.
,
Fleming
,
A.
and
Underwood
,
J.
(
2018
), “
Development of an integrated BIM and lean maturity model
”,
26th Annual Conference of the International Group for Lean Construction
, pp. 
1217
-
1228
, doi: .
Moradi
,
S.
and
Sormunen
,
P.
(
2024
), “
Integrating lean construction with BIM and sustainability: a comparative study of challenges, enablers, techniques, and benefits
”,
Construction Innovation
, Vol. 
24
No. 
7
, pp. 
188
-
203
, doi: .
Moyo
,
T.
and
Chigara
,
B.
(
2023
), “
Barriers to lean construction implementation in Zimbabwe
”,
Journal of Engineering, Design and Technology
, Vol. 
21
No. 
3
, pp. 
733
-
757
, doi: .
Najafi
,
M.
,
Sheikhkhoshkar
,
M.
and
Rahimian
,
F.
(
2024
), “
Innovation and lean practices for sustainable construction project management; emerging technologies, strategies and challenges
”,
Smart and Sustainable Built Environment
, Vol. 
13
No. 
3
, pp. 
473
-
478
, doi: .
Omrany
,
H.
,
Ghaffarianhoseini
,
A.
,
Ghaffarianhoseini
,
A.
and
Clements-Croome
,
D.J.
(
2023
), “
The uptake of City Information Modelling (CIM): a comprehensive review of current implementations, challenges and future outlook
”,
Smart and Sustainable Built Environment
, Vol. 
12
No. 
5
, pp. 
1090
-
1116
, doi: .
Pérez
,
Y.
,
Ávila
,
J.
and
Sánchez
,
O.
(
2024
), “
Influence of BIM and Lean on mitigating delay factors in building projects
”,
Results in Engineering
, Vol. 
22
, 102236, doi: .
Polat
,
F.
and
Demirkesen
,
S.
(
2024
), “
Measuring the impact of lean implementation on BIM and project success: case of construction firms
”,
Engineering, Construction and Architectural Management
, Vol.
ahead-of-print No. ahead-of-print
, doi: .
Power
,
W.
,
Sinnott
,
D.
and
Lynch
,
P.
(
2024
), “
Synthesizing Last Planner® system, takt, and scrum theory and practice to enhance construction project delivery
”,
Lean Construction Journal
, Vol. 
2024
, pp. 
16
-
28
, doi: .
Ramani
,
P.V.
and
Ksd
,
L.K.L.
(
2021
), “
Application of lean in construction using value stream mapping
”,
Engineering, Construction and Architectural Management
, Vol. 
28
No. 
1
, pp. 
216
-
228
, doi: .
Rasanjali
,
W.A.
,
Mendis
,
A.P.K.D.
,
Perera
,
B.A.K.S.
and
Disaratna
,
V.
(
2024
), “
Implementing enterprise resource planning for lean waste minimisation: challenges and proposed strategies
”,
Smart and Sustainable Built Environment
, Vol. 
13
No. 
2
, pp. 
330
-
353
, doi: .
Rashidi
,
A.
,
Najafi
,
M.
,
Arashpour
,
M.
,
Moehler
,
R.
,
Bai
,
Y.
and
Rahimian
,
F.
(
2024
), “
Guest editorial: embracing the future construction project lifecycle: education and training for construction 4.0
”,
Smart and Sustainable Built Environment
, Vol. 
13
No. 
4
, pp. 
757
-
762
, doi: .
Rashidian
,
S.
,
Drogemuller
,
R.
and
Omrani
,
S.
(
2024
), “
An integrated building information modelling, integrated project delivery and lean construction maturity model
”,
Architectural Engineering and Design Management
, Vol. 
20
No. 
6
, pp. 
1454
-
1470
, doi: .
Ren
,
X.
,
Nane
,
G.F.
,
Terwel
,
K.C.
and
van Gelder
,
P.H.A.J.M.
(
2024
), “
Measuring the impacts of human and organizational factors on human errors in the Dutch construction industry using structured expert judgement
”,
Reliability Engineering and System Safety
, Vol. 
244
, 109959,
available at:
.
Rosenbaum
,
S.
,
Toledo
,
M.
and
González
,
V.
(
2014
), “
Improving environmental and production performance in construction projects using value-stream mapping: case study
”,
Journal of Construction Engineering and Management
, Vol. 
140
No. 
2
, 04013045, doi: .
Salem
,
O.
,
Solomon
,
J.
,
Genaidy
,
A.
and
Minkarah
,
I.
(
2006
), “
Lean construction: from theory to implementation
”,
Journal of Management in Engineering
, Vol. 
22
No. 
4
, pp. 
168
-
175
, doi: .
Sbiti
,
M.
,
Beddiar
,
K.
,
Beladjine
,
D.
,
Perrault
,
R.
and
Mazari
,
B.
(
2021
), “
Toward BIM and LPS data integration for lean site project management: a state-of-the-art review and recommendations
”,
Buildings
, Vol. 
11
No. 
5
, p.
196
, doi: .
Schimanski
,
C.P.
,
Marcher
,
C.
,
Pasetti Monizza
,
G.
and
Matt
,
D.T.
(
2020
), “
The Last Planner® system and building information modeling in construction execution: from an integrative review to a conceptual model for integration
”,
Applied Sciences
, Vol. 
10
No. 
3
, p.
821
, doi: .
Schimanski
,
C.P.
,
Pradhan
,
N.L.
,
Chaltsev
,
D.
,
Monizza
,
G.P.
and
Matt
,
D.T.
(
2021
), “
Integrating BIM with lean construction approach: functional requirements and production management software
”,
Automation in Construction
, Vol. 
132
, 103969.
Shoar
,
S.
,
Yiu
,
T.W.
,
Payan
,
S.
and
Parchamijalal
,
M.
(
2023
), “
Modeling cost overrun in building construction projects using the interpretive structural modeling approach: a developing country perspective
”,
Engineering, Construction and Architectural Management
, Vol. 
30
No. 
2
, pp. 
365
-
392
, doi: .
Siriwardhana
,
S.
and
Moehler
,
R.
(
2024
), “
Mastering the skills of construction 4.0: a review of the literature using science mapping
”,
Smart and Sustainable Built Environment
, Vol. 
13
No. 
4
, pp. 
989
-
1014
, doi: .
Succar
,
B.
(
2009
), “
Building information modelling framework: a research and delivery foundation for industry stakeholders
”,
Automation in Construction
, Vol. 
18
No. 
3
, pp. 
357
-
375
, doi: .
Tezel
,
A.
,
Taggart
,
M.
,
Koskela
,
L.
,
Tzortzopoulos
,
P.
,
Hanahoe
,
J.
and
Kelly
,
M.
(
2020
), “
Lean construction and BIM in small and medium-sized enterprises (SMEs) in construction: a systematic literature review
”,
Canadian Journal of Civil Engineering
, Vol. 
47
No. 
2
, pp. 
186
-
201
, doi: .
ul Hassan
,
F.
,
Nguyen
,
T.
,
Le
,
T.
and
Le
,
C.
(
2023
), “
Automated prioritization of construction project requirements using machine learning and fuzzy failure mode and effects analysis (FMEA)
”,
Automation in Construction
, Vol. 
154
, 105013, doi: .
van der Heijden
,
J.
(
2024
), “
Public governance in the context of construction 4.0: a systematic and comprehensive literature review
”,
Smart and Sustainable Built Environment
, Vol. 
13
No. 
3
, pp. 
737
-
756
, doi: .
Zhan
,
Z.
,
Tang
,
Y.
,
Wang
,
C.
,
Yap
,
J.B.H.
and
Lim
,
Y.S.
(
2022
), “
System dynamics outlook on BIM and LEAN interaction in construction quantity surveying
”,
Iranian Journal of Science and Technology, Transactions of Civil Engineering
, Vol. 
46
No. 
5
, pp. 
1
-
16
, doi: .
Zhang
,
X.
,
Azhar
,
S.
,
Nadeem
,
A.
and
Khalfan
,
M.
(
2018
), “
Using building information modelling to achieve lean principles by improving efficiency of work teams
”,
International Journal of Construction Management
, Vol. 
18
No. 
4
, pp. 
293
-
300
, doi: .
Abdal Noor
,
B.
and
Yi
,
S.
(
2018
), “
Review of BIM literature in construction industry and transportation: meta-analysis
”,
Construction Innovation
, Vol. 
18
No. 
4
, pp. 
433
-
452
, doi: .
Ahuja
,
R.
,
Sawhney
,
A.
and
Arif
,
M.
(
2017
), “
Driving lean and green project outcomes using BIM: a qualitative comparative analysis
”,
International Journal of Sustainable Built Environment
, Vol. 
6
No. 
1
, pp. 
69
-
80
, doi: .
Assaad
,
R.
,
El-adaway
,
I.H.
,
Hakea
,
A.H.E.
,
Parker
,
M.J.
,
Henderson
,
T.I.
,
Salvo
,
C.R.
and
Ahmed
,
M.O.
(
2020
), “
Contractual perspective for BIM utilization in US construction projects
”,
Journal of Construction Engineering and Management
, Vol. 
146
No. 
12
, 04020128, doi: .
Bae
,
J.-W.
and
Kim
,
Y.-W.
(
2008
), “
Sustainable value on construction projects and lean construction
”,
Journal of Green Building
, Vol. 
3
No. 
1
, pp. 
156
-
167
, doi: .
Banduka
,
N.
,
Veza
,
I.
and
Bilic
,
B.
(
2016
), “
An integrated lean approach to Process Failure Mode and Effect Analysis (PFMEA): a case study from automotive industry
”,
Advances in Production Engineering and Management
, Vol. 
11
No. 
4
, pp. 
355
-
365
, doi: .
Barlish
,
K.
and
Sullivan
,
K.
(
2012
), “
How to measure the benefits of BIM—a case study approach
”,
Automation in Construction
, Vol. 
24
, pp. 
149
-
159
, doi: .
Bergmiller
,
G.G.
and
McCright
,
P.R.
(
2009
), “
Parallel models for lean and green operations
”,
Proceedings of the 2009 Industrial Engineering Research Conference
, Vol. 
1
No. 
1
, pp. 
22
-
26
,
Tampa, FL, USA: University of South Florida and Zero Waste Operations Research and Consulting, available at:
https://citeseerx.ist.psu.edu/document?repid=rep1&type=pdf&doi=0a67c7f0f6d60ba0506e037aaf17cfe8b3a89e7d
BIM Acceleration Committee
(
2017
), “
BIM acceleration committee – three year report (BIM: better building process – building better performance
”,
Issue, available at:
https://static1.squarespace.com/static/57390d2c8259b53089bcf066/t/59784c59ff7c50cc2d3a9fd8/1501056093902/BAC+-+3+Year+Report.+-+July+2017.pdf (
accessed
 26 August 2024).
Cheng
,
M.
and
Lu
,
Y.
(
2015
), “
Developing a risk assessment method for complex pipe jacking construction projects
”,
Automation in Construction
, Vol. 
58
, pp. 
48
-
59
, doi: .
Giel
,
B.
and
Issa
,
R.R.A.
(
2016
), “
Framework for evaluating the BIM competencies of facility Owners
”,
Journal of Management in Engineering
, Vol. 
32
No. 
1
, 04015024, doi: .
Mehrbod
,
S.
,
Staub-French
,
S.
,
Mahyar
,
N.
and
Tory
,
M.
(
2019
), “
Characterizing interactions with BIM tools and artifacts in building design coordination meetings
”,
Automation in Construction
, Vol. 
98
, pp. 
195
-
213
, doi: .
Published by Emerald Publishing Limited. This article is published under the Creative Commons Attribution (CC BY 4.0) licence. Anyone may reproduce, distribute, translate and create derivative works of this article (for both commercial and non-commercial purposes), subject to full attribution to the original publication and authors. The full terms of this licence may be seen at http://creativecommons.org/licences/by/4.0/legalcode