It was December 13, 2010. The Government of Uttar Pradesh announced their plan to urbanize the entire area along the Yamuna Expressway (YE) in order to prevent haphazard growth of urban sprawls on the flanks of the YE. The YE was conceived in 1997 as a dream project of Ms Mayawati, the then Chief Minister of Uttar Pradesh, with the idea of reducing the travel time between Delhi (and the larger National Capital Region) and Agra. It was a 165 km long expressway and was proposed to run from Greater Noida to Agra via Mathura. Amidst issues concerning land acquisition, and various protests and litigations, the deadline for completion of the project had extended beyond its original completion date of February 8, 2010 to April 2013. Meanwhile, the project cost had escalated from Rs 2500 crore (cr) in the year 2000 to about Rs 10,000 cr as of December 2010. By then, about 80% work on the expressway had been completed. The project was finally expected to be completed around April 2011. This was, however, subject to the pending court judgements and mitigation of risks as perceived by Jaypee Infratech, the concessionaire of the project.
Article navigation
Case Study|
May 18 2011
The Yumana Expressway Available to Purchase
We acknowledge the research support provided by Poojan Chokshi.
Received:
July 17 2020
Online ISSN: 1111-111X
Print ISSN: 1111-111X
© 2011 by the Indian Institute of Management, Ahmedabad
2011
Indian Institute of Management, Ahmedabad
Licensed re-use rights only. Cases of the Indian Institute of Management, Ahmedabad, are prepared as a basis for classroom discussion. They are not designed to present illustrations of either correct or incorrect handling of administrative problems.
Teaching Notes 1–39.
Article history
Received:
July 17 2020
Connected Content
Teaching Notes:
The Yumana Expressway
See also
-
relatedCaseResource
Citation
Raghuram G, Mehta P (2011;), "The Yumana Expressway". Teaching Notes, Vol. ahead-of-print No. ahead-of-print.
Download citation file:
Email alerts
Suggested Reading
The Yumana Expressway
Indian Institute of Management Ahmedabad (May,2011)
An investigation into the use of compulsory acquisitions by agreement
Property Management (March,1997)
No way to say “no”: Stakeholder analysis for compulsory purchase for public infrastructure project in Australia
Property Management (February,2018)
Legal and regulatory framework for mobile banking in Tanzania
International Journal of Law and Management (August,2023)
A risk-adjusted decoupled-net-present-value model to determine the optimal concession period of BOT projects
Built Environment Project and Asset Management (September,2020)
Related Chapters
The Challenges and Socioeconomic Impacts of Proposed Road Development to Gunung Mulu National Park, Sarawak, Malaysia: A Case Study of Local Community Perspectives on Sustainable Tourism
The Emerald Handbook of Tourism Economics and Sustainable Development
Chapter 15 Public Inputs, Urban Development, and Welfare in a Developing Economy
Contemporary and Emerging Issues in Trade Theory and Policy
Competitiveness of Cities and Their Regions in Poland – Changes in the Light of the Growth Pole Concept
Core-Periphery Patterns Across the European Union: Case Studies and Lessons from Eastern and Southern Europe
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.