Purpose

This study applied the lean approach to the reinforcement work process in the component production of industrialised building system precast concrete construction (IBSPCC). The purpose of this paper is to identify and eliminate non-value added (NVA) activities to enhance the efficiency of the production process.

Design/methodology/approach

Data were collected via a case study of six-storey precast concrete building. A mapping of the reinforcement work process was conducted based on observations using time study technique and time-lapsed video, complemented by semi-structured interviews.

Findings

Through this application, several NVA activities, such as unnecessary inventory, excessive movement and coordination issues, were identified. Production performance could be enhanced by implementing Just-in-Time, Kanban, and layout improvements, which would address NVA activities.

Research limitations/implications

Due to the complexity of the construction process, only specific process elements were observed. To map the complete process, comprehensive observation must be conducted from beginning to end, which, though worthwhile, would be very time and resource intensive.

Originality/value

This paper focusses on strategies for improving the efficiency of the IBSPCC production process in Malaysian construction by developing a conceptual framework of the lean approach for the reinforcement work process. Certain aspects in the process such as layout and inventory need to be redesigned and simplified by minimising NVA activities.

Licensed re-use rights only
You do not currently have access to this content.
Don't already have an account? Register

Purchased this content as a guest? Enter your email address to restore access.

Please enter valid email address.
Email address must be 94 characters or fewer.
Pay-Per-View Access
$39.00
Rental

or Create an Account

Close Modal
Close Modal

Gift article access

As a benefit of your subscription, you can share temporary access to restricted articles.

Each link will stop working after 30 days or 10 uses. You may create up to 10 links in a 30 day period.

Please sign in to your personal account to gift article access.

Register

Gift article access

As a benefit of your subscription, you can share temporary access to restricted articles.

Each link will stop working after 30 days or 10 uses. You may create up to 10 links in a 30 day period.

Gift articles remaining: --

Gift article access

Each link will stop working after 30 days or 10 uses. You may create up to 10 links in a 30 day period.

Gift articles remaining: --

Gift article access

As a benefit of your subscription, you can share temporary access to restricted articles.

Each link will stop working after 30 days or 10 uses.

You have reached the limit of 10 links within a 30 day period.