DECOMMISSIONING AND DEMOLITION 1990
Edited by
Emerald Publishing Limited
ISBN print:
978-0-7277-4675-7
Publication date:
1990
Book Chapter
PLANNING AND MANAGEMENT OF STAGE 1 DISMANTLING OF B16 PILE CHIMNEY, SELLAFIELD
A. E. Shiell
R. F. Mathews
-
Published:1990
Citation
A. E. Shiell, R. F. Mathews, 1990. "PLANNING AND MANAGEMENT OF STAGE 1 DISMANTLING OF B16 PILE CHIMNEY, SELLAFIELD", DECOMMISSIONING AND DEMOLITION 1990, I.L. Whyte
Download citation file:
Open figure viewer
Introduction
History
Function
Structures
Investigations
Studies
Safety
Demolition of The Upper and Concentrator Sections of B16
Removal of Insulation
Base Protection
Erection of Scaffolding and Working Platforms
Removal of Lining and Cap Plates
Removal of Upper Section
Removal of Concentrator Section
Further Work
You do not currently have access to this chapter.
Email alerts
Related Book Content
Related Articles
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.