Purpose

Despite advancements in safety technologies in the construction industry, such as building information modelling (BIM), their impact remains limited due to an insufficient understanding of influential areas of risks and their interconnections. Earthmoving equipment (EE) incidents in Australia underscore ongoing safety challenges. This research develops a model of influential risk factors in earthmoving equipment operations (EEOs) through Rasmussen’s (1997) risk management framework (RMF), uncovering interrelationships to enhance risk identification and support the application of appropriate solutions aligned with the specific system level where each risk originates and evolves. Thus, it paves the way for comprehensive vertical, horizontal and end-to-end integration of technological and managerial solutions across all layers of safety management.

Design/methodology/approach

A literature review identified seven main categories and 52 sub-risk factors, which were further refined through expert validation via 32 semi-structured interviews and alignment with relevant codes of practice and regulations. The research also applies fuzzy decision-making trial and evaluation laboratory (FDEMATEL) for the first time in the Australian construction context to analyse cause-and-effect relationships of EEO risk factors within Rasmussen’s (1997) framework. This methodology also integrates statistical validation techniques, including corrected item-total correlation and split-half methods within the FDEMATEL framework and sensitivity analysis to ensure response consistency, robustness and reliability, ultimately identifying critical areas for targeted interventions in EEOs’ safety management.

Findings

The most influential risk factors across the risk management framework were categorized into cause-and-effect groups, identifying influential factors of EEO incidents. This led to the impact relations map (IRM), classifying factors by causal and effect-driven roles, making influential factors the primary focus for technological advancements and managerial strategies.

Originality/value

To begin with, from the research focus, this study is the first to uncover cause-and-effect relationships of risk factors in the Australian construction context, not only in EEOs but also in broader construction operations. Furthermore, from the research method perspective, a rigorous expert selection approach is embedded in FDEMATEL to ensure robust findings. Ultimately, this shifts the focus of managers and practitioners towards addressing critical dynamic variables, those acting as the Gordian knot within the system, which must be untangled to enable effective safety interventions and informed decision-making in EEOs. These insights strongly support the application of tailored solutions, whether technological (e.g. sensor-based systems, BIM integration and computer vision) or procedural (e.g. regulatory alignment), by aligning interventions with the origin and trajectory of specific risk factors.

Earthmoving equipment (EE) plays a central role in construction operations but remains one of the most dangerous elements on-site, often leading to serious safety accidents due to its complex operation, heavy weight, and powerful hazards (Zhao et al., 2024). There were 168 deaths related to mobile plant and transport in Australian construction sites between 2008 and 2023, of which 65 deaths were related to trucks, excavators, bulldozers, and road compactors (Safe Work Australia, 2023). In Australia, 15% of construction incidents were attributed to interactions between individuals and moving equipment, particularly heavy machinery such as articulated haul trucks, excavators, front-end loaders, and dozers, which represented the second most common cause of incidents, following manual handling incidents (17%) (Woolley et al., 2018). An analysis of 100 construction incident reports in Australia revealed that plant operators were the most frequently identified actors at the staff level, with 70% of the reports attributing causality to their actions. Of the serious injury incidents, excavator buckets were commonly involved, while high-potential events often included heavy vehicle rollovers, contact with overhead power lines, and interactions between heavy and light vehicles (Woolley, 2020). Lingard et al. (2013a) highlighted a notable rise in workers’ compensation claims related to EE in the Australian construction industry, driven primarily by an increase in incidents involving excavators, backhoes, and other digging equipment.

Various technological solutions have sought to improve earthmoving equipment operations (EEOs) safety, yet challenges persist due to complex risk interactions and the difficulty in identifying causal areas to enhance the effectiveness of safety technologies (Gutierrez-Bucheli et al., 2024; Soltanmohammadlou et al., 2024b). The finding of Soltanmohammadlou et al. (2024b) indicate that development of technological solutions in EEOs are not well aligned with systems thinking particularly at the higher RMF levels. Integration of technological advancement in EEOs should go beyond isolated implementation and be embedded within the broader sociotechnical system (Soltanmohammadlou et al., 2024a). Integration of technological advancements in EEOs should go beyond isolated implementation and be embedded within the broader sociotechnical system. According to Sony and Naik (2020), Technological development in EEOs should align not only with immediate tasks but also with broader system elements, including organizational goals, regulatory expectations, worker capabilities, and site-specific processes. For meaningful impact, technologies must be integrated through vertical coordination across system levels, horizontal alignment across functions and stakeholders, and end-to-end support throughout the project lifecycle. To cite an example, although research in computer vision (CV) has rapidly advanced in EEOs, particularly in monitoring of EE through part and activity recognition (Luo et al., 2020; Wen et al., 2023), without integration of broader system-level risk factors, such as regulatory demands, these technologies risk becoming redundant (Fang et al., 2020). Technological advancement should also extend beyond purely technical observation to address context-specific hazards and the social dimensions of operations, including factors such as the operator’s mental state and overall situational awareness (Choi et al., 2020; Mehmood et al., 2023). To cite another example, the combination of BIM with technologies such as CAD, blockchain, VR simulation and training, RFID, smartphones, and IoT has been identified as effective in addressing the underlying causes of all six major mental disorders of workers (Nelumdeniya et al., 2023). While Building Information Modelling (BIM)-based automated safety rule-checking aids hazard recognition and risk management activities (Johansen et al., 2021), its success for EEOs safety at the stage of site planning is hindered by the absence of standardised methods for digitally representing and structuring site elements to align with various regulatory requirements and stakeholder needs (Getuli et al., 2025). Formulating information about the entities of EEOs facilitate the information exchange, increase stakeholders’ knowledge, and ensures a safer approach to EEOs (Taher et al., 2022). Getuli et al. (2025) have emphasized that for the comprehensive implementation of technological solutions in EEOs safety, such as BIM object libraries, it is essential to go beyond technical specifications by incorporating spatial and safety considerations to prevent operational conflicts and ensure worker safety. Ergo, there is a need to incorporate information about dynamic variables on construction sites and integrate them into an agent-based construction site simulator, where each site object functions as an autonomous agent. The coordination of EEOs can be significantly enhanced through BIM-enabled planning, which allows for real-time visualization and scheduling of equipment movements, detection of time-space conflicts, such as between the workspaces of activities and the bounding boxes of machinery, and the use of path planning modules to manage EE movements (e.g. loaders, and dump trucks) (Dashti et al., 2021), site planning of congested sites (Kumar and Cheng, 2015), and underground utility management (Wang et al., 2019). Compared to visually tangible risk factors, other risks in EEOs, such as those related to supervision, regulation, and knowledge, are more difficult to observe and measure (Guo et al., 2021). In this case, integrating technologies such as BIM and computer vision into safety supervision can effectively address other components of the RMF and enable broader system-wide monitoring and feedback (Kulinan et al., 2024). Identifying focal risk areas and their cause-effect relationships is key to directing technology where it can have the greatest system-wide impact, ensuring that solutions align with both technical needs and broader sociotechnical dynamics in EEOs.

Therefore, as technological functionalities convey information on risk factors in EEOs across different levels of Rasmussen (1997) risk management framework (RMF), including government, regulatory bodies, companies, management, staff, environment, and equipment (Soltanmohammadlou et al., 2024b), incorporating causal variables into this digital framework is essential to ensure that safety solutions are effectively tailored to specific contextual challenges and control the root causes of EEO accidents.

Although studies on plant and machinery risk identification in Australia, such as those focusing on EE risk factors (Lingard et al., 2013a, b) as well as crane safety (Lingard et al., 2021) have provided valuable insights, particularly through models like the Loughborough Construction Accident Causation (ConAC) model, the progression of knowledge has largely remained limited to the identification stage (Kazan and Usmen, 2018; Lingard et al., 2021). Nevertheless, as highlighted by the gaps in existing qualitative research around the safety management of plant and machinery in Australian construction sites (Lingard et al., 2021), there is a notable lack of quantitative research aimed at uncovering the complex interrelationships between proximal and distal risk factors in EEOs to support judicious decisions by the relevant decision-makers.

To bridge these gaps in knowledge and practice, a systems thinking approach is required particularly in the Australian construction sector, which emphasises risk control to improve safety but often overlooks systems factors, prioritising immediate, surface-level causes. This paper develops a causal model of risk factors in EEOs within the Australian construction context by categorizing these risk factors across the levels of Rasmussen (1997) RMF. DEMATEL (Decision-Making Trial and Evaluation Laboratory) (Fontela, 1976) is a prominent Multi-Criteria Decision-Making (MCDM) method with a strong capacity to analyse the cause and effect relationships among risk factors within a complex system. FDEMATEL generates impact relations maps (IRM) which form the basis of the causal model by classifying factors based on their cause-and-effect roles and offering a clear visual structure of influence within the within complex sociotechnical systems system (Mohandes et al., 2022; Sadeghi et al., 2023; Zhang et al., 2020). By applying such methods, it becomes possible to move beyond descriptive risk identification and develop systematic models that clarify the areas and characteristics of risk factors to support proactive safety management strategies.

The fuzzy extension of DEMATEL (FDEMATEL) (Wu et al., 2025) is particularly well-suited for addressing the inherent vagueness and uncertainty in human judgements, which frequently arise in real-world scenarios where precise numerical values may not adequately capture the available knowledge (Bellman and Zadeh, 1970; Rostamnezhad et al., 2020). The integrated techniques of corrected item-total correlation and split-half method is embedded within the FDEMATEL framework to achieve higher precision, maintain consistency and improve accuracy in judgement of decision makers. Furthermore, the model, coupled with sensitivity analysis to verify the reliability and robustness of the derived outcomes.

As such, the research questions are:

RQ1.

How can the subjectivity of safety experts’ responses, the uncertainty surrounding EEOs, and the consistency rate of their evaluations be effectively addressed?

RQ2.

How can the cause-and-effect interrelationships among EEOs risk factors within the Australian construction context be identified?

RQ3.

What are the most central and influential risk factors that require particular scrutiny?

Leveraging the findings of this paper provide a unique contribution to the construction practitioners’ understanding of the main causal risk factors affecting EEOs across the various levels of Rasmussen (1997) framework in the Australian construction context. This research encourages technology developers in EEOs to ground their innovations in a deep understanding of context-based hazards and the focal needs of risk factors. Technologies should not only be data-driven in controlling primary causal risk factors but also capable of detecting and monitoring the behaviour of other influencing factors while supporting the implementation of corrective actions such as site supervision and coordination of EE (Woolley, 2020). By identifying cause-and-effect relationships specific to Australian EEOs, this insight supports decision-makers in assessing systemic safety conditions and guiding the development of technologies that are both targeted and integrated into the broader sociotechnical framework. Moreover, policymakers can gain valuable insight into the specific areas of challenge within EEOs, enabling them to identify which elements of the sociotechnical system require targeted improvements. Collecting and analysing data on the cause-and-effect relationships of accidents in the construction process enables more rigorous and accurate predictions about the causes and consequences of EEO incidents. This capability enhances proactive risk identification and supports the development of targeted safety interventions.

The upcoming sections present the structure of the paper. First, Section 2 provides a brief background and an overview of related previous studies. Section 3 outlines the proposed research methods. In this section, the main categories of risk factors and sub-risk factors are identified based on a rigorous and structured literature review, with insights, attitudes, and contextual experiences shared through semi-structured interviews with Australian experts and adherence to applicable codes of practice and regulations related to EEOs in Australian construction context. From the literature, this is the first application of FDEMATEL as a quantitative approach to uncover the cause-and-effect relationships of risk factors in the Australian construction context with a specific focus on EEO safety. Finally, Section 4 presents the results, while Section 5 discusses their reliability and validation. Section 6 provides a detailed discussion of the findings. Section 7 discusses the implications, while Section 8 outlines the conclusions, contributions, limitations, and future research directions.

Work Health and Safety (WHS) laws implemented in many countries are primarily designed to safeguard workers and others from harm associated with work activities (Bayramova et al., 2024; Bluff, 2019). In Australia, based on Model Work Health and Safety Regulations 2011 (Safe Work Australia, 2024b), in safety management of EEOs, Persons Conducting a Business or Undertaking (PCBUs) are legally responsible for managing plant-related risks and ensuring workers receive adequate information, training, instruction and supervision (ITIS), even without formal certification. However, prosecutions often focus only on cases where ITIS was absent, offering little guidance on proper delivery (Bluff, 2019). Moreover, despite the presence of national and international standards such as UN Regulations, Global Technical Regulations, and codes of practice and guidelines regulating for importation, utilisation, and safe operation of construction equipment, the practical hurdles to promptly notifying upper-level management of the need for improvements (Woolley 2020), cause the ongoing rate of workers’ injury compensation to remain high, highlighting the shared responsibility across all levels is not consistently implemented or practised as intended (Woolley et al., 2018). Challenges include limited safety information flow due to the absence of formal input systems for regulations and performance monitoring, delayed communication channels, feedback mechanisms prioritising financial and compliance metrics over safety outcomes, and the significant yet unenforced influence of unions, suppliers, and communities due to their lack of formal governance integration (Woolley et al., 2020).

The necessity for identifying causal factors, which are the primary source of underlying issues, remains critical even with technological advances in integrated safety management for EEOs. This underscores the importance of prioritising the effective capture, management, and dissemination of risk information across all levels of Rasmussen (1997) RMF (Soltanmohammadlou et al., 2024b).

Within the construction process, as a complex sociotechnical system (STSs) with diverse human and technological components that have non-linear interactions (Bayramova et al., 2023), there will inevitably be instances where the magnitude of variability in a single function or activity is sufficient to increase the probability of adverse outcomes, such as accidents or incidents (Hollnagel and Slater, 2018). Systems thinking-based accident causation models such as Rasmussen (1997) RMF conceptualises a hierarchical and interconnected socio-technical structure extending from the governmental level to the work environment level. Applying this paradigm in the domain of construction research sheds light on various aspects of safety management (e.g. underlying causes of the incident in construction safety of developing countries (Mohandes et al., 2022),and tower crane safety (Sadeghi et al., 2023).

(Soltanmohammadlou et al., 2024a) reviewed a total of 87 published papers and applied a systems thinking approach to categorise the risk factors of EEOs into five groups based on (Rasmussen, 1997): regulatory bodies and associations (R), company management (C), construction site management (S), workforce (W), and environment and equipment (E). Recently, some scholars have employed a systems thinking approach to analyse risk factors in crane incidents in China using empirical data (Zhou et al., 2018), others have applied decision-making methods for assessing risk factors in the excavation process in construction yards (Ilbahar et al., 2018), and root causes of construction site accidents in developing countries (Mohandes et al., 2022). Evidence shows that the causal and contributing factors of Australian construction plant and machinery such as crane incidents originate from multiple dimensions, including (1) regulatory frameworks and socio-economic contexts, (2) planning, management, and operational practices at organisational and project levels, and (3) site-specific behaviours and conditions at the locations where incidents occur (Lingard et al., 2021). Allowing embedded information from causal risk factors to move effectively through the system can help untangle ongoing systemic challenges and support the development of improved safety management practices aligned with Australia’s OHS ambitions (Lingard et al., 2009).

Figure 1 illustrates the research method summary, detailing the sequential steps involved in identifying, validating, and analysing risk factors through expert interviews, designing the fuzzy DEMATEL survey, and conducting consistency rate and sensitivity analyses.

The identification of risk factors began with a literature review and analysis of codes of practice, followed by expert interviews conducted within the Australian construction industry. These interviews refined the understanding of risk factors, enabling the design of a structured questionnaire for data collection. Following this, the FDEMATEL technique was employed to explore the interrelationships among the main and sub-risk factors of EEOs and generate various impactful cause-and-effect diagrams. The interviews and FDEMATEL questionnaires were approved by the University Human Research Ethics Committee (UHREC, approval no. LR, 2023–5693–16275), confirming compliance with ethical standards regarding consent, confidentiality, and data handling. Finally, sensitivity analysis was conducted to assess the robustness of the results and ensure the reliability of identified causal relationships.

The extraction of risk factors for EEOs was conducted in two stages: first, identifying risk factors through a comprehensive review of the literature and codes of practice, and second, validating these factors through brainstorming interviews with selected experts. (Soltanmohammadlou et al., 2024a) classified the EEOs safety research into two major types (Type one: Identification of the risk factors of EEOs and Type two: safety solutions of EEOs). This research primarily draws on Type One research to extract and analyse relevant risk factors associated with EEOs. Additionally, Lingard et al. (2021) highlighted that some causal and contributing factors identified in the crane safety incident causation model in Australian construction sites might also apply to other plant and work vehicle types. The work of Lingard et al. (2013a, b), Lingard et al. (2021) served as the cornerstone of risk identification in this study, providing a foundational understanding of safety challenges in Australian heavy equipment operations. As shown in Table 5, the research team subsequently broadened the scope of risk factors through collaborative expert consultation, supplementing the initial framework with insights from peer-reviewed literature on heavy equipment operation risks (Kazan and Usmen, 2018; Sadeghi et al., 2023).

In addition, the refinement of the framework was guided by authoritative resources drawn from Australian jurisdiction-specific Codes of Practice developed under section 274 of the Work Health and Safety Act 2011 (Office of Parliamentary Counsel, 2018), such as Managing the Risks of Plant in the Workplace (Safe Work Australia, 2024a) and Code of Practice for Excavation Work (Safe Work Australia, 2021). In the next stage, a brainstorming interview was conducted with 32 shortlisted experts from various states of Australia to ensure the validity and applicability of these risk factors. To address potential concerns regarding jurisdictional differences in work health and safety regulations across Australian states and territories, this study deliberately selected experts from various regions within Australia. By incorporating a diverse group of professionals, the research captures a broad spectrum of insights and practices reflective of the different regulatory environments. Moreover, this approach reinforces the premise that certain risk factors extend beyond regulatory boundaries and remain relevant to construction work irrespective of specific state or territory contexts (Lingard et al., 2021).

This study employed purposeful sampling to identify and select experts with relevant knowledge and experience (Suri, 2011). The experts were selected based on two criteria to ensure their qualifications and relevance to the study:

  1. A minimum of five years of experience in construction operations or related sectors, such as EE manufacturing or technical training institutions specialising in the operation of these types of equipment.

  2. Involvement in EEOs in the construction process, either in their current role or through prior relevant experience, demonstrating practical expertise in the field.

They were asked to validate the extracted risk factors by sharing their perspectives on those presented for review. Table 1 represents the profile of the experts interviewed to validate these risk factors.

The DEMATEL technique (Fontela, 1976) is a robust multi-criteria analysis tool designed to capture collective knowledge and visualise complex causal relationships within systems as well as prioritise central indicators (Cheng et al., 2024; Yu and Ma, 2024). Integrating fuzzy logic (Zadeh, 1965, 1975) into DEMATEL overcomes the limitations of traditional crisp values by addressing uncertainty and ambiguity in human judgement. This extension transforms imprecise judgements into precise insights, enhancing the accuracy and reliability of decision-making processes. The process of the FDEMATEL method comprises several essential steps, which are outlined and explained as follows:

  • Step 1. Design of the questionnaire

A triangular fuzzy number, defined as (a,b,c), represents uncertainty through three key parameters: a, the lower boundary of the value range; b, the most probable value; and c, as the upper boundary. This type of fuzzy number is a specific variant of a trapezoidal fuzzy set, in which the core, or the range of maximum membership, reduces to a single precise point, making it especially useful for scenarios with a distinct peak likelihood (Ren et al., 2008). The questionnaires were structured using five linguistic scales and fuzzy numbers, as presented in Table 2. The linguistic terms were used to indicate the strength of the relationships between factors.

  • Step 2. Questionnaire distribution to the experts

The questionnaires were initially distributed to 42 subject matter experts, including individuals who participated in the interview process. From the interview group, 17 experts provided responses. One additional individual, beyond those initially interviewed, also participated in this stage, bringing the total number of respondents to 18 as shown in Table 3. presents the profile of the respondents who participated in the questionnaire. Each expert was instructed to evaluate the direct influences among the risk factors, ensuring that no cause was assessed as influencing itself. As a result, a total of n×(n1) influences needed assessment, where n is the number of causes in each group.

  • Step 3: Generating the fuzzy initial direct-relation matrix

To create the initial direct relation matrix, for the n factors, k number of experts were asked to assess the impact of the factor i on the factor j . On the other hand, a higher linguistic rating from a respondent reflects the belief that inadequate engagement with the problem of element i has a stronger direct impact on the inability of element j as illustrated in Figure 2. Therefore, the direct-relation matrix is established as zK=[zijk].

(1)

Where ZijK=(lijK,mijKuijK), and where zij indicates the direct effect of factor i on factor j; and when i=j, the diagonal elements zij=0.

  1. Consistency Rate Calculation: integrated approach of corrected item-total correlation and split-half methods

Before proceeding to the next main stage of the DEMATEL method, it is essential to evaluate the consistency of the expert responses. This process consolidates individual expert evaluations into a unified matrix, representing the collective perspectives on the relationships among factors. An expert’s responses may significantly differ from others for various reasons, such as a different interpretation of the questions, and can affect the result and reduce the overall consistency. Therefore, it is advisable to assess the consistency of the responses and remove those that lower the consistency of the aggregated matrix (Shieh and Wu, 2016). A key reason for ensuring a consistency rate in the fuzzy DEMATEL method lies in its use of arithmetic means to aggregate expert opinions, unlike the geometric means approach employed in other multi-criteria decision-making methods (MCDM) methods such as AHP (Wu and Tsai, 2012). This distinction underscores the importance of verifying logical coherence and alignment among individual judgements to minimise subjective biases and validate the logical alignment of judgements (Wu and Tsai, 2011). To ensure consistency and refine the collected data from experts, the model outlined in Shieh and Wu (2016) was employed, adhering to the procedural steps detailed in Figure 3.

The steps of this model are as follows:

  1. The collected responses are transformed into a vector format by arranging all values from the matrix, excluding those on the main diagonal, sequentially beneath one another to form a single vector.

  2. Each expert’s response is compared with the average responses of the other participants. Correlation values for all survey responses are calculated based on the average of the group using Eq. (2), with the correlation between X and Y determined using Eq. (3). This measure quantifies the strength of the relationship between each individual survey item and the overall survey results, providing insight into the consistency and alignment of responses within the group.

(2)
(3)
  1. Any calculated correlation values from the previous step that fall below 0.3 are addressed by removing the expert with the lowest correlation. The process then reverts to Step 2 with the updated list of experts. This iterative procedure is repeated as necessary until all corrected item-total correlation values meet or exceed the threshold of 0.3. By applying this approach, only reliable and consistent expert responses are retained, ensuring the robustness of the data for subsequent analysis.

  2. Generate all possible split-halves of the dataset using an appropriate method (e.g. the MATLAB function nchoosek). For each split-half, compute the correlation values and adjust these correlations using the Spearman-Brown formula, as expressed in Eq. (4), where r represents the estimated correlation between the two halves. Finally, calculate the average of all adjusted split-half correlations to determine the overall consistency of the dataset.

(4)

In step 4, if the number of remaining experts from step 3 exceeds 15, the number of possible split-half combinations will increase exponentially. To address this, the required number of half combinations (n) can be calculated using Eq. (5), where Zα2=1.96, p represents the expected response rate, and q=1p. The final required number of half combinations is then determined by Eq. (6). This method ensures an efficient evaluation process while preserving statistical validity.

(5)
(6)

The selected 10 expert respondents demonstrated a high level of consistency in their evaluations, meeting the predefined threshold for inclusion in the analysis. This ensured the reliability of the aggregated responses and minimised the impact of subjective biases on the study’s findings. As shown in Table 4, the final selected respondents’ profiles reflect their expertise and relevant backgrounds, ensuring the credibility and robustness of the data used in the analysis.

  • Step 4: Aggregating the direct-relation matrices.

An average matrix is constructed by aggregating the direct matrices from multiple respondents. Each element in this matrix represents the mean of the corresponding elements across the individual direct matrices provided by the respondents (Tzeng et al., 2007). The average normalised direct relation fuzzy matrix (Az) for all experts’ input is calculated as follows:

(7)

Where pij= (k=1KZij(k))/K)

  • Step 5: Normalising the direct relation matrix.

The initial direct influence matrix (Nij) is derived by normalising the average matrix (Az), ensuring that all principal diagonal elements are zero. Matrix N illustrates the initial influence that each element exerts on and receives from others.

(8)

Where r=maxij{maxij=1nuij,maxji=1nuij}i,j{1,2,3,,n}

  • Step 6: Developing the total (direct–indirect) relation matrix.

Eq. (9) is used with all the fuzzy values to compute the total relation matrix. Once the normalised fuzzy direct-relation matrix N~=(Nl,Nm,Nu) is obtained, where Nl=[nijl]n×n, Nm=[nijm]n×n, Nu=[niju]n×n, the fuzzy total-relation matrix T~=[t~ij]n×m where t~ij=(tijl,tijm,tiju), is derived as follows:

  1. The lower bound matrix Tl=[tijl]n×n is calculated as Nl(INl)1

  2. The middle-bound matrix Tm=[tijm]n×n is calculated as Nm(INm)1

  3. The upper bound matrix Tu=[tiju]n×n is calculated as Nu(INu)1

Where I represents the identity matrix. These computations are executed in Microsoft Excel utilising the “Minverse” and “Mmult” functions.

(9)
  • Step 7: Converting the values of the total relation matrix into crisp values

Defuzzification of the total relation matrix T values are performed to generate the total relation matrix with crisp values. This process involves applying the defuzzification method using Eq. (10) and (11) (Ocampo et al., 2018).

(10)
(11)
  • Step 8: Set threshold value and obtain the Impact Relations Map (IRM)

Tzeng et al. (2007), recommend simplification of the structure of elements in matrix DT, by setting a threshold value TS, to filter the most significant effects represented by the elements of the matrix. Each element dTij in matrix DT indicates the degree to which element i influences element j. If all elements from matrix DT are converted into an Impact-Relation Map (IRM), the resulting map would be overly complex, making it difficult to extract meaningful information for decision-making. Only those elements in matrix DT with influence levels exceeding the threshold are selected and included in the final IRM. There are various methods to calculate thresholds in the DEMATEL method, each presents unique challenges in balancing the trade-off between providing more or less relational information (Apaydın and Aladağ, 2022). Methods providing more information often complicate IRM with trivial relations, while those offering less information risk omitting significant relationships, potentially compromising analytical accuracy and clarity (Si et al., 2018). In this paper, the third quartile was used as a threshold to identify relationships that are above the median but below the extreme outliers (Si et al., 2018). The total relation matrix S, after removing the minor influences, is shown as follows:

(12)
(13)
(14)
  • Step 9: Generating Impact Relations Map (IRM)

Eq. (15) and (16) are utilised to compute the two influence indexes from the total relation matrix. The two influence indices Di and Ri are instrumental in determining the centrality and causality levels of the factors under analysis. The first index Di represents the influence exerted by one factor on others, referred to as the dispatcher. Similarly Ri reflects the influence received by a factor from other surrounding criteria, referred to as the receiver (Alshahrani et al., 2024).

(15)
(16)
  • Step 10: The Centrality Degree (CE) and Causality Degree (CA)

The Centrality Degree (CE) and Causality Degree (CA) have been computed using Eq. (17). CE quantifies the relative importance of the factors, while CA determines the cause-and-effect relationships among them. Criteria with positive CA values are classified within the cause group, whereas those with negative CA values are assigned to the effect group (Alshahrani et al., 2024).

(17)

As a result, the causal diagram was divided into four distinct quarters (first, second, third, and fourth) based on the values of DR and D+R (Figure 4) (Mohandes et al., 2022).

To calculate the probability of a change in the factor region within the DEMATEL model, two key parameters must first be defined: N, representing the number of iterations, and W, representing the range of experts’ weights. In this paper, N is set to 1,000 iterations, and W is set within the range of [75, 100]. For each participant, their weight is denoted by w, meaning their influence is considered w times in the model. At the start of the process, the iteration index i is initialised to 1. Then, for each iteration, a random weight is assigned to each participant, and the DEMATEL model is executed based on these weights. After running DEMATEL, the region of each factor is determined and recorded. Once all 1,000 iterations are complete, the factor regions from each iteration are compared. The probability of change for each factor is then calculated by counting the number of iterations in which a change in the region occurs, relative to the total number of iterations (1,000). Figure 5 illustrates the process of sensitivity analysis conducted on the findings.

The literature review comprehensively identified the main and subcategories of risk factors contributing to EEOs as summarised in Table 5, to establish a comprehensive and contextually relevant foundation for the study. While the FDEMATEL method has been specifically applied to evaluate safety in EEOs, the majority of identified risk factors are not unique to these operations but are broadly reflective of general conditions and challenges inherent to construction activities. This overlap underscores the systemic nature of the risks and highlights the applicability of the findings to Australian construction operations as a whole.

The cause-and-effect relationships among risk factors were analysed as described above. This analysis provides insights into the influence and dependency levels of the identified causes, helping to distinguish between key drivers and outcomes within the system. The total direct–indirect matrix of all identified causes was calculated prior to the exclusion of minor influences (step 6). Threshold values were subsequently determined for each group to filter out these minor effects. The refined direct–indirect matrix highlights zero values corresponding to the isolated influences (step 8). The cause-and-effect relationships among all causes are illustrated in Figure 6 derived from the values presented in Table 6.

Sensitivity analysis was employed to validate the reliability and strength of the obtained results (Guo et al., 2024).The sensitivity analysis, performed through 1,000 trials with expert weightings varied between 0.75 and 1, reveals that most factors exhibit 0% variation, offering significant insights into the reliability and stability of their positions within the Impact-Relation Map (IRM). G2 (47%), EN (33%), and EQ (7) (29%) exhibited the highest probability of zone variation, indicating significant sensitivity to changes in experts’ weightings. CS10 (21%) and CS (13%) showed moderate variation, suggesting some susceptibility to expert input shifts. S (9%) and W12 (7%) demonstrated minimal variation, reflecting a relatively stable position with slight responsiveness to modifications. The overall aggregation value (3%) further highlights the general robustness of the results, with most factors remaining stable despite expert weight variations. These findings underscore the reliability of the aggregated results while highlighting a few factors that require further examination to better understand their interrelations and ensure comprehensive decision-making.

This section discusses the main findings of the study, focusing on the various categories of EEOs safety management systems.

As shown in Figure 6(a), in the safety management of EE, construction site management (CS) and workers (W) are positioned in the first quarter, indicating their central and dominant roles within the system. They exhibit high influence on other elements while being strongly influenced themselves, highlighting their pivotal role in interrelationships. CS and W not only exert mutual influence but also collectively shape practices within stakeholders in the S level, influencing how stakeholder-related mechanisms (e.g. safety management plan of the principal contractor (S1)) are developed and enacted. Their embedded operational decisions and interactions serve as upstream determinants of downstream stakeholder actions. Furthermore, the observed influence of the government level (G) on CS underscores how regulatory decisions cascade into construction management processes, ultimately shaping outcomes at the worker level through policies, procedural requirements, and compliance expectations. This interconnectedness explains why technological developments in construction safety often prioritize construction site (CS) monitoring (Soltanmohammadlou et al., 2024b), given its central role as the operational bridge between regulatory directives and frontline activities. Such prioritisation is not only logical but necessary, as CS serves as the point of convergence between policy formulation and physical task execution. However, the environment (EN) is isolated, acting as an external and uncontrollable variable, such as weather conditions, that affects construction operations independently, without being shaped by internal processes, serving instead as a broader contextual influence. In the Australian construction industry, workforce involvement is crucial for a strong safety culture, as their hands-on experience offers insights often overlooked by management. A bottom-up approach leverages these insights to identify hazards and suggest practical safety improvements, ensuring effective and lasting safety strategies (Biggs et al., 2013; Newaz et al., 2019). However, top-down rules often fail to address real-world complexities, whereas involving workers in rule development and maintaining continuous dialogue with management ensures relevance and adaptability (Hale and Borys, 2013a, b). In EEOs, subcontractors act as key sources of safety information in EEOs (Rashidi et al., 2024), supporting a bottom-up approach that refines safety rules dynamically to align with real-world operations (Hale and Borys, 2013a, b). This approach ensures a balanced and practical response to equipment-related hazards, including location-based risks (e.g. movement between zones) and state-based risks (e.g. task-specific actions) (Taher et al., 2019).

At the G level, safety regulation (G1) holds a predominant position, influencing all other factors in its category (Figure 6 (b)). G1 serves as the central mechanism of Australian construction safety management, ITIS Regulations 2011; Safe Work Australia, 2024b) require PCBUs and supervisors to monitor site operations, identify hazards, and enforce compliance (Safe Work Australia, 2024b). However, the WHS Act and Regulations are flexible and open-ended, lacking specific guidance on ITIS delivery. Similarly, codes of practice provide general compliance advice but offer limited direction and rarely address specific ITIS methods (Bluff, 2019). In Australia, ensuring construction safety is not the sole responsibility of an individual or organisation but requires coordinated efforts across all levels of the system, similar to other complex sociotechnical systems (STSs) (Woolley et al., 2018). However, this integrated approach is rarely fully realised in practice, leading to a gap where those creating construction safety laws may lack critical information needed for informed decision-making.

Regulatory training requirements/standards (G3) are positioned in the first quarter, exerting significant influence on safety regulation (G1), safety supervision (G2), and verification of competency (VOC) (G5). Despite this, the actual implementation of training and competency processes is compromised by the inconsistent performance of Registered Training Organisations (RTOs), which are often poorly regulated. Previous research has identified issues such as low instructional standards, fraudulent practices (e.g. sale of VOC certifications), and inadequate assessment processes (Lingard et al., 2021), all of which undermine the reliability of competency validation in practice.

Despite G5 being in the third quarter with low influence and impact, prioritising VOC remains critical. According to the verification of competency – mobile plant fact sheet, a standardised checklist aligned with the nationally recognised training package should cover hazard identification, risk controls, operator manual requirements, and emergency responses (Office of the Federal Safety Commissioner, 2021). This research highlights that current VOC implementation may not consistently provide reliable evidence of operator competency, revealing key areas of concern:

  1. The VOC process lacks a feedback loop to evaluate operator performance over time, which is critical in equipment-intensive and project-specific earthwork operations such as cleaning, excavation, compaction, and grading. Without a mechanism to address skill gaps, refine criteria, or adapt RTO requirements, the VOC process remains static. As a result, it does not ensure operation-specific competency or enable continuous improvement.

  2. Without a reliable and standardised VOC process, PCBUs struggle to ensure operator competency for project/task-specific and evolving operational demands. Additionally, this limits PCBUs’ ability to address skill gaps and improve safety performance effectively.

Expert interviews confirmed that the VOC process may involve subjective assessments of operator competency and issues such as misalignment with machinery types and associated risks, the use of multiple machines in earthmoving operations, and gaps in task-specific training. This highlights the need for task- and equipment-specific training and evaluation mechanisms to ensure operators have the necessary skills and adaptability for safe and effective performance in diverse operational contexts.

Figure 6(c) shows procurement management (C2) as a central and dominant factor within the system. While procurement management was not explicitly linked to accident causes in the Australian construction industry (Lingard et al., 2013a), this analysis confirms its influence on other risk factors. C2 plays a pivotal role in ensuring EE safety by influencing the selection of high-quality machinery that meets safety standards (Edwards and Holt, 2011) and aligning with manufacturer performance for optimal safety and efficiency (Soltanmohammadlou et al., 2024a). However, decision-makers often prioritise cost and manufacturer reputation, shaped by client experience, after considering operational and environmental factors (Edwards and Holt, 2011). Budget constraints may lead to compromises on equipment quality and safety features, increasing risks. Additionally, adequate resources must be allocated not only for advanced machinery acquisition but also for workforce training on operational requirements. Technical standards, task step definitions, and hazard identification require further attention to ensure the safe and efficient integration of advanced machinery (Soltanmohammadlou et al., 2024a). EEOs account for a significant portion of project expenses, making up 20% of total costs in construction projects and up to 30% in highway construction (Shehadeh et al., 2022). The position of client management (C1) highlights its influence on work health and safety (WHS) performance in construction through management actions (Lingard et al., 2019) such as budgets, schedules, goals, performance criteria, project delivery methods, contracting approaches, and team selection (Gibb et al., 2014). In Australian construction projects, government agencies as clients play a key role in fostering positive safety cultures through procurement practices (Kiani Mavi et al., 2024; Lingard et al., 2019). Understanding how performance measurement and management interact at the client-contractor interface is crucial for positive WHS outcomes, as clients are key actors in shaping safety practices in the Australian construction industry (Lingard and Pirzadeh, 2025). Clients are not passive overseers but active agents capable of embedding safety into procurement frameworks, thereby enabling system-level safety improvements.

Shifting the focus to the stakeholder safety management (S) sub-risk factors (see Figure 6(d)), the safety management plan of the principal contractor (S1) has influence on, accident investigation plan by principal contractor (S3), safety management plan of subcontractor (S4), safety training by contractors (S7), and equipment maintenance plans by contractors (S8), highlighting its pivotal role in driving coordinated safety practices across contracting tiers. Indeed, in interviewing the experts for validation of risk factors, most participants concurred that S1 acts as an umbrella, aligning subcontractor safety plans under a unified system to promote consistency while reducing administrative burdens. They also mentioned that for the safe operation of EE, it is essential to address several key aspects. Insufficient prequalification can increase the risk of unskilled or unqualified sub-contractors being permitted on-site, compromising safety. Clearly defining sub-contractor responsibilities before site commencement is crucial to ensure accountability and compliance. Additionally, outlining comprehensive requirements for site acceptance enhances clarity and establishes necessary safety benchmarks.

Each of the PCBUs such as the principal contractors and EE subcontractors should have flow of information about the risk management of these kinds of operations. Owing to the fact that principal contractors are tasked with bridging the gap between regulatory expectations and on-site realities, necessitating proactive engagement with subcontractors and the implementation of robust safety systems (Biggs and Biggs, 2013; Biggs et al., 2013; Loosemore and Andonakis, 2007). Moreover, subcontractors possess valuable tacit knowledge of safe practices, often acquired informally through hands-on job experience. Because of this importance, the safety management plan of subcontractor (S4) is highly affected by S1. To encapsulate, in this level, if sufficient attention is directed toward S1, it is likely to result in substantial improvements in other sub-risk factors. Another noteworthy finding is the position of incentive and disciplinary measures of principal contractors for safety management (S2), represents a factor with significant influence on other elements within the system. Providing rewards and incentives for good safety performance, such as active participation in safety talks, reporting near misses, and identifying unsafe conditions, fosters a safety culture (Jalil Al-Bayati et al., 2023). However, experts during the risk factors validation interviews criticised traditional methods like toolbox talks for failing to resolve recurring issues and advocated for rewarding proactive behaviour while ensuring fair accountability for negligence. This approach promotes collective responsibility and aligns with evolving regulations, such as the “chain of responsibility” or which holds senior leaders accountable for endangering workers and underscores the need for ethical governance and adoption of emerging safety technologies (Khorrami Shad et al., 2024) . Specifically, the training of subcontractors for operators of EE is essential to facilitate shared decision-making for operations requiring the coordination of a fleet of equipment (Rashidi et al., 2024). The positions of the safety plan of equipment designers (S5) and qualifications of manufacturers (S6) highlight their foundational roles rather than acting as drivers of interconnected sub-risk factors. Subcontractors of EE rely heavily on manufacturer-provided equipment characteristics, making it essential that these properties are clearly documented in the equipment manufacturer’s handbook to support contractors in work improvement (Alshboul et al., 2024).

Figure 6(e) highlights site supervision (CS1) as a central factor in managing sub-risk factors in earthmoving and other construction operations. CS1 connects and supports site isolation and warning region setting (CS2), safety plan (CS3), schedule pressure (CS4), traffic management plan (CS5), coordination and planning of multiple operations (CS7), obstacles and congested site (CS8), and change management (CS10). CS1 is closely linked to the role of the direct supervisor, responsible for assigning tasks and ensuring safety and operational procedures. The hazards of EEOs vary based on machinery combinations, project types, tasks, and sub-tasks, each requiring onsite coordination (Alshboul et al., 2024; Taher et al., 2022). The role of CS1 underpins the practical enforcement of critical controls such as isolation zones, task sequencing, and traffic planning, particularly essential in EEOs where spatial constraints and task interdependencies are high. The central positioning of CS1 reflects its role as a mediating function that not only interprets safety protocols but dynamically adjusts them in response to site conditions, acting as the interface between planning intentions and real-time operational demands. In Australia, frontline supervisors play a pivotal role in managing high-risk workers and implementing leadership-level safety strategies (Biggs et al., 2013). Utility-related problems (CS9) have a high influence on other sub-risk factors (high D-R), emphasising the role of Dial Before You Dig (DBYD) in Australia. DBYD acts as a critical boundary object, fostering consensus for safe practices, ensuring infrastructure integrity and public safety, and facilitating data transfer about existing buried infrastructure between utility companies and those planning excavation work (Moshtaghian and Noorzai, 2023) in sociotechnical systems.

While Safe Work Methods (SWMs) (CS6) is located in the second quarter with high influence, its lack of direct connections to other risk factors suggests a fragile integration into broader site safety systems—where changes in related practices may not be adequately captured or adjusted. In the Australian context, SWMs are legally mandated for high-risk construction work (HRCW), such as excavation with intense equipment operation, and must be completed in writing (Zhu et al., 2024). However, discrepancies exist between SWMs as imagined and as performed, as they are often developed by back-office employees, consultants, or head contractors with little input from workers, leading to low engagement and minimal updates during high-risk tasks (Bluff, 2019). Addressing HRCW gaps, such as excavations exceeding 1.5 m involving EE, requires comprehensive hazard assessments, including risks from multiple machines and tasks. PCBUs are legally required to engage workers in managing WHS risks, but socio-psychological barriers, such as low literacy and non-English-speaking backgrounds, hinder hazard identification and SWMs compliance (O'Neill et al., 2022). SWMs are widely recognized by WHS regulators and contractors as lacking practical impact, yet they remain unchallenged. Until workers and practitioners expose these flaws, the system will persist, reinforcing the “tick and flick” approach to documentation (Lingard et al., 2021).

Figure 6(f) highlights human-related sub-risk factors in the first quarter, including supervisor’s safety commitment (W5), workers’ knowledge/experience (W2), operation communication (W13), lack of hazard/situational awareness of workers (W3), supervisor’s safety instruction (W6), and operators’ proficiency (W9). Refining these factors would lead to corresponding improvements in the cluster. Expert interviews confirmed that W5 acts as a canopy for the supervisor’s safety inspection (W4) and supervisor’s safety instruction (W6), influencing on-site safety management and safety culture. However, the high D + R value of Supervisor’s safety instruction (W6) demonstrates its pivotal function in shaping interconnected workforce-related risk factors, positioning it as a central mechanism through which broader safety outcomes can be effectively influenced. Supervisors who provide consistent guidance, engage in safety practices and respond to concerns reinforce safety awareness and help apprentices apply up-to-date safety knowledge (W2) from TAFE to on-site operation. A strong supervisor-worker relationship allows workers to raise safety issues, contribute to SWMs, and discuss personal challenges (Oswald et al., 2022). Effective safety instructions (W6) depend on supervisors’ qualifications, which are particularly crucial in HRCW, such as excavation (Tang et al., 2019; Winge et al., 2019). Minimal supervision and inadequate instruction (W6) contributed to the serious injuries of two young, inexperienced workers on their first day at a construction site in NSW (Loosemore and Andonakis, 2007).

The high injury risk among inexperienced workers is attributed to a lack of workers’ knowledge and experience (W2), hazard awareness (W3), ability to handle unexpected events, understanding of workplace safety policies, and greater exposure to hazardous conditions (Breslin et al., 2019). The lack of hazard/situational awareness of workers (W3) is influenced by the repetitive nature of EEOs, which reduces attention and varies based on awareness levels (Hussain et al., 2024). Construction equipment operation relies on cognitive functions such as selective attention, situational awareness, and spatial cognition, further affected by individual factors like experience, fatigue, and working memory, as well as external conditions such as pedestrian workers and other equipment (Cheng and Teizer, 2014; Fang and Cho, 2017). These operations require shared hazard/situational awareness (W3), along with individual recognition of skills, knowledge, and their contribution to team efforts (Harris et al., 2024).

Effective operation communication (W13) enhances the safety climate (Kima et al., 2024) and outcomes in EEOs, such as excavator crews. Communication failures contributed to 17% of 81 fatal plant and machinery incidents on Australian construction sites (Lingard et al., 2013b). Improved operational communication (W13) has the potential to enhance multiple interconnected worker-related factors in EEOs, including reducing job stress of workers (W1), strengthening workers’ knowledge and experience (W2), increasing situational awareness (W3), reinforcing supervisors’ safety commitment (W5) and instruction (W6), improving operators’ proficiency (W9), and ensuring more effective use of personal protective equipment (W11). Improved operational communication fosters clearer task expectations, facilitates timely feedback, and supports informed decision-making on-site. As coordination among workers and supervisors improves, it creates a more supportive environment that indirectly benefits EE’s operators, who frequently rely on such interactions for safe and effective task execution (Mehmood et al., 2024). Although operators’ proficiency (W9) requires adequate training and competency in handling EE and attachments. While formal licenses are not always required, reliance on the VOC process (see section 6.2) raises concerns about assessment consistency, leading to gaps in safety practices, this collective communication reduces cognitive load, enhances situational awareness, reinforces supervisory guidance, encourages proper use of protective equipment, and supports overall task proficiency across the crew (Zamani et al., 2020). Finally, W11 (Personal Protective Equipment) emerges as a risk factor highly influenced by other risk factors within the workforce group. It also exerts cascading influence, meaning that its proper or improper use can significantly affect overall safety performance.

Figure 6(g) highlights weather condition (EN1) as the central factor at the environment level, influencing all other environmental risk factors. This prominence reflects its recurring presence in the literature, where it is often noted for its impact on the physiological and psychological well-being of construction workers in the Australian context (Alashwal and Moustafa, 2022). Increased injury rates have been linked to the frequent operation of heavy machinery and power tools, especially when combined with prolonged exposure to direct sunlight. (Xiang et al., 2014). EEOs in road and highway projects expose workers to heat-generated process such as hot asphalt and paving (Fatima et al., 2023; Taher et al., 2022). Repetitive tasks, combined with weather conditions, further exacerbate fatigue among operators and pedestrian workers. Weather conditions significantly impact safety in Australia, with operators often pressured to work in unsafe conditions to meet deadlines (Lingard et al., 2021). The willingness to halt work in adverse weather varies, influenced by judgement, personality, and employment arrangements. While reputable companies follow safety standards, others may encourage unsafe practices and increasing risks. Heat-related policies in Australian construction remain underdeveloped and require improvement (Fatima et al., 2023). Ground condition (EN4) is another key risk factor, affecting EEOs near the operation of construction equipment like cranes. Unstable ground and underground services pose significant hazards, especially when multiple crews prioritise deadlines over safety (Lingard et al., 2021).

Figure 6(h) highlights Safety reliability of attachment of equipment (EQ1) and safety stability of main structural bodies of the equipment (EQ2) as central factors within the equipment level, showing strong mutual influence. These two interrelated factors collectively impact other equipment-related risks, including failure or disorder of the control system (EQ4), Inappropriate application of equipment for tasks being performed (EQ5), and Blindspot issues (EQ7), indicating that deficiencies in structural stability or attachment reliability can propagate to systemic malfunctions. These two ITIS risk factors align with safety plan of equipment designers (S5) and qualifications of manufacturers (S6) at the stakeholder management level, underscoring their role in equipment design, operational standards, and compliance with OEM recommendations (Edwards et al., 2019). EE classification varies (Taher et al., 2022), but the use of excavators as cranes introduces significant safety hazards, often overlooked by stakeholders. Improper load connection methods and non-compliance with manufacturer guidelines highlight the need for adhering to protocols and integrating proper equipment usage into risk management (Edwards and Holt, 2010). Additionally, assessing excavator stability under dynamic load conditions instead of relying solely on tilt-table performance data can enhance equipment selection and stability considerations (Edwards and Holt, 2009, 2011). Inappropriate application of equipment for tasks (EQ5) is positioned in the fourth quarter, reflecting high dependency on other risk factors. This highlights the importance of a well-defined step-by-step breakdown of tasks and sub-tasks to ensure proper equipment selection, reducing risks and improving operational safety (Soltanmohammadlou et al., 2024a). Reassigning an excavator’s function alters its classification, changing associated hazards and risk factors (Taher et al., 2022).

A clear understanding of cause-and-effect relationships within EEOs reveals that, although the most influential factors lie at the construction site management and workforce levels, both maintain a reciprocal relationship with stakeholder safety management level. The stakeholder management level often serves as the central hub for executing corrective measures, where tangible actions are taken not only to increase awareness but also to translate knowledge into practical improvements (e.g. safety management plans by contractors) (Woolley et al., 2018). Technological interventions across these interconnected levels can support vertical, horizontal, and end-to-end integration of safety management by aligning frontline practices, supervisory actions, and strategic oversight as part of a unified system. This opens the avenue for combining technological solutions to integrate the core functionalities of anticipation, prevention, response, and AI-driven learning within a multi-layered risk management system (Soltanmohammadlou et al., 2024b) that supports task-specific operation in EEOs, human-cantered vulnerabilities, and regulatory compliance simultaneously.

Technologies such as Building Information Modelling (BIM), when integrated meaningfully, can support this multi-level coordination by offering a shared digital environment where regulatory requirements, site-specific conditions, and operational sequences are visualized, simulated, and adjusted in real-time. When we return to the risk factors identified in this research, it becomes clear that technologies must align closely with real-time, task-based risk management. For example, SWMS as documents often remain static in excavation operation, BIM transforms this paradigm by linking these static plans with dynamic site conditions through real-time visualization and data integration. For instance, BIM empowers supervisors to embed SWMS directly within the 3D model environment, enabling the spatial mapping of specific workspaces, tasks, and hazard zones in alignment with the construction schedule via the Work Breakdown Structure (WBS) in EEOs (Moon and Seo, 2017). Through 4D BIM, principal contractors can simulate safety-critical sequences, such as excavation near temporary structures, and proactively adjust timelines or site layouts to mitigate risks, as demonstrated in the study by Abed et al. (2020). Supervisor instructions can be dynamically linked to model-based alerts and digital workflows, ensuring that high-risk scenarios, such as potential trench collapses or activity clashes in EEOs (Abed et al., 2020; Khan et al., 2019), are communicated in real time through visual and data-rich interfaces. Integrating ontology-based knowledge of earthwork operations into BIM has the potential to illuminate the entire excavation lifecycle by transforming BIM from a geometric modelling tool into a semantic, system-aware platform.

The Earthwork Ontology (Taher et al., 2022) enables formal representation of critical concepts such as equipment types, micro-tasks, hazard categories, soil classifications, and regulatory requirements. This structured knowledge allows BIM systems to reason about cause-effect relationships across phases and actor levels, improving hazard detection, excavation planning, and compliance validation. When combined with monitoring technologies like computer vision (for behaviour, task, pattern, and activity recognition), sensor-based systems (for real-time monitoring), and digital twins (for simulation and feedback), BIM becomes the backbone of an integrated safety management system. These connections allow for vertical integration (from policy to site operation), horizontal integration (across project stages and stakeholder roles), and end-to-end integration (from planning through operation and post-excavation review) (Khan et al., 2019).

Understanding cause-and-effect relationships among risk factors enables proactive risk mitigation. For safety managers, this means gaining clearer insights into where interventions should be prioritized within EEOs. This study introduces those focal areas by accounting for context-based influences and identifying reflective zones where upstream causes manifest. Additionally, the empirical representation of causal risk factors, informed by expert insights, serves as an inductive guide for earthmoving operation planners and managers to understand risk factors based on project conditions and policy settings. This has direct implications for improving safety documents, such as codes of practice, SWMs, and VOC. Policy reforms should emphasize collaborative SWMS development with frontline workers and VOC should be reclassified and regulated as a structured certification process tailored to specific equipment types and task complexities within EEOs. The emergence of supervisory factors across various levels, such as site supervision (CS1) and supervisor safety commitment (W2), as causal elements presents an opportunity for stakeholders to enhance supervisory safety leadership characteristics and practices (Oswald et al., 2022). For example, the emergence of supervisory factors across various levels, such as site supervision (CS1) and supervisor safety commitment (W2), as causal elements highlight the need for stakeholders to enhance supervisory safety leadership characteristics and practices.

The study’s findings also prompt critical inquiries into WHS practices, particularly regarding codes of practice for HRCW, such as excavation, which relies heavily on comprehensive and high-level safety instructions. The study highlights the need to address EEO hazards through a structured ITIS delivery. When training processes are aligned with task-specific safety requirements, contractors are better equipped to meet both operational goals and compliance expectations. Moreover, environmental influences such as weather have drawn attention to the issue of providing more weather-responsive regulations by government agencies, where weather is identified as the primary environmental risk in construction operations.

Future research could prioritize the most influential factors and further investigate their interconnections to gain a deeper understanding of their impact. Additionally, future studies should focus on developing Decision Support Systems (DSS) and Expert Systems (ES) to facilitate data-driven safety interventions. Applying the Hierarchical DEMATEL method for analysing complex systems (Du and Li, 2021) is essential for addressing the challenges experts face in evaluating relationships between multiple factors. In Australian construction safety research, MCDM methods remain underexplored, with existing studies predominantly qualitative. This research paves the way for integrating additional MCDM models, such as AHP, ANP, or fuzzy TOPSIS, allowing researchers to compare results across methodologies for a more thorough examination of risk factor behaviour. This research also offers a structured foundation for exploring the dynamics of risk factors in EEOs through a systems ergonomics lens, particularly using the Event Analysis of Systemic Teamwork (EAST) framework, which analyses systems across task, social, and information networks. The identification of dominant causal factors paves the way for a longitudinal ethnographic study and network-based inquiries that capture how safety is shaped through interactions among roles, tasks, and flows of information.

This research has several limitations that should be acknowledged. First, its geographic focus is limited to the Australian construction context, which may affect the broader applicability of the findings to other regions with different regulatory or operational environments. Second, the use of purposive sampling, while appropriate for targeting expert insights, may limit the generalizability of the results. Moreover, it does not differentiate between organizational sizes, small, medium, and large enterprises, which may exhibit distinct safety capacities and practices, particularly in WHS system maturity. As a final point, the analysis does not account for the temporal evolution of causal risk factors, leaving the dynamic nature of risk interactions underexplored.

This study was driven by the need for formal risk modelling in EEOs to streamline hazard recognition, evaluation, and risk assessment, ensuring more targeted and effective interventions within the Australian construction context. In Australian construction safety research, no prior study has examined the importance of existing causes and their interrelationships within a system while addressing the uncertainty inherent in construction activities, particularly in EEOs. This research conducted a meticulous investigation, integrating a one-step qualitative approach, which validated expert identification of EEO risk factors, with a quantitative three-step methodology. The quantitative approach combines corrected item-total correlation and split-half methods to calculate response consistency within the FDEMATEL framework, followed by rigorous sensitivity analysis to ensure robustness and reliability. The results uncover cause-and-effect relationships of risk factors across each level of (Rasmussen, 1997) RMF using a systems thinking approach, culminating in an Impact Relations Map (IRM) that classifies risk factors based on their causal and effect-driven roles. This understanding provides a foundation for guiding the integration of targeted technologies to address causal factors more effectively and enhance system-wide safety interventions.

This paper forms part of a special section “Beyond BIM – Navigating the Transformative Journey of the AECO Industry”, guest edited by Mehran Oraee, M. Reza Hosseini and Farzad Rahimian.

This work was supported by a Ph.D. scholarship of BUILDING 4.0 CRC. The support of the Commonwealth of Australia through the Cooperative Research Centre Program is acknowledged.

Data availability: The total direct–indirect matrix, before and after isolating minor effects, will be made available upon request.

Declaration of interest: This work is supported by Ph.D. scholarship of BUILDING 4.0 CRC. The support of the Commonwealth of Australia through the Cooperative Research Centre Program is acknowledged. All writers confirm that there is no known conflict of interest associated with this publication.

Ethical approval: Ethical approval for this research was granted by the Queensland University of Technology (QUT) University Human Research Ethics Committee (UHREC) or its delegated review body as meeting the requirements of the National Statement on Ethical Conduct in Human Research (reference number: LR, 2023–5693–16275). The approval affirms the ethical rigour of the research design, including the informed consent process, participant confidentiality, and the responsible handling of data.

Abed
,
H.R.
,
Hatem
,
W.A.
and
Jasim
,
N.A.
(
2020
), “
Role of BIM technology in enhancing safety analysis of Iraqi oil projects
”,
Asian Journal of Civil Engineering
, Vol. 
21
No. 
4
, pp. 
695
-
706
, doi: .
Alashwal
,
A.
and
Moustafa
,
A.A.
(
2022
), “
Weather and suicide of construction workers in Australia
”,
Proceedings of World Building Congress: Building our future, IOP Conference Series: Earth and Environmental Science
, Vol. 
1101
No. 
3
, 032010, doi: .
Alshahrani
,
R.
,
Yenugula
,
M.
,
Algethami
,
H.
,
Alharbi
,
F.
,
Goswami
,
S.S.
,
Naveed
,
Q.N.
,
Lasisi
,
A.
,
Islam
,
S.
,
Khan
,
N.A.
and
Zahmatkesh
,
S.
(
2024
), “
Establishing the fuzzy integrated hybrid MCDM framework to identify the key barriers to implementing artificial intelligence-enabled sustainable cloud system in an IT industry
”,
Expert Systems with Applications
, Vol. 
238
, 121732, doi: .
Alshboul
,
O.
,
Shehadeh
,
A.
,
Tatari
,
O.
,
Almasabha
,
G.
and
Saleh
,
E.
(
2024
), “
Multiobjective and multivariable optimization for earthmoving equipment
”,
Journal of Facilities Management
, Vol. 
22
No. 
1
, pp. 
21
-
48
, doi: .
Apaydın
,
O.
and
Aladağ
,
Z.
(
2022
), “
Ranking the evaluation criteria of Hi-Fi audio systems and constricted information space: a novel method for determining the DEMATEL threshold value
”,
Applied Acoustics
, Vol. 
190
, 108584, doi: .
Bayramova
,
A.
,
Edwards
,
D.J.
,
Roberts
,
C.
and
Rillie
,
I.
(
2023
), “
Enhanced safety in complex socio-technical systems via safety-in-cohesion
”,
Safety Science
, Vol. 
164
, 106176, doi: .
Bayramova
,
A.
,
Edwards
,
D.J.
,
Roberts
,
C.
and
Rillie
,
I.
(
2024
), “
Uncovering the genome of leading indicators from lagging indicators and normative documents: a proof-of-concept study
”,
Journal of Safety Research
, Vol. 
91
, pp. 
230
-
244
, doi: .
Bellman
,
R.E.
and
Zadeh
,
L.A.
(
1970
), “
Decision-making in a fuzzy environment
”,
Management Science
, Vol. 
17
No. 
4
, pp. 
141
-
164
, doi: .
Biggs
,
H.C.
and
Biggs
,
S.E.
(
2013
), “
Interlocked projects in safety competency and safety effectiveness indicators in the construction sector
”,
Safety Science
, Vol. 
52
, pp. 
37
-
42
, doi: .
Biggs
,
S.E.
,
Banks
,
T.D.
,
Davey
,
J.D.
and
Freeman
,
J.E.
(
2013
), “
Safety leaders’ perceptions of safety culture in a large Australasian construction organisation
”,
Safety Science
, Vol. 
52
, pp. 
3
-
12
, doi: .
Bluff
,
E.
(
2019
), “
How SMEs respond to legal requirements to provide information, training, instruction and supervision to workers about work health and safety matters
”,
Safety Science
, Vol. 
116
, pp. 
45
-
57
, doi: .
Breslin
,
F.C.
,
Dollack
,
J.
,
Mahood
,
Q.
,
Maas
,
E.T.
,
Laberge
,
M.
and
Smith
,
P.M.
(
2019
), “
Are new workers at elevated risk for work injury? A systematic review
”,
Occupational and Environmental Medicine
, Vol. 
76
No. 
9
, pp.
694
-
701
, doi: .
Cheng
,
T.
and
Teizer
,
J.
(
2014
), “
Modeling tower crane operator visibility to minimize the risk of limited situational awareness
”,
Journal of Computing in Civil Engineering
, Vol. 
28
No. 
3
, 04014004, doi: .
Cheng
,
M.
,
Liu
,
L.
,
Cheng
,
X.
and
Tao
,
L.
(
2024
), “
Risk analysis of public-private partnership waste-to-energy incineration projects in China: a hybrid fuzzy DEMATEL-ISM approach
”,
Engineering Construction and Architectural Management
, Vol. 
31
No. 
11
, pp. 
4255
-
4280
, doi: .
Choi
,
M.
,
Ahn
,
S.
and
Seo
,
J.
(
2020
), “
VR-Based investigation of forklift operator situation awareness for preventing collision accidents
”,
Accident Analysis and Prevention
, Vol. 
136
, 105404, doi: .
Dashti
,
M.S.
,
RezaZadeh
,
M.
,
Khanzadi
,
M.
and
Taghaddos
,
H.
(
2021
), “
Integrated BIM-based simulation for automated time-space conflict management in construction projects
”,
Automation in Construction
, Vol. 
132
, 103957, doi: .
Du
,
Y.-W.
and
Li
,
X.-X.
(
2021
), “
Hierarchical DEMATEL method for complex systems
”,
Expert Systems with Applications
, Vol. 
167
, 113871, doi: .
Edwards
,
D.J.
and
Holt
,
G.D.
(
2008
), “
Health and safety issues relating to construction excavators and their attachments
”,
Engineering Construction and Architectural Management
, Vol. 
15
No. 
4
, pp. 
321
-
335
, doi: .
Edwards
,
D.J.
and
Holt
,
G.D.
(
2009
), “
New stability field tests for construction excavators
”,
Engineering Construction and Architectural Management
, Vol. 
16
No. 
4
, pp. 
337
-
352
, doi: .
Edwards
,
D.J.
and
Holt
,
G.D.
(
2010
), “
Case study analysis of risk from using excavators as cranes
”,
Automation in Construction
, Vol. 
19
No. 
2
, pp. 
127
-
133
, doi: .
Edwards
,
D.J.
and
Holt
,
G.D.
(
2011
), “
Mini-excavator safety: toward innovative stability testing, procurement, and manufacture
”,
Journal of Construction Engineering and Management
, Vol. 
137
No. 
12
, pp. 
1125
-
1133
, doi: .
Edwards
,
D.J.
and
Love
,
P.E.D.
(
2016
), “
A case study of machinery maintenance protocols and procedures within the UK utilities sector dedicated to MRS. June Edwards, a lady of great distinction who preserved the health and dignity of others for many years. A loving mother and grandmother, without whose help, this work and many achievements would not have been possible
”,
Accident Analysis and Prevention
, Vol. 
93
, pp. 
319
-
329
, doi: .
Edwards
,
D.J.
,
Holt
,
G.D.
and
Robinson
,
B.
(
2002
), “
An artificial intelligence approach for improving plant operator maintenance proficiency
”,
Journal of Quality in Maintenance Engineering
, Vol. 
8
No. 
3
, pp. 
239
-
252
, doi: .
Edwards
,
D.
,
Parn
,
E.A.
,
Sing
,
M.C.P.
and
Thwala
,
W.D.
(
2019
), “
Risk of excavators overturning: determining horizontal centrifugal force when slewing freely suspended loads
”,
Engineering Construction and Architectural Management
, Vol. 
26
No. 
3
, pp. 
479
-
498
, doi: .
Fang
,
Y.
and
Cho
,
Y.K.
(
2017
), “
Effectiveness analysis from a cognitive perspective for a real-time safety assistance system for Mobile crane lifting operations
”,
Journal of Construction Engineering and Management
, Vol. 
143
No. 
4
, 05016025, doi: .
Fang
,
W.
,
Ding
,
L.
,
Love
,
P.E.D.
,
Luo
,
H.
,
Li
,
H.
,
Peña-Mora
,
F.
,
Zhong
,
B.
and
Zhou
,
C.
(
2020
), “
Computer vision applications in construction safety assurance
”,
Automation in Construction
, Vol. 
110
, 103013, doi: .
Fatima
,
S.H.
,
Rothmore
,
P.
,
Giles
,
L.C.
and
Bi
,
P.
(
2023
), “
Impacts of hot climatic conditions on work, health, and safety in Australia: a case study of policies in practice in the construction industry
”,
Safety Science
, Vol. 
165
, 106197, doi: .
Fontela
,
E.
(
1976
), “The DEMATEL observer”, in
DEMATEL
.
Getuli
,
V.
,
Bruttini
,
A.
and
Rahimian
,
F.
(
2025
), “
Parametric design methodology for developing BIM object libraries in construction site modeling
”,
Automation in Construction
, Vol. 
170
, 105897, doi: .
Gibb
,
A.
,
Lingard
,
H.
,
Behm
,
M.
and
Cooke
,
T.
(
2014
), “
Construction accident causality: learning from different countries and differing consequences
”,
Construction Management and Economics
, Vol. 
32
No. 
5
, pp. 
446
-
459
, doi: .
Guo
,
B.H.W.
,
Zou
,
Y.
,
Fang
,
Y.
,
Goh
,
Y.M.
and
Zou
,
P.X.W.
(
2021
), “
Computer vision technologies for safety science and management in construction: a critical review and future research directions
”,
Safety Science
, Vol. 
135
, 105130, doi: .
Guo
,
X.
,
Yang
,
Z.
,
Sun
,
J.
and
Zhang
,
Y.
(
2024
), “
Impact pathways of emerging ITs to mitigate supply chain vulnerability: a novel DEMATEL-ISM approach based on grounded theory
”,
Expert Systems with Applications
, Vol. 
239
, 122398, doi: .
Gutierrez-Bucheli
,
L.
,
Goh
,
J.T.
,
Rashidi
,
A.
,
Maxwell
,
D.
,
Digby
,
R.
,
Fang
,
Y.
,
Pook
,
H.
and
Arashpour
,
M.
(
2024
), “
Adopting immersive technologies in construction training: determining educational decision-making criteria through a Delphi technique
”,
Smart and Sustainable Built Environment
, Vol. 
ahead-of-print
 
No. ahead-of-print
, doi: .
Hale
,
A.
and
Borys
,
D.
(
2013a
), “
Working to rule or working safely? Part 2: the management of safety rules and procedures
”,
Safety Science
, Vol. 
55
, pp. 
222
-
231
, doi: .
Hale
,
A.
and
Borys
,
D.
(
2013b
), “
Working to rule, or working safely? Part 1: a state of the art review
”,
Safety Science
, Vol. 
55
, pp. 
207
-
221
, doi: .
Harris
,
K.M.
,
Stankovic
,
A.
,
Thoolen
,
S.
,
Strangman
,
G.
,
Caldwell
,
B.
and
Robinson
,
S.K.
(
2024
), “
Team dynamics and collaborative problem-solving for lunar construction: lessons from complex construction scenarios on Earth
”,
Human Factors
, Vol. 
66
No. 
5
, pp. 
1616
-
1632
, doi: .
Hinze
,
J.W.
and
Teizer
,
J.
(
2011
), “
Visibility-related fatalities related to construction equipment
”,
Safety Science
, Vol. 
49
No. 
5
, pp. 
709
-
718
, doi: .
Hinze
,
J.
,
Huang
,
X.
and
Terry
,
L.
(
2005
), “
The nature of struck-by accidents
”,
Journal of Construction Engineering and Management
, Vol. 
131
No. 
2
, pp. 
262
-
268
, doi: .
Hinze
,
J.
,
Olbina
,
S.
,
Orozco
,
J.
and
Beaumont
,
K.
(
2017
), “
Earthmoving equipment fatalities in the construction industry
”,
Practice Periodical on Structural Design and Construction
, Vol. 
22
No. 
4
, 04017015, doi: .
Hollnagel
,
E.
and
Slater
,
D.
(
2018
), “
The functional RESONANCE analysis method and manual (Version 2)
”.
Hussain
,
R.
,
Zaidi
,
S.F.A.
,
Pedro
,
A.
,
Lee
,
H.
and
Park
,
C.
(
2024
), “
Exploring construction workers’ attention and awareness in diverse virtual hazard scenarios to prevent struck-by accidents
”,
Safety Science
, Vol. 
175
, 106526, doi: .
Ilbahar
,
E.
,
Karaşan
,
A.
,
Cebi
,
S.
and
Kahraman
,
C.
(
2018
), “
A novel approach to risk assessment for occupational health and safety using Pythagorean fuzzy AHP and fuzzy inference system
”,
Safety Science
, Vol. 
103
, pp. 
124
-
136
, doi: .
Jalil Al-Bayati
,
A.
,
Rener
,
A.T.
,
Listello
,
M.P.
and
Mohamed
,
M.
(
2023
), “
PPE non-compliance among construction workers: an assessment of contributing factors utilizing fuzzy theory
”,
Journal of Safety Research
, Vol. 
85
, pp. 
242
-
253
, doi: .
Johansen
,
K.W.
,
Nielsen
,
R.
,
Schultz
,
C.
and
Teizer
,
J.
(
2021
), “
Automated activity and progress analysis based on non-monotonic reasoning of construction operations
”,
Smart and Sustainable Built Environment
, Vol. 
10
No. 
3
, pp. 
457
-
486
, doi: .
Kazan
,
E.
and
Usmen
,
M.A.
(
2018
), “
Worker safety and injury severity analysis of earthmoving equipment accidents
”,
Journal of Safety Research
, Vol. 
65
, pp. 
73
-
81
, doi: .
Khan
,
N.
,
Ali
,
A.K.
,
Skibniewski
,
M.J.
,
Lee
,
D.Y.
and
Park
,
C.
(
2019
), “
Excavation safety modeling approach using BIM and VPL
”,
Advances in Civil Engineering
, Vol. 
2019
No. 
1
, 1515808, doi: .
Khorrami Shad
,
H.
,
Tak Wing Yiu
,
K.
,
Lovreglio
,
R.
and
Feng
,
Z.
(
2024
), “
State-of-the-art analysis of the integration of augmented reality with construction technologies to improve construction safety
”,
Smart and Sustainable Built Environment
, Vol. 
13
No. 
6
, pp. 
1434
-
1449
, doi: .
Kiani Mavi
,
N.
,
Brown
,
K.
,
Fulford
,
R.G.
and
Goh
,
M.
(
2024
), “
An MCDM analysis of critical success criteria for medium and large construction projects in Australia and New Zealand
”,
Engineering Construction and Architectural Management
, Vol. 
ahead-of-print
 
No. ahead-of-print
, doi: .
Kima
,
O.
,
Urlainis
,
A.
,
Wang
,
K.-C.
and
Shohet
,
I.M.
(
2024
), “
Safety climate in small and medium construction enterprises
”,
Smart and Sustainable Built Environment
, Vol. 
ahead-of-print
 
No. ahead-of-print
, doi: .
Kulinan
,
A.S.
,
Park
,
M.
,
Aung
,
P.P.W.
,
Cha
,
G.
and
Park
,
S.
(
2024
), “
Advancing construction site workforce safety monitoring through BIM and computer vision integration
”,
Automation in Construction
, Vol. 
158
, 105227, doi: .
Kumar
,
S.S.
and
Cheng
,
J.C.
(
2015
), “
A BIM-based automated site layout planning framework for congested construction sites
”,
Automation in Construction
, Vol. 
59
, pp. 
24
-
37
, doi: .
Lingard
,
H.
and
Pirzadeh
,
P.
(
2025
), “
Workplace health and safety performance at the client-contractor interface: measurement, management and behaviour
”,
Safety Science
, Vol. 
184
, 106753, doi: .
Lingard
,
H.
,
Blismas
,
N.
,
Cooke
,
T.
and
Cooper
,
H.
(
2009
), “
The model client framework: resources to help Australian government agencies to promote safe construction
”,
International Journal of Managing Projects in Business
, Vol. 
2
No. 
1
, pp. 
131
-
140
.
Lingard
,
H.
,
Cooke
,
T.
and
Gharaie
,
E.
(
2013a
), “
A case study analysis of fatal incidents involving excavators in the Australian construction industry
”,
Engineering Construction and Architectural Management
, Vol. 
20
No. 
5
, pp. 
488
-
504
, 17097846, doi: .
Lingard
,
H.
,
Cooke
,
T.
and
Gharaie
,
E.
(
2013b
), “
The how and why of plant-related fatalities in the Australian construction industry
”,
Engineering Construction and Architectural Management
, Vol. 
20
No. 
4
, pp. 
365
-
380
, doi: .
Lingard
,
H.
,
Oswald
,
D.
and
Le
,
T.
(
2019
), “
Embedding occupational health and safety in the procurement and management of infrastructure projects: institutional logics at play in the context of new public management
”,
Construction Management and Economics
, Vol. 
37
No. 
10
, pp. 
567
-
583
, doi: .
Lingard
,
H.
,
Cooke
,
T.
,
Zelic
,
G.
and
Harley
,
J.
(
2021
), “
A qualitative analysis of crane safety incident causation in the Australian construction industry
”,
Safety Science
, Vol. 
133
, 105028, doi: .
Loosemore
,
M.
and
Andonakis
,
N.
(
2007
), “
Barriers to implementing OHS reforms–the experiences of small subcontractors in the Australian construction industry
”,
International Journal of Project Management
, Vol. 
25
No. 
6
, pp. 
579
-
588
, doi: .
Luo
,
H.
,
Wang
,
M.
,
Wong
,
P.K.Y.
and
Cheng
,
J.C.P.
(
2020
), “
Full body pose estimation of construction equipment using computer vision and deep learning techniques
”,
Automation in Construction
, Vol. 
110
, 103016, doi: .
Mehmood
,
I.
,
Li
,
H.
,
Qarout
,
Y.
,
Umer
,
W.
,
Anwer
,
S.
,
Wu
,
H.
,
Hussain
,
M.
and
Antwi-Afari
,
M.F.
(
2023
), “
Deep learning-based construction equipment operators’ mental fatigue classification using wearable EEG sensor data
”,
Advanced Engineering Informatics
, Vol. 
56
, 101978, doi: .
Mehmood
,
I.
,
Li
,
H.
,
Umer
,
W.
,
Ma
,
J.
,
Shakeel
,
M.S.
,
Anwer
,
S.
,
Antwi-Afari
,
M.F.
,
Tariq
,
S.
and
Wu
,
H.
(
2024
), “
Non-invasive detection of mental fatigue in construction equipment operators through geometric measurements of facial features
”,
Journal of Safety Research
, Vol. 
89
, pp. 
234
-
250
, doi: .
Mohandes
,
S.R.
,
Sadeghi
,
H.
,
Fazeli
,
A.
,
Mahdiyar
,
A.
,
Hosseini
,
M.R.
,
Arashpour
,
M.
and
Zayed
,
T.
(
2022
), “
Causal analysis of accidents on construction sites: a hybrid fuzzy Delphi and DEMATEL approach
”,
Safety Science
, Vol. 
151
, 105730, doi: .
Moon
,
S.
and
Seo
,
J.
(
2017
), “
Virtual graphic representation of construction equipment for developing a 3D earthwork BIM
”,
Journal of Civil Engineering and Management
, Vol. 
23
No. 
8
, pp. 
977
-
984
, doi: .
Moshtaghian
,
F.
and
Noorzai
,
E.
(
2023
), “
Integration of risk management within the building information modeling (BIM) framework
”,
Engineering Construction and Architectural Management
, Vol. 
30
No. 
5
, pp. 
1951
-
1977
, doi: .
Nelumdeniya
,
A.U.
,
Perera
,
B.
and
Gimhani
,
K.
(
2023
), “
Usage of digital technology in improving the mental health of workers on construction sites
”,
Construction Innovation
, Vol. 
25
No. 
3
, pp. 
931
-
971
, doi: .
Newaz
,
M.T.
,
Davis
,
P.R.
,
Jefferies
,
M.
and
Pillay
,
M.
(
2019
), “
Validation of an agent-specific safety climate model for construction
”,
Engineering Construction and Architectural Management
, Vol. 
26
No. 
3
, pp. 
462
-
478
, doi: .
O'Neill
,
C.
,
Gopaldasani
,
V.
and
Coman
,
R.
(
2022
), “
Factors that influence the effective use of safe work method statements for high-risk construction work in Australia–A literature review
”,
Safety Science
, Vol. 
147
, 105628, doi: .
Ocampo
,
L.A.
,
Tan
,
T.A.G.
and
Sia
,
L.A.
(
2018
), “
Using fuzzy DEMATEL in modeling the causal relationships of the antecedents of organizational citizenship behavior (OCB) in the hospitality industry: a case study in the Philippines
”,
Journal of Hospitality and Tourism Management
, Vol. 
34
, pp. 
11
-
29
, doi: .
Office of Parliamentary Counsel
(
2018
),
Work Health and Safety Act 2011
,
Office of Parliamentary Counsel
,
Canberra
.
Oswald
,
D.
,
Lingard
,
H.
and
Zhang
,
R.P.
(
2022
), “
How transactional and transformational safety leadership behaviours are demonstrated within the construction industry
”,
Construction Management and Economics
, Vol. 
40
No. 
5
, pp. 
374
-
390
, doi: .
Rashidi
,
A.
,
Woon
,
G.L.
,
Dasandara
,
M.
,
Bazghaleh
,
M.
and
Pasbakhsh
,
P.
(
2024
), “
Smart personal protective equipment for intelligent construction safety monitoring
”,
Smart and Sustainable Built Environment
, Vol. 
14
No. 
3
, pp. 
835
-
858
, doi: .
Rasmussen
,
J.
(
1997
), “
Risk management in a dynamic society: a modelling problem
”,
Safety Science
, Vol. 
27
Nos
2-3
, pp. 
183
-
213
, doi: .
Ren
,
J.
,
Jenkinson
,
I.
,
Wang
,
J.
,
Xu
,
D.
and
Yang
,
J.
(
2008
), “
A methodology to model causal relationships on offshore safety assessment focusing on human and organizational factors
”,
Journal of Safety Research
, Vol. 
39
No. 
1
, pp. 
87
-
100
, doi: .
Riaz
,
Z.
,
Edwards
,
D.J.
and
Thorpe
,
A.
(
2006
), “
SightSafety: a hybrid information and communication technology system for reducing vehicle/pedestrian collisions
”,
Automation in Construction
, Vol. 
15
No. 
6
, pp. 
719
-
728
, doi: .
Riaz
,
Z.
,
Edwards
,
D.J.
,
Holt
,
G.D.
and
Thorpe
,
T.
(
2011
), “
Data flow analysis of plant and equipment health and safety management
”,
Journal of Engineering, Design and Technology
, Vol. 
9
No. 
2
, pp. 
178
-
203
, doi: .
Rostamnezhad
,
M.
,
Nasirzadeh
,
F.
,
Khanzadi
,
M.
,
Jarban
,
M.J.
and
Ghayoumian
,
M.
(
2020
), “
Modeling social sustainability in construction projects by integrating system dynamics and fuzzy‐DEMATEL method: a case study of highway project
”,
Engineering Construction and Architectural Management
, Vol. 
27
No. 
7
, pp. 
1595
-
1618
, doi: .
Sadeghi
,
H.
,
Zhang
,
X.
and
Mohandes
,
S.R.
(
2023
), “
Developing an ensemble risk analysis framework for improving the safety of tower crane operations under coupled Fuzzy-based environment
”,
Safety Science
, Vol. 
158
, 105957, doi: .
Safe Work Australia
(
2021
), “
Excavation work code of practice 2021
”,
available at:
 https://www.worksafe.qld.gov.au/__data/assets/pdf_file/0018/72630/excavation-work-cop-2021.pdf
Safe Work Australia
(
2023
), “
Interactive data
”,
available at:
 https://data.safeworkaustralia.gov.au/interactive-data/industry/construction
Safe Work Australia
(
2024a
), “
Managing the risks of plant in the workplace, code of practice
”,
available at:
 https://www.safeworkaustralia.gov.au/sites/default/files/2024-11/model_code_of_practice-managing_the_risks_of_plant_in_the_workplace-nov24.pdf
Safe Work Australia
(
2024b
), “
Model work health and safety regulations
”,
The Parliamentary Counsel’s Committee, available at:
 https://www.safeworkaustralia.gov.au/sites/default/files/2024-08/consolidated_model_whs_regulations_-1_september_2024.pdf
Shehadeh
,
A.
,
Alshboul
,
O.
,
Tatari
,
O.
,
Alzubaidi
,
M.A.
and
Salama
,
A.H.E.-S.
(
2022
), “
Selection of heavy machinery for earthwork activities: a multi-objective optimization approach using a genetic algorithm
”,
Alexandria Engineering Journal
, Vol. 
61
No. 
10
, pp. 
7555
-
7569
, doi: .
Shieh
,
J.I.
and
Wu
,
H.H.
(
2016
), “
Measures of consistency for DEMATEL method
”,
Communications in Statistics – Simulation and Computation
, Vol. 
45
No. 
3
, pp. 
781
-
790
, doi: .
Si
,
S.-L.
,
You
,
X.-Y.
,
Liu
,
H.-C.
and
Zhang
,
P.
(
2018
), “
DEMATEL technique: a systematic review of the state‐of‐the‐art literature on methodologies and applications
”,
Mathematical Problems in Engineering
, Vol. 
2018
No. 
1
, 3696457, doi: .
Soltanmohammadlou
,
N.
,
Hon
,
C.K.
and
Drogemuller
,
R.
(
2024a
), “
Applying systems thinking to research into risk factors influencing earthmoving equipment operation safety in construction sites
”,
Buildings
, Vol. 
14
No. 
7
, p.
1978
, doi: .
Soltanmohammadlou
,
N.
,
Hon
,
C.K.
,
Drogemuller
,
R.
,
Sheikhkhoshkar
,
M.
and
Rahimian
,
F.
(
2024b
), “
An advanced exploration of technological functionalities addressing risk factors in earthmoving equipment operation on construction sites: a systematic literature review
”,
Smart and Sustainable Built Environment
, Vol.
ahead-of-print
No.
ahead-of-print
, doi: .
Sony
,
M.
and
Naik
,
S.
(
2020
), “
Industry 4.0 integration with socio-technical systems theory: a systematic review and proposed theoretical model
”,
Technology in Society
, Vol. 
61
, 101248, doi: .
Suri
,
H.
(
2011
), “
Purposeful sampling in qualitative research synthesis
”,
Qualitative Research Journal
, Vol. 
11
No. 
2
, pp. 
63
-
75
, doi: .
Taher
,
A.
,
Vahdatikhaki
,
F.
and
Hammad
,
A.
(
2019
), “
Integrating earthwork ontology and safety regulations to enhance operations safety
”,
36th International Symposium on Automation and Robotics in Construction, ISARC
.
Taher
,
A.
,
Vahdatikhaki
,
F.
and
Hammad
,
A.
(
2022
), “
Formalizing knowledge representation in earthwork operations through development of domain ontology
”,
Engineering Construction and Architectural Management
, Vol. 
29
No. 
6
, pp. 
2382
-
2414
, doi: .
Tang
,
N.
,
Hu
,
H.
,
Xu
,
F.
and
Zhu
,
F.
(
2019
), “
Personalized safety instruction system for construction site based on internet technology
”,
Safety Science
, Vol. 
116
, pp. 
161
-
169
, doi: .
Tzeng
,
G.-H.
,
Chiang
,
C.-H.
and
Li
,
C.-W.
(
2007
), “
Evaluating intertwined effects in e-learning programs: a novel hybrid MCDM model based on factor analysis and DEMATEL
”,
Expert Systems with Applications
, Vol. 
32
No. 
4
, pp. 
1028
-
1044
, doi: .
Wang
,
M.
,
Deng
,
Y.
,
Won
,
J.
and
Cheng
,
J.C.
(
2019
), “
An integrated underground utility management and decision support based on BIM and GIS
”,
Automation in Construction
, Vol. 
107
, 102931, doi: .
Wen
,
L.
,
Kim
,
D.
,
Liu
,
M.
and
Lee
,
S.
(
2023
), “
3D excavator pose estimation using projection-based pose optimization for contact-driven hazard monitoring
”,
Journal of Computing in Civil Engineering
, Vol. 
37
No. 
1
, 04022048, doi: .
Winge
,
S.
,
Albrechtsen
,
E.
and
Arnesen
,
J.
(
2019
), “
A comparative analysis of safety management and safety performance in twelve construction projects
”,
Journal of Safety Research
, Vol. 
71
, pp. 
139
-
152
, doi: .
Woolley
,
M.
(
2020
),
Development of a Systems Thinking–based Incident Analysis Method for Construction
,
University of the Sunshine Coast
,
Queensland
.
Woolley
,
M.J.
,
Goode
,
N.
,
Read
,
G.J.
and
Salmon
,
P.M.
(
2018
), “
Moving beyond the organizational ceiling: do construction accident investigations align with systems thinking?
”,
Human Factors and Ergonomics in Manufacturing and Service Industries
, Vol. 
28
No. 
6
, pp. 
297
-
308
, doi: .
Wu
,
H.-H.
and
Tsai
,
Y.-N.
(
2011
), “
A DEMATEL method to evaluate the causal relations among the criteria in auto spare parts industry
”,
Applied Mathematics and Computation
, Vol. 
218
No. 
5
, pp. 
2334
-
2342
, doi: .
Wu
,
H.-H.
and
Tsai
,
Y.-N.
(
2012
), “
Using AHP to evaluate the criteria of auto spare parts industry
”,
Quality and Quantity
, Vol. 
46
No. 
1
, pp. 
359
-
364
, doi: .
Wu
,
H.
,
Zhong
,
W.
,
Zhong
,
B.
,
Li
,
H.
,
Guo
,
J.
and
Mehmood
,
I.
(
2025
), “
Barrier identification, analysis and solutions of blockchain adoption in construction: a fuzzy DEMATEL and TOE integrated method
”,
Engineering Construction and Architectural Management
, Vol. 
32
No. 
1
, pp. 
409
-
426
, doi: .
Xiang
,
J.
,
Bi
,
P.
,
Pisaniello
,
D.
,
Hansen
,
A.
and
Sullivan
,
T.
(
2014
), “
Association between high temperature and work-related injuries in Adelaide, South Australia, 2001-2010
”,
Occupational and Environmental Medicine
, Vol. 
71
No. 
4
, pp. 
246
-
252
, doi: .
Yu
,
R.
and
Ma
,
L.
(
2024
), “
Risk evaluation of mega infrastructure construction supply chain in engineering-procurement-construction projects: an integrated fuzzy AHP and fuzzy DEMATEL approach
”,
Engineering Construction and Architectural Management
, Vol. 
32
No. 
5
, pp. 
3217
-
3235
, doi: .
Zadeh
,
L.A.
(
1965
), “
Fuzzy sets
”,
Information and control
, Vol. 
8
No. 
3
, pp. 
338
-
353
, doi: .
Zadeh
,
L.A.
(
1975
), “
The concept of a linguistic variable and its application to approximate reasoning—I
”,
Information Sciences
, Vol. 
8
No. 
3
, pp. 
199
-
249
, doi: .
Zamani
,
V.
,
Banihashemi
,
S.Y.
and
Abbasi
,
A.
(
2020
), “
How can communication networks among excavator crew members in construction projects affect the relationship between safety climate and safety outcomes?
”,
Safety Science
, Vol. 
128
, 104737, doi: .
Zhang
,
X.
,
Zhang
,
W.
,
Jiang
,
L.
and
Zhao
,
T.
(
2020
), “
Identification of critical causes of tower-crane accidents through system thinking and case analysis
”,
Journal of Construction Engineering and Management
, Vol. 
146
No. 
7
, 04020071, doi: .
Zhao
,
J.
,
Cao
,
Y.
and
Xiang
,
Y.
(
2024
), “
Pose estimation method for construction machine based on improved AlphaPose model
”,
Engineering Construction and Architectural Management
, Vol. 
31
No. 
3
, pp. 
976
-
996
, doi: .
Zhou
,
W.
,
Zhao
,
T.S.
,
Liu
,
W.
and
Tang
,
J.J.
(
2018
), “
Tower crane safety on construction sites: a complex sociotechnical system perspective
”,
Safety Science
, Vol. 
109
, pp. 
95
-
108
, doi: .
Zhu
,
R.
,
Hu
,
X.
,
Wei
,
A.
,
Yang
,
W.
and
Ji
,
F.
(
2024
), “
Measuring safety performance of construction employees using data envelopment analysis: a case in Australia
”,
Journal of Safety Research
, Vol. 
88
, pp. 
293
-
302
, doi: .
Published by Emerald Publishing Limited. This article is published under the Creative Commons Attribution (CC BY 4.0) licence. Anyone may reproduce, distribute, translate and create derivative works of this article (for both commercial and non-commercial purposes), subject to full attribution to the original publication and authors. The full terms of this licence may be seen at http://creativecommons.org/licences/by/4.0/legalcode

Data & Figures

Figure 1
A flowchart shows the research method involving identification of risk factors.The flowchart is divided into three main sections, each enclosed in a dashed box. The sections are interconnected with arrows indicating the process flow. The left section is labeled “Identification of Risk Factors.” It shows a flowchart with four sequence steps from top to bottom: Step 1: Identification of Key Risk Categories and Their Sub-Factors Through Literature Review and Code of Practices. This step has an icon of a yellow warning sign with an exclamation mark and a magnifying glass. Step 2: Contextualization and Validation of Risk Factors of E E O s Through Interviewing Competent Experts in Australia. This step has an icon of two people with a checkmark and speech bubbles. Step 3: Analysing the interviews for identification of new risk factors. This step has an icon of a person analyzing reports. Step 4: Designing a Questionnaire for Data Collection. This step has an icon of a clipboard with a pencil and paper. Arrows connect these boxes downward, indicating the sequence. An arrow from step 4 leads to the second section in the middle. The middle section is labeled “Designing the Fuzzy DEMATEL Survey.” It shows a flowchart with nine sequence steps from top to bottom: Step 1: Questionnaire distribution to the experts. Step 2: Generating the fuzzy initial direct-relation matrix. Step 3: Consistency Rate Calculation. Step 4: Aggregating the direct-relation matrices. Step 5: Normalizing the direct relation matrix. Step 6: Developing the total (direct–indirect) relation matrix. Step 7: Converting the values of the total relation matrix into crisp values. Step 8: Set threshold value and obtain the Impact Relations Map (I R M). Step 9: Generating Impact Relations Map (I R M). An arrow from the “Consistency Rate Calculation” step points rightwards to the next section. The right section has 2 subsections. Both sections are enclosed in a dashed box. The first subsection is labeled “Consistency Rate Calculation.” It shows a flowchart as follows: The flowchart flows vertically from top to bottom, with various shapes and icons connected by arrows. At the top, a rounded rectangle labeled “Start.” Below it, a rectangular box titled “Fuzzy Number Transformation into Vector Format.” This box contains a depiction of multiple stacked sheets or tables with fuzzy numbers transformed into vectors, showing matrices with numerical values such as 0.25, 0.5, 0.75, 1, et cetera. Next, a rectangular process box with a graphic showing overlapping circles containing colored icons representing respondents. The text inside reads, “Calculate the estimation of each respondent with the average of other respondents.” A decision diamond follows with the question, “If smaller collation is less than 0.3, question mark.” The diamond shows two arrows: If “Yes,” it leads to a rectangular process box to the right that says, “Remove the respondent with the lowest solution,” accompanied by an icon of a single respondent figure. The rectangular box leads back to the process box. If “No,” it continues downward. Below the decision box is a process box illustrating “Generate all possible split half,” showing the respondents split into three groups inside overlapping circles. Then, two process boxes follow sequentially: “Compute the correlation value of each split half.” “Compute the average adjusted split-half correlation.” Finally, the flowchart ends with another rounded rectangle labeled “Start,” indicating either a loop or the conclusion of the process. On the left side of the dashed box, there is a large circular icon with arrows in orange and blue, forming a loop around a checkmark. The second subsection is labeled “Sensitivity Analysis.” It also shows a flowchart as follows: At the top, an oval labeled “Start.” Below, a rectangular process box reads, “Initialize the parameters, including N as the number of iterations and W as the weight range.” A small rectangular box with “i equals 1,” indicating the initialization of an iteration counter. Next, a process box with icons of four respondents colored in different colors. The text reads: “Randomly generate the weight of experts in range W.” Below this, a process box reads, “Repeat each response as much as its weight.” Another process box states, “Run DEMATEL,” from which an arrow extends to the “Designing the Fuzzy DEMATEL Survey.” Next, a process box reads, “Determine the region of each factor.” A decision diamond asks, “Is i less than N question mark” with two arrows: If yes, an arrow points right to a small box, “i equals i plus 1,” which then loops back to the “Randomly Generate the Weight of Experts in Range W” box. If no, the flow continues down. Below the decision, a process box reads, “Calculate the probability as the change of region.” At the bottom, an oval labeled “End.” On the left side of the dashed box, there is an icon depicting a stack of graphs and charts connected by lines, representing data analysis or statistics. The process box labeled “Run DEMATEL” leads to the middle section. An arrow from the middle section leads to the second subsection labeled “Sensitivity Analysis.”

Research method. Source: Authors’ own work

Figure 1
A flowchart shows the research method involving identification of risk factors.The flowchart is divided into three main sections, each enclosed in a dashed box. The sections are interconnected with arrows indicating the process flow. The left section is labeled “Identification of Risk Factors.” It shows a flowchart with four sequence steps from top to bottom: Step 1: Identification of Key Risk Categories and Their Sub-Factors Through Literature Review and Code of Practices. This step has an icon of a yellow warning sign with an exclamation mark and a magnifying glass. Step 2: Contextualization and Validation of Risk Factors of E E O s Through Interviewing Competent Experts in Australia. This step has an icon of two people with a checkmark and speech bubbles. Step 3: Analysing the interviews for identification of new risk factors. This step has an icon of a person analyzing reports. Step 4: Designing a Questionnaire for Data Collection. This step has an icon of a clipboard with a pencil and paper. Arrows connect these boxes downward, indicating the sequence. An arrow from step 4 leads to the second section in the middle. The middle section is labeled “Designing the Fuzzy DEMATEL Survey.” It shows a flowchart with nine sequence steps from top to bottom: Step 1: Questionnaire distribution to the experts. Step 2: Generating the fuzzy initial direct-relation matrix. Step 3: Consistency Rate Calculation. Step 4: Aggregating the direct-relation matrices. Step 5: Normalizing the direct relation matrix. Step 6: Developing the total (direct–indirect) relation matrix. Step 7: Converting the values of the total relation matrix into crisp values. Step 8: Set threshold value and obtain the Impact Relations Map (I R M). Step 9: Generating Impact Relations Map (I R M). An arrow from the “Consistency Rate Calculation” step points rightwards to the next section. The right section has 2 subsections. Both sections are enclosed in a dashed box. The first subsection is labeled “Consistency Rate Calculation.” It shows a flowchart as follows: The flowchart flows vertically from top to bottom, with various shapes and icons connected by arrows. At the top, a rounded rectangle labeled “Start.” Below it, a rectangular box titled “Fuzzy Number Transformation into Vector Format.” This box contains a depiction of multiple stacked sheets or tables with fuzzy numbers transformed into vectors, showing matrices with numerical values such as 0.25, 0.5, 0.75, 1, et cetera. Next, a rectangular process box with a graphic showing overlapping circles containing colored icons representing respondents. The text inside reads, “Calculate the estimation of each respondent with the average of other respondents.” A decision diamond follows with the question, “If smaller collation is less than 0.3, question mark.” The diamond shows two arrows: If “Yes,” it leads to a rectangular process box to the right that says, “Remove the respondent with the lowest solution,” accompanied by an icon of a single respondent figure. The rectangular box leads back to the process box. If “No,” it continues downward. Below the decision box is a process box illustrating “Generate all possible split half,” showing the respondents split into three groups inside overlapping circles. Then, two process boxes follow sequentially: “Compute the correlation value of each split half.” “Compute the average adjusted split-half correlation.” Finally, the flowchart ends with another rounded rectangle labeled “Start,” indicating either a loop or the conclusion of the process. On the left side of the dashed box, there is a large circular icon with arrows in orange and blue, forming a loop around a checkmark. The second subsection is labeled “Sensitivity Analysis.” It also shows a flowchart as follows: At the top, an oval labeled “Start.” Below, a rectangular process box reads, “Initialize the parameters, including N as the number of iterations and W as the weight range.” A small rectangular box with “i equals 1,” indicating the initialization of an iteration counter. Next, a process box with icons of four respondents colored in different colors. The text reads: “Randomly generate the weight of experts in range W.” Below this, a process box reads, “Repeat each response as much as its weight.” Another process box states, “Run DEMATEL,” from which an arrow extends to the “Designing the Fuzzy DEMATEL Survey.” Next, a process box reads, “Determine the region of each factor.” A decision diamond asks, “Is i less than N question mark” with two arrows: If yes, an arrow points right to a small box, “i equals i plus 1,” which then loops back to the “Randomly Generate the Weight of Experts in Range W” box. If no, the flow continues down. Below the decision, a process box reads, “Calculate the probability as the change of region.” At the bottom, an oval labeled “End.” On the left side of the dashed box, there is an icon depicting a stack of graphs and charts connected by lines, representing data analysis or statistics. The process box labeled “Run DEMATEL” leads to the middle section. An arrow from the middle section leads to the second subsection labeled “Sensitivity Analysis.”

Research method. Source: Authors’ own work

Close modal
Figure 2
Four respondent icons with individual 3 cross 3 linguistic rating matrices representing direct impact relationships.The icons of respondents are arranged horizontally, each above a 3 cross 3 matrix labeled with factors F 1, F 2, and F 3 for both rows and columns. Each matrix contains entries representing relationship strengths between factors F 1, F 2, and F 3, with abbreviations as follows: V L: Very Low L: Low H: High V H: Very High Details for each table are as follows: The First Person's Matrix: F 1 row: Column F 1, blank. Column F 2, V L. Column F 3, L. F 2 row: Column F 1, L. Column F 2, blank. Column F 3, V H. F 3 row: Column F 1, L. Column F 2, V H. Column F 3, blank. The Second Person's Matrix: F 1 row: Column F 1, blank. Column F 2, V L. Column F 3, L. F 2 row: Column F 1, L. Column F 2, blank. Column F 3, V H. F 3 row: Column F 1, V L. Column F 2, H. Column F 3, blank. The Third Person's Matrix: F 1 row: Column F 1, blank. Column F 2, V L. Column F 3, V L. F 2 row: Column F 1, L. Column F 2, blank. Column F 3, V H. F 3 row: Column F 1, V L. Column F 2, V H. Column F 3, blank. The Fourth Person's Matrix: F 1 row: Column F 1, blank. Column F 2, V H. Column F 3, H. F 2 row: Column F 1, V H. Column F 2, blank. Column F 3, V L. F 3 row: Column F 1, V H. Column F 2, L. Column F 3, blank.

Linguistic ratings reflecting direct impact relationships. Source: Authors’ own work

Figure 2
Four respondent icons with individual 3 cross 3 linguistic rating matrices representing direct impact relationships.The icons of respondents are arranged horizontally, each above a 3 cross 3 matrix labeled with factors F 1, F 2, and F 3 for both rows and columns. Each matrix contains entries representing relationship strengths between factors F 1, F 2, and F 3, with abbreviations as follows: V L: Very Low L: Low H: High V H: Very High Details for each table are as follows: The First Person's Matrix: F 1 row: Column F 1, blank. Column F 2, V L. Column F 3, L. F 2 row: Column F 1, L. Column F 2, blank. Column F 3, V H. F 3 row: Column F 1, L. Column F 2, V H. Column F 3, blank. The Second Person's Matrix: F 1 row: Column F 1, blank. Column F 2, V L. Column F 3, L. F 2 row: Column F 1, L. Column F 2, blank. Column F 3, V H. F 3 row: Column F 1, V L. Column F 2, H. Column F 3, blank. The Third Person's Matrix: F 1 row: Column F 1, blank. Column F 2, V L. Column F 3, V L. F 2 row: Column F 1, L. Column F 2, blank. Column F 3, V H. F 3 row: Column F 1, V L. Column F 2, V H. Column F 3, blank. The Fourth Person's Matrix: F 1 row: Column F 1, blank. Column F 2, V H. Column F 3, H. F 2 row: Column F 1, V H. Column F 2, blank. Column F 3, V L. F 3 row: Column F 1, V H. Column F 2, L. Column F 3, blank.

Linguistic ratings reflecting direct impact relationships. Source: Authors’ own work

Close modal
Figure 3
A flowchart shows the consistency rate calculation process.The flowchart consists of multiple steps, represented by rectangular and diamond-shaped boxes connected by arrows, flowing mostly from left to right and then looping back. The process begins with an oval labeled “Start.” It leads to a process box labeled “Fuzzy Number Transformation into Vector Format,” which shows the transformation of fuzzy numbers into vector form. It contains a matrix with factors F 1, F 2, and F 3, leading to a fuzzy number scale. From top to bottom, the scale shows the labels V L, L, V H, L, and V H. This scale leads to a numeric vector matrix. The entries in the matrix are as follows: Row 1: 0, 0.25, 0.5. Row 2: 0.25, 0.5, 0.75. Row 3: 0.25, 0.5, 0.75. Row 4: 0.75, 1, 1. Row 5: 0.25, 0.5, 0.75. Row 6: 0.75, 1, 1. Next, a rectangular box labeled “Calculate the correlation of each respondent with the average of other respondents” is illustrated with four circles in a large circle containing colored icons of respondents. Each circle has two parts: the left part contains three respondents, and the right part contains one. A decision diamond labeled “If smaller collation less than 0.3” follows. It contains a similar split visual showing three respondents on the left and one respondent on the right. If yes, the flow moves upward to a rectangular box labeled “Remove the respondent with the lowest collation,” indicated by a single respondent icon, which is further connected to the box “Calculate the correlation of each respondent with the average of other respondents.” If no, the flow moves downward. The downward arrow leads to a rectangular box labeled “Generate all possible split half,” showing respondents divided into two groups within three circles inside a large circle. Each circle has two parts: the left and right parts contain two respondents. Next, a rectangular box labeled “Compute the correlation value of each split-half” leads to another box labeled “Compute the average adjusted split-half correlations.” The flow then loops back from the last step to the “Start” oval, indicating iteration or completion of the process.

The detailed of consistency rate calculation. Source: Authors’ own work

Figure 3
A flowchart shows the consistency rate calculation process.The flowchart consists of multiple steps, represented by rectangular and diamond-shaped boxes connected by arrows, flowing mostly from left to right and then looping back. The process begins with an oval labeled “Start.” It leads to a process box labeled “Fuzzy Number Transformation into Vector Format,” which shows the transformation of fuzzy numbers into vector form. It contains a matrix with factors F 1, F 2, and F 3, leading to a fuzzy number scale. From top to bottom, the scale shows the labels V L, L, V H, L, and V H. This scale leads to a numeric vector matrix. The entries in the matrix are as follows: Row 1: 0, 0.25, 0.5. Row 2: 0.25, 0.5, 0.75. Row 3: 0.25, 0.5, 0.75. Row 4: 0.75, 1, 1. Row 5: 0.25, 0.5, 0.75. Row 6: 0.75, 1, 1. Next, a rectangular box labeled “Calculate the correlation of each respondent with the average of other respondents” is illustrated with four circles in a large circle containing colored icons of respondents. Each circle has two parts: the left part contains three respondents, and the right part contains one. A decision diamond labeled “If smaller collation less than 0.3” follows. It contains a similar split visual showing three respondents on the left and one respondent on the right. If yes, the flow moves upward to a rectangular box labeled “Remove the respondent with the lowest collation,” indicated by a single respondent icon, which is further connected to the box “Calculate the correlation of each respondent with the average of other respondents.” If no, the flow moves downward. The downward arrow leads to a rectangular box labeled “Generate all possible split half,” showing respondents divided into two groups within three circles inside a large circle. Each circle has two parts: the left and right parts contain two respondents. Next, a rectangular box labeled “Compute the correlation value of each split-half” leads to another box labeled “Compute the average adjusted split-half correlations.” The flow then loops back from the last step to the “Start” oval, indicating iteration or completion of the process.

The detailed of consistency rate calculation. Source: Authors’ own work

Close modal
Figure 4
A quadrant chart categorizes factors into four quarters based on (D minus R) and (D plus R) values.The quadrant chart is divided into four labeled sections by two dashed lines. The vertical axis is labeled “(D minus R)” and represents causal versus result factors. The horizontal axis is labeled “(D plus R)” and represents low to high impact factors. The intersection of the axes is marked as “0.00” on the vertical axis and “Average” on the horizontal axis. Each quadrant is labeled and contains explanatory text. First Quarter (Top right): High impact factor: Causal factors: These factors have a high influence on others (high D minus R) and are highly affected by others (high D plus R). They are central, dominant factors in the system. They have a strong influence and are influenced strongly as well. Second Quarter (Top left): Low impact factor: Causal factors: These factors also have a high influence on others (high D minus R) but have a low total impact (low D plus R). They are less central to the system but are still “cause factors” because they influence other factors more than they are influenced. Third Quarter (Bottom left): Low impact factor: Result factors: These factors are both low in influence and low in total impact. They are peripheral factors that neither strongly influence others nor are strongly influenced by them. Fourth Quarter (Bottom right): High impact factor: Result factors: These factors have a low influence on others (low D minus R) but a high total impact (high D plus R). They are highly affected by other factors but do not influence the system much in return.

Impact-relation map (IRM) divided into four quarters for causal analysis. Source: Authors’ own work

Figure 4
A quadrant chart categorizes factors into four quarters based on (D minus R) and (D plus R) values.The quadrant chart is divided into four labeled sections by two dashed lines. The vertical axis is labeled “(D minus R)” and represents causal versus result factors. The horizontal axis is labeled “(D plus R)” and represents low to high impact factors. The intersection of the axes is marked as “0.00” on the vertical axis and “Average” on the horizontal axis. Each quadrant is labeled and contains explanatory text. First Quarter (Top right): High impact factor: Causal factors: These factors have a high influence on others (high D minus R) and are highly affected by others (high D plus R). They are central, dominant factors in the system. They have a strong influence and are influenced strongly as well. Second Quarter (Top left): Low impact factor: Causal factors: These factors also have a high influence on others (high D minus R) but have a low total impact (low D plus R). They are less central to the system but are still “cause factors” because they influence other factors more than they are influenced. Third Quarter (Bottom left): Low impact factor: Result factors: These factors are both low in influence and low in total impact. They are peripheral factors that neither strongly influence others nor are strongly influenced by them. Fourth Quarter (Bottom right): High impact factor: Result factors: These factors have a low influence on others (low D minus R) but a high total impact (high D plus R). They are highly affected by other factors but do not influence the system much in return.

Impact-relation map (IRM) divided into four quarters for causal analysis. Source: Authors’ own work

Close modal
Figure 5
A flowchart shows the detailed sensitivity analysis.The flowchart consists of multiple steps, represented by rectangular and diamond-shaped boxes connected by arrows, moving sequentially from left to right and looping back for iterations. The process begins with an oval labeled “Start.” It leads to a rectangular process box labeled “Initialize the parameters, including N as the number of iterations and W as the weight range.” Next, a rectangular box labeled “i equals 1” initializes the iteration index. This is followed by a process box labeled “Randomly generate the weight of experts in range W,” illustrated with icons of four respondents. Then, the flow proceeds to a rectangular box labeled “Repeat each response as much as its weight.” Next, the process continues to a box labeled “Run DEMATEL.” After that, a process box labeled “Determine the region of each factor” follows. The flow then reaches a decision diamond labeled “i less than N.” If yes, it loops to a box labeled “i equals i plus 1” and returns to the step for generating the weights of experts. If no, the flow continues downward, leading to a box labeled “Calculate the probability as the change of region.” Finally, the flow ends at an oval labeled “End.”

The detailed of sensitivity analysis. Source: Authors’ own work

Figure 5
A flowchart shows the detailed sensitivity analysis.The flowchart consists of multiple steps, represented by rectangular and diamond-shaped boxes connected by arrows, moving sequentially from left to right and looping back for iterations. The process begins with an oval labeled “Start.” It leads to a rectangular process box labeled “Initialize the parameters, including N as the number of iterations and W as the weight range.” Next, a rectangular box labeled “i equals 1” initializes the iteration index. This is followed by a process box labeled “Randomly generate the weight of experts in range W,” illustrated with icons of four respondents. Then, the flow proceeds to a rectangular box labeled “Repeat each response as much as its weight.” Next, the process continues to a box labeled “Run DEMATEL.” After that, a process box labeled “Determine the region of each factor” follows. The flow then reaches a decision diamond labeled “i less than N.” If yes, it loops to a box labeled “i equals i plus 1” and returns to the step for generating the weights of experts. If no, the flow continues downward, leading to a box labeled “Calculate the probability as the change of region.” Finally, the flow ends at an oval labeled “End.”

The detailed of sensitivity analysis. Source: Authors’ own work

Close modal
Figure 6
A set of 8 graphs shows impact-relation maps (I R M).(a) I R M of the main category of risk factors: The horizontal axis is labeled D plus R and ranges from 8.4 to 10 in increments of 0.2 units. The vertical axis is labeled D minus R and ranges from negative 0.2 to 0.2 in increments of 0.05 units. The graph shows the following data points: E N (8.54, 0.007), C (8.59, 0.06), G (8.78, 0.10), S (9.163, negative 0.16), E Q (9.48, negative 0.05), C S (9.82, 0.01), and W (9.56, 0.03). All points are enclosed in a shaded region, except for E N and C S. A dashed arrow from the point W points to point S, and a dashed arrow from point S points back to W. Two dashed arrows from the point C S, one points to W, and another points to E Q. A dashed arrow from the point E Q points to S. Another dashed arrow from the point C S points to S. A dashed arrow from the point S points to W. A dashed arrow from E Q points to W. A dashed arrow from point W points to E Q. A highlighted dashed arrow from the second quadrant points to C S. (b) I R M of government and regulatory association level (G): The horizontal axis is labeled D plus R and ranges from 6.4 to 7.2 in increments of 0.1 units. The vertical axis is labeled D minus R and ranges from negative 0.4 to 0.5 in increments of 0.1 units. The graph shows the following data points: G 1 (7.10, 0.46), G 2 (6.93, 0), G 3 (7.06, 0.07), G 4 (6.49, negative 0.17), G 5 (6.63, negative 0.027), and G 6 (6.69, negative 0.05). Bidirectional dashed arrows connect the point G 1 to G 4, G 5, G 6, G 2, and G 3. A dashed arrow from point G 3 points to G 1. A dashed arrow from the point G 3 points to G 2, and an arrow from G 2 points back to G 3. A dashed arrow from G 3 points to G 5. (c) I R M of commercial management level (C): The horizontal axis is labeled D plus R and ranges from 43.8 to 45.8 in increments of 0.2 units. The vertical axis is labeled D minus R and ranges from negative 0.25 to 0.25 in increments of 0.05 units. The graph shows the following data points: C 1 (44.03, 0.21), C 2 (45.13, 0.03), and C 3 (45.59, negative 0.23). A dashed arrow from point C 1 points to point C 3. A dashed arrow from point C 2 points to C 3. Another dashed arrow from point C 3 points back to C 2. (d) I R M of stakeholder safety management level (S): The horizontal axis is labeled D plus R and ranges from 5.5 to 7.5 in increments of 0.2 units. The vertical axis is labeled D minus R and ranges from negative 0.4 to 0.4 in increments of 0.1 units. The graph shows the following data points: S 1 (7.38, 0.08), S 2 (6.59, 0.079), S 3 (7.14, negative 0.14), S 4 (6.90, negative 0.30), S 5 (6.41, 0.37), S 6 (5.70, 0.14), S 7 (6.92, negative 0.17) and S 8 (6.91, negative 0.018). All points are enclosed in a shaded region, except for S 1, S 5, and S 6. A dashed arrow from S 3 points to S 1. A dashed arrow from S 8 points to S 1. A dashed arrow from S 7 points to S 1. A dashed arrow from S 3 points to S 7. A dashed arrow from S 7 points to S 4. Another arrow from S 3 points to S 4. Two arrows from S 8, one points to S 3, and the other points to S 4. Two dashed arrows from S 2 points to S 3 and S 1. A highlighted dashed arrow from S 1 points to the shaded region. (e) I R M of construction site management level (C S): The horizontal axis is labeled D plus R and ranges from 7.6 to 9.2 in increments of 0.2 units. The vertical axis is labeled D minus R and ranges from negative 0.3 to 0.3 in increments of 0.1 units. The graph shows the following data points: C S 1 (9.07, 0.05), C S 2 (8.16, 0.08), C S 3 (8.72, negative 0.14), C S 4 (8.59, negative 0.02), C S 5 (8.08, negative 0.03), C S 6 (7.69, 0.02), C S 7 (8.85, negative 0.04), C S 8 (8.53, negative 0.13), C S 9 (7.94, 0.27) and C S 10 (8.21, negative 0.006). All points are enclosed in a shaded region, except for C S 1, C S 6, and C S 9. A dashed arrow from C S 9 points to C S 1. A dashed arrow from C S 1 points to C S 5. A dashed arrow from C S 2 points to C S 3. A dashed arrow from C S 4 points to C S 8. A dashed arrow from C S 4 points to C S 7, and another arrow from C S 7 points back to C S 4. A dashed arrow from C S 3 points to C S 4. A dashed arrow from C S 7 points to C S 8, and another arrow from C S 8 points back to C S 7. A dashed arrow from C S 7 points to C S 3, and another arrow from C S 3 points back to C S 7. A dashed arrow from C S 3 points to C S 8, and another arrow from C S 8 points back to C S 3. A highlighted dashed arrow from the shaded region points to C S 1, and another from C S 1 points back to the shaded region. (f) I R M of workers and staff on construction site level (W): The horizontal axis is labeled D plus R and ranges from 7 to 11 in increments of 0.5 units. The vertical axis is labeled D minus R and ranges from negative 2 to 2 in increments of 0.5 units. The graph shows the following data points: W 1 (9.42, negative 0.153), W 2 (9.212, 0.354), W 3 (9.473, 0.26), W 4 (8.938, 0.301), W 5 (9.219, 0.385), W 6 (9.525, 0.153), W 7 (8.984, 0.332), W 8 (9.003, 0.385), W 9 (9.14, 0.037), W 10 (7.287, negative 0.227), W 11 (10.393, negative 1.926), W 12 (7.529, 0.111), and W 13 (9.467, 0.301). All points are enclosed in a shaded region, except for W 11. Two dashed arrows from W 5, one points to W 13 and the other points to W 3. Two dashed arrows from W 2, one points to W 3, and the other points to W 13. Two dashed arrows from C S 3, one points to W 2, and the other points to W 5. A dashed arrow from W 13 points to W 2. Dashed arrows from W 2, W 13, W 3, and W 6 point to W 9. A dashed arrow from W 6 points to W 3. Two dashed arrows, one from W 8 and the other from W 7, point to W 1. All points are enclosed in a pink-shaded region. A small yellow region enclosed the points W 2, W 3, W 4, W 5, W 7, W 8, and W 13. A blue shaded region encloses the points W 2, W 3, W 5, W 6, W 9, and W 13. A dashed arrow from the yellow shaded region points to W 6. A dashed arrow from the blue region points to W 1. A dashed arrow from the pink region points to W 11. A dashed curve loops the point W 11 itself. An inset of the shaded region with points and arrows is shown on the top right. (g) I R M of environment level (E N): The horizontal axis is labeled D plus R and ranges from 3.95 to 4.45 in increments of 0.10 units. The vertical axis is labeled D minus R and ranges from negative 0.7 to 0.7 in increments of 0.2 units. The graph shows the following data points: E N 1 (4.434, 0.66), E N 2 (4.14, negative 0.25), E N 3 (3.97, negative 0.206), E N 4 (4.204, 0.025), and E N 5 (4.09, negative 0.0214). Three bidirectional arrows connect E N 1 to E N 2, E N 3, E N 4, and E N 5. Two bidirectional arrows connect the point E N 4 to E N 5 and E N 2. Two bidirectional arrows connect E N 2 to E N 3. (h) I R M of equipment level (E Q): The horizontal axis is labeled D plus R and ranges from 9.4 to 10.4 in increments of 0.1 units. The vertical axis is labeled D minus R and ranges from negative 0.4 to 0.4 in increments of 0.1 units. The graph shows the following data points: E Q 1 (10.13, 0.30), E Q 2 (10.18, 0.3), E Q 3 (9.51, negative 0.103), E Q 4 (9.67, negative 0.185), E Q 5 (10.17, negative 0.074), E Q 6 (9.50, negative 0.16) and E Q 7 (9.87, negative 0.062). Dashed arrows from E Q 1 point to E Q 2, E Q 4, E Q 5, and E Q 7. Dashed arrows from E Q 2 point to E Q 1, E Q 4, E Q 5, E Q 6, and E Q 7. Dashed arrows from E Q 5 point to E Q 1, E Q 2, and E Q 7. A dashed arrow from E Q 7 points to E Q 5. Note: All numerical values are approximated.

Impact-relation maps (IRM) of main category of risk and sub-risk factors in EEOs. Source: Authors’ own work

Figure 6
A set of 8 graphs shows impact-relation maps (I R M).(a) I R M of the main category of risk factors: The horizontal axis is labeled D plus R and ranges from 8.4 to 10 in increments of 0.2 units. The vertical axis is labeled D minus R and ranges from negative 0.2 to 0.2 in increments of 0.05 units. The graph shows the following data points: E N (8.54, 0.007), C (8.59, 0.06), G (8.78, 0.10), S (9.163, negative 0.16), E Q (9.48, negative 0.05), C S (9.82, 0.01), and W (9.56, 0.03). All points are enclosed in a shaded region, except for E N and C S. A dashed arrow from the point W points to point S, and a dashed arrow from point S points back to W. Two dashed arrows from the point C S, one points to W, and another points to E Q. A dashed arrow from the point E Q points to S. Another dashed arrow from the point C S points to S. A dashed arrow from the point S points to W. A dashed arrow from E Q points to W. A dashed arrow from point W points to E Q. A highlighted dashed arrow from the second quadrant points to C S. (b) I R M of government and regulatory association level (G): The horizontal axis is labeled D plus R and ranges from 6.4 to 7.2 in increments of 0.1 units. The vertical axis is labeled D minus R and ranges from negative 0.4 to 0.5 in increments of 0.1 units. The graph shows the following data points: G 1 (7.10, 0.46), G 2 (6.93, 0), G 3 (7.06, 0.07), G 4 (6.49, negative 0.17), G 5 (6.63, negative 0.027), and G 6 (6.69, negative 0.05). Bidirectional dashed arrows connect the point G 1 to G 4, G 5, G 6, G 2, and G 3. A dashed arrow from point G 3 points to G 1. A dashed arrow from the point G 3 points to G 2, and an arrow from G 2 points back to G 3. A dashed arrow from G 3 points to G 5. (c) I R M of commercial management level (C): The horizontal axis is labeled D plus R and ranges from 43.8 to 45.8 in increments of 0.2 units. The vertical axis is labeled D minus R and ranges from negative 0.25 to 0.25 in increments of 0.05 units. The graph shows the following data points: C 1 (44.03, 0.21), C 2 (45.13, 0.03), and C 3 (45.59, negative 0.23). A dashed arrow from point C 1 points to point C 3. A dashed arrow from point C 2 points to C 3. Another dashed arrow from point C 3 points back to C 2. (d) I R M of stakeholder safety management level (S): The horizontal axis is labeled D plus R and ranges from 5.5 to 7.5 in increments of 0.2 units. The vertical axis is labeled D minus R and ranges from negative 0.4 to 0.4 in increments of 0.1 units. The graph shows the following data points: S 1 (7.38, 0.08), S 2 (6.59, 0.079), S 3 (7.14, negative 0.14), S 4 (6.90, negative 0.30), S 5 (6.41, 0.37), S 6 (5.70, 0.14), S 7 (6.92, negative 0.17) and S 8 (6.91, negative 0.018). All points are enclosed in a shaded region, except for S 1, S 5, and S 6. A dashed arrow from S 3 points to S 1. A dashed arrow from S 8 points to S 1. A dashed arrow from S 7 points to S 1. A dashed arrow from S 3 points to S 7. A dashed arrow from S 7 points to S 4. Another arrow from S 3 points to S 4. Two arrows from S 8, one points to S 3, and the other points to S 4. Two dashed arrows from S 2 points to S 3 and S 1. A highlighted dashed arrow from S 1 points to the shaded region. (e) I R M of construction site management level (C S): The horizontal axis is labeled D plus R and ranges from 7.6 to 9.2 in increments of 0.2 units. The vertical axis is labeled D minus R and ranges from negative 0.3 to 0.3 in increments of 0.1 units. The graph shows the following data points: C S 1 (9.07, 0.05), C S 2 (8.16, 0.08), C S 3 (8.72, negative 0.14), C S 4 (8.59, negative 0.02), C S 5 (8.08, negative 0.03), C S 6 (7.69, 0.02), C S 7 (8.85, negative 0.04), C S 8 (8.53, negative 0.13), C S 9 (7.94, 0.27) and C S 10 (8.21, negative 0.006). All points are enclosed in a shaded region, except for C S 1, C S 6, and C S 9. A dashed arrow from C S 9 points to C S 1. A dashed arrow from C S 1 points to C S 5. A dashed arrow from C S 2 points to C S 3. A dashed arrow from C S 4 points to C S 8. A dashed arrow from C S 4 points to C S 7, and another arrow from C S 7 points back to C S 4. A dashed arrow from C S 3 points to C S 4. A dashed arrow from C S 7 points to C S 8, and another arrow from C S 8 points back to C S 7. A dashed arrow from C S 7 points to C S 3, and another arrow from C S 3 points back to C S 7. A dashed arrow from C S 3 points to C S 8, and another arrow from C S 8 points back to C S 3. A highlighted dashed arrow from the shaded region points to C S 1, and another from C S 1 points back to the shaded region. (f) I R M of workers and staff on construction site level (W): The horizontal axis is labeled D plus R and ranges from 7 to 11 in increments of 0.5 units. The vertical axis is labeled D minus R and ranges from negative 2 to 2 in increments of 0.5 units. The graph shows the following data points: W 1 (9.42, negative 0.153), W 2 (9.212, 0.354), W 3 (9.473, 0.26), W 4 (8.938, 0.301), W 5 (9.219, 0.385), W 6 (9.525, 0.153), W 7 (8.984, 0.332), W 8 (9.003, 0.385), W 9 (9.14, 0.037), W 10 (7.287, negative 0.227), W 11 (10.393, negative 1.926), W 12 (7.529, 0.111), and W 13 (9.467, 0.301). All points are enclosed in a shaded region, except for W 11. Two dashed arrows from W 5, one points to W 13 and the other points to W 3. Two dashed arrows from W 2, one points to W 3, and the other points to W 13. Two dashed arrows from C S 3, one points to W 2, and the other points to W 5. A dashed arrow from W 13 points to W 2. Dashed arrows from W 2, W 13, W 3, and W 6 point to W 9. A dashed arrow from W 6 points to W 3. Two dashed arrows, one from W 8 and the other from W 7, point to W 1. All points are enclosed in a pink-shaded region. A small yellow region enclosed the points W 2, W 3, W 4, W 5, W 7, W 8, and W 13. A blue shaded region encloses the points W 2, W 3, W 5, W 6, W 9, and W 13. A dashed arrow from the yellow shaded region points to W 6. A dashed arrow from the blue region points to W 1. A dashed arrow from the pink region points to W 11. A dashed curve loops the point W 11 itself. An inset of the shaded region with points and arrows is shown on the top right. (g) I R M of environment level (E N): The horizontal axis is labeled D plus R and ranges from 3.95 to 4.45 in increments of 0.10 units. The vertical axis is labeled D minus R and ranges from negative 0.7 to 0.7 in increments of 0.2 units. The graph shows the following data points: E N 1 (4.434, 0.66), E N 2 (4.14, negative 0.25), E N 3 (3.97, negative 0.206), E N 4 (4.204, 0.025), and E N 5 (4.09, negative 0.0214). Three bidirectional arrows connect E N 1 to E N 2, E N 3, E N 4, and E N 5. Two bidirectional arrows connect the point E N 4 to E N 5 and E N 2. Two bidirectional arrows connect E N 2 to E N 3. (h) I R M of equipment level (E Q): The horizontal axis is labeled D plus R and ranges from 9.4 to 10.4 in increments of 0.1 units. The vertical axis is labeled D minus R and ranges from negative 0.4 to 0.4 in increments of 0.1 units. The graph shows the following data points: E Q 1 (10.13, 0.30), E Q 2 (10.18, 0.3), E Q 3 (9.51, negative 0.103), E Q 4 (9.67, negative 0.185), E Q 5 (10.17, negative 0.074), E Q 6 (9.50, negative 0.16) and E Q 7 (9.87, negative 0.062). Dashed arrows from E Q 1 point to E Q 2, E Q 4, E Q 5, and E Q 7. Dashed arrows from E Q 2 point to E Q 1, E Q 4, E Q 5, E Q 6, and E Q 7. Dashed arrows from E Q 5 point to E Q 1, E Q 2, and E Q 7. A dashed arrow from E Q 7 points to E Q 5. Note: All numerical values are approximated.

Impact-relation maps (IRM) of main category of risk and sub-risk factors in EEOs. Source: Authors’ own work

Close modal
Table 5

Risk factors contributing to accidents in earthmoving equipment operation on Australian construction sites were identified through a review of literature and interviews with experts

The main category of risk factors (Code)Sub-risk factors (code)ReferencesInterview
123456789101112131415161718
Government and regulatory association (G)Safety regulation (G1)           
Safety supervision (G2)             
Regulatory training requirements/standards (G3)            
Authorities’/regulators’ permit condition (G4)                 
Verification of competency (G5)               
Construction equipment registration (G6)                 
Commercial management (C)Client management (C1)               
Procurement management (C2)                
Budget (C3)                
Stakeholder safety management (S)Safety management plan of the principal contractor (S1)              
Incentive and disciplinary measures of principal contractors for safety management (S2)                 *
Accident investigation plan by principal contractor (S3)               
Safety management plan of subcontractor (S4)             
Safety plan of equipment designers (S5)            
Qualifications of manufacturers (S6)     
Safety training by contractors (S7)    
Equipment maintenance plans by contractors (S8)            
Construction site management (CS)Site supervision (CS1)         
Site isolation and warning region setting (CS2)          
Implementation of safety plan (CS3)                
Schedule Pressure (CS4)                
Traffic management plan (CS5)            
Requirements to submit Safe Work Methods (SWMs) (CS6)               
Coordination and planning of multiple operations (CS7)                *
Obstacles and congested site (CS8)                 
Utility-related problems (CS9)              
Change management (CS10)                  *
Workers and staff on construction site (W)Job stress of workers (W1)                
Workers’ knowledge/experience (W2)               
Lack of hazard/situational awareness of workers (W3)               
Supervisor’s safety inspection (W4)           
Supervisor’s safety commitment (W5)                *
Supervisor’s safety instruction (W6)                
Supervisor’s character (W7)                *
Operators’ character (W8)               *
Operators’ proficiency (W9)               
The physical and health quality of the Operator (W10)                   
Personal protective equipment (PPE) (W11)                
Operator’s employment source (W12)                 
Operation communication (W13)         
Environment (EN)Weather condition (EN1)             
Poor visibility (EN2)          
Site Layout (EN3)          
Ground condition (EN4)          
Soil condition (EN5)             
Equipment (EQ)Safety reliability of attachment of equipment (EQ1)        
Safety stability of main structural bodies of the equipment (EQ2)             
Ergonomic level of operator’s cab (EQ3)                 
Failure/disorder of the control system (e.g. hydraulic system, error in software) (EQ4)                
Task-related malfunction (EQ5)          
Operation aid (e.g. digital display) (EQ6)                  
Blindspot (EQ7)            
Table 1

Demographics of interviewees

Demographic variable of intervieweesNumber
GenderMale29
Female3
Work experience (years)≥5 and <105
≥10 and <209
≥20 and <3013
≥305
Job positionSite management (Safety manager = 15, Construction project manager = 2, Operational manager = 1, Project engineer = 1, Site supervisor = 1, Site engineer = 1, and Project manager = 2)23
Earthmoving equipment management (Plant trainer = 3, Earthmoving equipment production manager = 1, and Technical Director Resources = 1)5
Managerial board (Managing director = 1 and General manager = 2)3
Project compliance manager1
Highest qualificationDiploma9
Graduate certificate2
Bachelor’s degree9
Master’s degree12

Source(s): Authors’ own work

Table 2

Linguistic scales and corresponding fuzzy numbers

Linguistic scaleAbbreviationFuzzy number
No influenceN(0, 0, 0)
Very low influenceVL(0, 0.25, 0.5)
Low influenceL(0.25, 0.5, 0.75)
High influenceH(0.5, 0.75, 1)
Very high influenceVH(0.75, 1, 1)

Source(s): Authors’ own work

Table 3

Profile of experts responding to the FDEMATEL questionnaire without consistency rate

Demographic variable of experts responding to the FDEMATEL questionnaireNumber
GenderMale16
Female2
Work experience (years)≥5 and <104
≥10 and <204
≥20 and <307
≥303
Job positionSite management (Safety manager = 12, Site supervisor = 1, Site engineer = 1, and Project manager = 1)15
Earthmoving equipment management (Earthmoving equipment production manager = 1)1
Managerial board (General manager = 1)1
Safe work design strategist = 11
Highest qualificationDiploma4
Graduate Certificate1
Bachelor’s degree4
Master’s degree8
Doctorate degree1

Source(s): Authors’ own work

Table 4

Profile of selected experts after consistency rate calculation

ExpertsPositionGenderHighest qualificationWork experience
Expert 1Earthmoving equipment production managerMaleBachelor’s degree33
Expert 5Safety managerMaleBachelor’s degree25
Expert 7Project managerMaleMaster’s degree20
Expert 9Safe work design strategistFemaleDoctorate degree20
Expert 11Safety managerMalePost Graduate Certificate15
Expert 13Safety managerMaleDiploma12
Expert 15Site supervisorMaleMaster’s degree8
Expert 16Safety managerMaleMaster’s degree6
Expert 17Site engineerMaleMaster’s degree5
Expert 18Safety managerMaleDiploma5

Source(s): Authors’ own work

Table 6

The cause-and-effect analysis

The main category of risk factors (Code)Sub-risk factors (code)DRCE (D + R)CA (D-R)Located quarter in IRMRelation
Main categoryGovernment and regulatory association (G)4.4484.3418.7890.107Quarter 2Cause
Commercial management (C)4.3324.2668.5980.066Quarter 2Cause
Stakeholder safety management (S)4.5004.6679.167−0.167Quarter 4Effect
Construction site management (CS)4.9214.9109.8310.011Quarter 1Cause
Workers and Staff on Construction Site (W)4.7984.7699.5670.029Quarter 1Cause
Environment (EN)4.2764.2698.5450.007Quarter 2Cause
Equipment (EQ)4.7174.7709.487−0.053Quarter 4Effect
The main category of risk factors (Code)Sub-risk factors (code)DRCECALocated quarter in IRM derived from the findingsRelation
Government and regulatory association (G)Safety regulation (G1)3.7883.3237.1110.465Quarter 1Cause
Safety supervision (G2)3.4693.4696.938−0.001Quarter 1Effect
Regulatory training requirements/standards (G3)3.5653.4997.0640.066Quarter 1Cause
Authorities’/regulators’ permit condition (G4)3.1563.3386.494−0.182Quarter 3Effect
Verification of competency (G5)3.1763.4596.636−0.283Quarter 3Effect
Construction equipment registration (G6)3.3163.3816.697−0.065Quarter 3Effect
Commercial management (C)Client management (C1)22.12321.91444.0380.209Quarter 2Cause
Procurement management (C2)22.58422.55545.1390.029Quarter 1Cause
Budget (C3)22.68322.92145.604−0.238Quarter 4Effect
Stakeholder safety management (S)Safety management plan of the principal contractor (S1)3.73943.6547.3940.085Quarter 1Cause
Incentive and disciplinary measures of principal contractors for safety management (S2)3.33653.2596.5950.078Quarter 2Cause
Accident investigation plan by principal contractor (S3)3.49673.6497.146−0.152Quarter 4Effect
Safety management plan of subcontractor (S4)3.29903.6116.910−0.312Quarter 4Effect
Safety plan of equipment designers (S5)3.39273.0266.4190.366Quarter 2Cause
Qualifications of manufacturers (S6)2.92322.7865.7090.138Quarter 2Cause
Safety training by contractors (S7)3.37193.5546.926−0.182Quarter 4Effect
Equipment maintenance plans by contractors (S8)3.44923.4696.9185−0.020Quarter 4Effect
Construction site management (CS)Site supervision (CS1)4.5674.5169.0830.051Quarter 1Cause
Site isolation and warning region setting (CS2)4.1284.0448.1710.084Quarter 2Cause
Implementation of safety plan (CS3)4.2894.4378.726−0.148Quarter 4Effect
Schedule pressure (CS4)4.2844.3168.600−0.033Quarter 4Effect
Traffic management plan (CS5)4.0264.0638.090−0.037Quarter 3Effect
Requirements to submit safe work methods (SWMs) (CS6)3.8583.8417.6990.018Quarter 2Cause
Coordination and planning of multiple operations (CS7)4.4044.4568.861−0.052Quarter 4Effect
Obstacles and congested site (CS8)4.2004.3408.540−0.140Quarter 4Effect
Utility-related problems (CS9)4.1043.8387.9420.266Quarter 2Cause
Change management (CS10)4.1034.1128.215−0.009Quarter 3Effect
Workers and Staff on Construction Site (W)Job stress of workers (W1)4.6264.8049.430−0.178Quarter 4Effect
Workers’ knowledge/experience (W2)4.7824.4389.2200.345Quarter 1Cause
Lack of hazard awareness of workers (W3)4.8624.6199.4810.243Quarter 1Cause
Supervisor’s safety inspection (W4)4.6134.3358.9480.278Quarter 2Cause
Supervisor’s safety commitment (W5)4.8014.4279.2280.374Quarter 1Cause
Supervisor’s safety instruction (W6)4.8334.7079.5390.126Quarter 1Cause
Supervisor’s character (W7)4.6434.3438.9860.300Quarter 2Cause
Operators’ character (W8)4.6864.3299.0150.357Quarter 2Cause
Operators’ proficiency (W9)4.5804.5669.1460.014Quarter 1Cause
The physical and health quality of the Operator (W10)3.5233.7777.300−0.255Quarter 3Effect
Personal protective equipment (PPE) (W11)4.2116.18510.396−1.974Quarter 4Effect
Operator’s employment source (W12)3.8093.7247.5340.085Quarter 2Cause
Operation communication (W13)4.8794.5959.4740.285Quarter 1Cause
Environment (EN)Weather condition (EN1)2.5441.8894.4330.655Quarter 1Cause
Poor visibility (EN2)1.9512.1984.149−0.247Quarter 3Effect
Site Layout (EN3)1.8852.0953.980−0.211Quarter 3Effect
Ground condition (EN4)2.1082.0954.2030.013Quarter 1Cause
Soil condition (EN5)1.9422.1534.095−0.211Quarter 3Effect
Equipment (EQ)Safety reliability of attachment of equipment (EQ1)5.2214.92010.1410.301Quarter 1Cause
Safety stability of main structural bodies of the equipment (EQ2)5.2414.94210.1830.298Quarter 1Cause
Ergonomic level of operator’s cab (EQ3)4.7074.8109.517−0.103Quarter 3Effect
failure/disorder of the control system (e.g. hydraulic system, error in software) (EQ4)4.7454.9359.680−0.189Quarter 3Effect
Inappropriate application of equipment for tasks being performed/ task-related malfunction (EQ5)5.0535.12810.181−0.075Quarter 4Effect
Operation aid (e.g. digital display) (EQ6)4.6674.8369.503−0.169Quarter 3Effect
Blindspot (EQ7)4.9054.9689.873−0.063Quarter 4Effect

Source(s): Authors’ own work

Supplements

References

Abed
,
H.R.
,
Hatem
,
W.A.
and
Jasim
,
N.A.
(
2020
), “
Role of BIM technology in enhancing safety analysis of Iraqi oil projects
”,
Asian Journal of Civil Engineering
, Vol. 
21
No. 
4
, pp. 
695
-
706
, doi: .
Alashwal
,
A.
and
Moustafa
,
A.A.
(
2022
), “
Weather and suicide of construction workers in Australia
”,
Proceedings of World Building Congress: Building our future, IOP Conference Series: Earth and Environmental Science
, Vol. 
1101
No. 
3
, 032010, doi: .
Alshahrani
,
R.
,
Yenugula
,
M.
,
Algethami
,
H.
,
Alharbi
,
F.
,
Goswami
,
S.S.
,
Naveed
,
Q.N.
,
Lasisi
,
A.
,
Islam
,
S.
,
Khan
,
N.A.
and
Zahmatkesh
,
S.
(
2024
), “
Establishing the fuzzy integrated hybrid MCDM framework to identify the key barriers to implementing artificial intelligence-enabled sustainable cloud system in an IT industry
”,
Expert Systems with Applications
, Vol. 
238
, 121732, doi: .
Alshboul
,
O.
,
Shehadeh
,
A.
,
Tatari
,
O.
,
Almasabha
,
G.
and
Saleh
,
E.
(
2024
), “
Multiobjective and multivariable optimization for earthmoving equipment
”,
Journal of Facilities Management
, Vol. 
22
No. 
1
, pp. 
21
-
48
, doi: .
Apaydın
,
O.
and
Aladağ
,
Z.
(
2022
), “
Ranking the evaluation criteria of Hi-Fi audio systems and constricted information space: a novel method for determining the DEMATEL threshold value
”,
Applied Acoustics
, Vol. 
190
, 108584, doi: .
Bayramova
,
A.
,
Edwards
,
D.J.
,
Roberts
,
C.
and
Rillie
,
I.
(
2023
), “
Enhanced safety in complex socio-technical systems via safety-in-cohesion
”,
Safety Science
, Vol. 
164
, 106176, doi: .
Bayramova
,
A.
,
Edwards
,
D.J.
,
Roberts
,
C.
and
Rillie
,
I.
(
2024
), “
Uncovering the genome of leading indicators from lagging indicators and normative documents: a proof-of-concept study
”,
Journal of Safety Research
, Vol. 
91
, pp. 
230
-
244
, doi: .
Bellman
,
R.E.
and
Zadeh
,
L.A.
(
1970
), “
Decision-making in a fuzzy environment
”,
Management Science
, Vol. 
17
No. 
4
, pp. 
141
-
164
, doi: .
Biggs
,
H.C.
and
Biggs
,
S.E.
(
2013
), “
Interlocked projects in safety competency and safety effectiveness indicators in the construction sector
”,
Safety Science
, Vol. 
52
, pp. 
37
-
42
, doi: .
Biggs
,
S.E.
,
Banks
,
T.D.
,
Davey
,
J.D.
and
Freeman
,
J.E.
(
2013
), “
Safety leaders’ perceptions of safety culture in a large Australasian construction organisation
”,
Safety Science
, Vol. 
52
, pp. 
3
-
12
, doi: .
Bluff
,
E.
(
2019
), “
How SMEs respond to legal requirements to provide information, training, instruction and supervision to workers about work health and safety matters
”,
Safety Science
, Vol. 
116
, pp. 
45
-
57
, doi: .
Breslin
,
F.C.
,
Dollack
,
J.
,
Mahood
,
Q.
,
Maas
,
E.T.
,
Laberge
,
M.
and
Smith
,
P.M.
(
2019
), “
Are new workers at elevated risk for work injury? A systematic review
”,
Occupational and Environmental Medicine
, Vol. 
76
No. 
9
, pp.
694
-
701
, doi: .
Cheng
,
T.
and
Teizer
,
J.
(
2014
), “
Modeling tower crane operator visibility to minimize the risk of limited situational awareness
”,
Journal of Computing in Civil Engineering
, Vol. 
28
No. 
3
, 04014004, doi: .
Cheng
,
M.
,
Liu
,
L.
,
Cheng
,
X.
and
Tao
,
L.
(
2024
), “
Risk analysis of public-private partnership waste-to-energy incineration projects in China: a hybrid fuzzy DEMATEL-ISM approach
”,
Engineering Construction and Architectural Management
, Vol. 
31
No. 
11
, pp. 
4255
-
4280
, doi: .
Choi
,
M.
,
Ahn
,
S.
and
Seo
,
J.
(
2020
), “
VR-Based investigation of forklift operator situation awareness for preventing collision accidents
”,
Accident Analysis and Prevention
, Vol. 
136
, 105404, doi: .
Dashti
,
M.S.
,
RezaZadeh
,
M.
,
Khanzadi
,
M.
and
Taghaddos
,
H.
(
2021
), “
Integrated BIM-based simulation for automated time-space conflict management in construction projects
”,
Automation in Construction
, Vol. 
132
, 103957, doi: .
Du
,
Y.-W.
and
Li
,
X.-X.
(
2021
), “
Hierarchical DEMATEL method for complex systems
”,
Expert Systems with Applications
, Vol. 
167
, 113871, doi: .
Edwards
,
D.J.
and
Holt
,
G.D.
(
2008
), “
Health and safety issues relating to construction excavators and their attachments
”,
Engineering Construction and Architectural Management
, Vol. 
15
No. 
4
, pp. 
321
-
335
, doi: .
Edwards
,
D.J.
and
Holt
,
G.D.
(
2009
), “
New stability field tests for construction excavators
”,
Engineering Construction and Architectural Management
, Vol. 
16
No. 
4
, pp. 
337
-
352
, doi: .
Edwards
,
D.J.
and
Holt
,
G.D.
(
2010
), “
Case study analysis of risk from using excavators as cranes
”,
Automation in Construction
, Vol. 
19
No. 
2
, pp. 
127
-
133
, doi: .
Edwards
,
D.J.
and
Holt
,
G.D.
(
2011
), “
Mini-excavator safety: toward innovative stability testing, procurement, and manufacture
”,
Journal of Construction Engineering and Management
, Vol. 
137
No. 
12
, pp. 
1125
-
1133
, doi: .
Edwards
,
D.J.
and
Love
,
P.E.D.
(
2016
), “
A case study of machinery maintenance protocols and procedures within the UK utilities sector dedicated to MRS. June Edwards, a lady of great distinction who preserved the health and dignity of others for many years. A loving mother and grandmother, without whose help, this work and many achievements would not have been possible
”,
Accident Analysis and Prevention
, Vol. 
93
, pp. 
319
-
329
, doi: .
Edwards
,
D.J.
,
Holt
,
G.D.
and
Robinson
,
B.
(
2002
), “
An artificial intelligence approach for improving plant operator maintenance proficiency
”,
Journal of Quality in Maintenance Engineering
, Vol. 
8
No. 
3
, pp. 
239
-
252
, doi: .
Edwards
,
D.
,
Parn
,
E.A.
,
Sing
,
M.C.P.
and
Thwala
,
W.D.
(
2019
), “
Risk of excavators overturning: determining horizontal centrifugal force when slewing freely suspended loads
”,
Engineering Construction and Architectural Management
, Vol. 
26
No. 
3
, pp. 
479
-
498
, doi: .
Fang
,
Y.
and
Cho
,
Y.K.
(
2017
), “
Effectiveness analysis from a cognitive perspective for a real-time safety assistance system for Mobile crane lifting operations
”,
Journal of Construction Engineering and Management
, Vol. 
143
No. 
4
, 05016025, doi: .
Fang
,
W.
,
Ding
,
L.
,
Love
,
P.E.D.
,
Luo
,
H.
,
Li
,
H.
,
Peña-Mora
,
F.
,
Zhong
,
B.
and
Zhou
,
C.
(
2020
), “
Computer vision applications in construction safety assurance
”,
Automation in Construction
, Vol. 
110
, 103013, doi: .
Fatima
,
S.H.
,
Rothmore
,
P.
,
Giles
,
L.C.
and
Bi
,
P.
(
2023
), “
Impacts of hot climatic conditions on work, health, and safety in Australia: a case study of policies in practice in the construction industry
”,
Safety Science
, Vol. 
165
, 106197, doi: .
Fontela
,
E.
(
1976
), “The DEMATEL observer”, in
DEMATEL
.
Getuli
,
V.
,
Bruttini
,
A.
and
Rahimian
,
F.
(
2025
), “
Parametric design methodology for developing BIM object libraries in construction site modeling
”,
Automation in Construction
, Vol. 
170
, 105897, doi: .
Gibb
,
A.
,
Lingard
,
H.
,
Behm
,
M.
and
Cooke
,
T.
(
2014
), “
Construction accident causality: learning from different countries and differing consequences
”,
Construction Management and Economics
, Vol. 
32
No. 
5
, pp. 
446
-
459
, doi: .
Guo
,
B.H.W.
,
Zou
,
Y.
,
Fang
,
Y.
,
Goh
,
Y.M.
and
Zou
,
P.X.W.
(
2021
), “
Computer vision technologies for safety science and management in construction: a critical review and future research directions
”,
Safety Science
, Vol. 
135
, 105130, doi: .
Guo
,
X.
,
Yang
,
Z.
,
Sun
,
J.
and
Zhang
,
Y.
(
2024
), “
Impact pathways of emerging ITs to mitigate supply chain vulnerability: a novel DEMATEL-ISM approach based on grounded theory
”,
Expert Systems with Applications
, Vol. 
239
, 122398, doi: .
Gutierrez-Bucheli
,
L.
,
Goh
,
J.T.
,
Rashidi
,
A.
,
Maxwell
,
D.
,
Digby
,
R.
,
Fang
,
Y.
,
Pook
,
H.
and
Arashpour
,
M.
(
2024
), “
Adopting immersive technologies in construction training: determining educational decision-making criteria through a Delphi technique
”,
Smart and Sustainable Built Environment
, Vol. 
ahead-of-print
 
No. ahead-of-print
, doi: .
Hale
,
A.
and
Borys
,
D.
(
2013a
), “
Working to rule or working safely? Part 2: the management of safety rules and procedures
”,
Safety Science
, Vol. 
55
, pp. 
222
-
231
, doi: .
Hale
,
A.
and
Borys
,
D.
(
2013b
), “
Working to rule, or working safely? Part 1: a state of the art review
”,
Safety Science
, Vol. 
55
, pp. 
207
-
221
, doi: .
Harris
,
K.M.
,
Stankovic
,
A.
,
Thoolen
,
S.
,
Strangman
,
G.
,
Caldwell
,
B.
and
Robinson
,
S.K.
(
2024
), “
Team dynamics and collaborative problem-solving for lunar construction: lessons from complex construction scenarios on Earth
”,
Human Factors
, Vol. 
66
No. 
5
, pp. 
1616
-
1632
, doi: .
Hinze
,
J.W.
and
Teizer
,
J.
(
2011
), “
Visibility-related fatalities related to construction equipment
”,
Safety Science
, Vol. 
49
No. 
5
, pp. 
709
-
718
, doi: .
Hinze
,
J.
,
Huang
,
X.
and
Terry
,
L.
(
2005
), “
The nature of struck-by accidents
”,
Journal of Construction Engineering and Management
, Vol. 
131
No. 
2
, pp. 
262
-
268
, doi: .
Hinze
,
J.
,
Olbina
,
S.
,
Orozco
,
J.
and
Beaumont
,
K.
(
2017
), “
Earthmoving equipment fatalities in the construction industry
”,
Practice Periodical on Structural Design and Construction
, Vol. 
22
No. 
4
, 04017015, doi: .
Hollnagel
,
E.
and
Slater
,
D.
(
2018
), “
The functional RESONANCE analysis method and manual (Version 2)
”.
Hussain
,
R.
,
Zaidi
,
S.F.A.
,
Pedro
,
A.
,
Lee
,
H.
and
Park
,
C.
(
2024
), “
Exploring construction workers’ attention and awareness in diverse virtual hazard scenarios to prevent struck-by accidents
”,
Safety Science
, Vol. 
175
, 106526, doi: .
Ilbahar
,
E.
,
Karaşan
,
A.
,
Cebi
,
S.
and
Kahraman
,
C.
(
2018
), “
A novel approach to risk assessment for occupational health and safety using Pythagorean fuzzy AHP and fuzzy inference system
”,
Safety Science
, Vol. 
103
, pp. 
124
-
136
, doi: .
Jalil Al-Bayati
,
A.
,
Rener
,
A.T.
,
Listello
,
M.P.
and
Mohamed
,
M.
(
2023
), “
PPE non-compliance among construction workers: an assessment of contributing factors utilizing fuzzy theory
”,
Journal of Safety Research
, Vol. 
85
, pp. 
242
-
253
, doi: .
Johansen
,
K.W.
,
Nielsen
,
R.
,
Schultz
,
C.
and
Teizer
,
J.
(
2021
), “
Automated activity and progress analysis based on non-monotonic reasoning of construction operations
”,
Smart and Sustainable Built Environment
, Vol. 
10
No. 
3
, pp. 
457
-
486
, doi: .
Kazan
,
E.
and
Usmen
,
M.A.
(
2018
), “
Worker safety and injury severity analysis of earthmoving equipment accidents
”,
Journal of Safety Research
, Vol. 
65
, pp. 
73
-
81
, doi: .
Khan
,
N.
,
Ali
,
A.K.
,
Skibniewski
,
M.J.
,
Lee
,
D.Y.
and
Park
,
C.
(
2019
), “
Excavation safety modeling approach using BIM and VPL
”,
Advances in Civil Engineering
, Vol. 
2019
No. 
1
, 1515808, doi: .
Khorrami Shad
,
H.
,
Tak Wing Yiu
,
K.
,
Lovreglio
,
R.
and
Feng
,
Z.
(
2024
), “
State-of-the-art analysis of the integration of augmented reality with construction technologies to improve construction safety
”,
Smart and Sustainable Built Environment
, Vol. 
13
No. 
6
, pp. 
1434
-
1449
, doi: .
Kiani Mavi
,
N.
,
Brown
,
K.
,
Fulford
,
R.G.
and
Goh
,
M.
(
2024
), “
An MCDM analysis of critical success criteria for medium and large construction projects in Australia and New Zealand
”,
Engineering Construction and Architectural Management
, Vol. 
ahead-of-print
 
No. ahead-of-print
, doi: .
Kima
,
O.
,
Urlainis
,
A.
,
Wang
,
K.-C.
and
Shohet
,
I.M.
(
2024
), “
Safety climate in small and medium construction enterprises
”,
Smart and Sustainable Built Environment
, Vol. 
ahead-of-print
 
No. ahead-of-print
, doi: .
Kulinan
,
A.S.
,
Park
,
M.
,
Aung
,
P.P.W.
,
Cha
,
G.
and
Park
,
S.
(
2024
), “
Advancing construction site workforce safety monitoring through BIM and computer vision integration
”,
Automation in Construction
, Vol. 
158
, 105227, doi: .
Kumar
,
S.S.
and
Cheng
,
J.C.
(
2015
), “
A BIM-based automated site layout planning framework for congested construction sites
”,
Automation in Construction
, Vol. 
59
, pp. 
24
-
37
, doi: .
Lingard
,
H.
and
Pirzadeh
,
P.
(
2025
), “
Workplace health and safety performance at the client-contractor interface: measurement, management and behaviour
”,
Safety Science
, Vol. 
184
, 106753, doi: .
Lingard
,
H.
,
Blismas
,
N.
,
Cooke
,
T.
and
Cooper
,
H.
(
2009
), “
The model client framework: resources to help Australian government agencies to promote safe construction
”,
International Journal of Managing Projects in Business
, Vol. 
2
No. 
1
, pp. 
131
-
140
.
Lingard
,
H.
,
Cooke
,
T.
and
Gharaie
,
E.
(
2013a
), “
A case study analysis of fatal incidents involving excavators in the Australian construction industry
”,
Engineering Construction and Architectural Management
, Vol. 
20
No. 
5
, pp. 
488
-
504
, 17097846, doi: .
Lingard
,
H.
,
Cooke
,
T.
and
Gharaie
,
E.
(
2013b
), “
The how and why of plant-related fatalities in the Australian construction industry
”,
Engineering Construction and Architectural Management
, Vol. 
20
No. 
4
, pp. 
365
-
380
, doi: .
Lingard
,
H.
,
Oswald
,
D.
and
Le
,
T.
(
2019
), “
Embedding occupational health and safety in the procurement and management of infrastructure projects: institutional logics at play in the context of new public management
”,
Construction Management and Economics
, Vol. 
37
No. 
10
, pp. 
567
-
583
, doi: .
Lingard
,
H.
,
Cooke
,
T.
,
Zelic
,
G.
and
Harley
,
J.
(
2021
), “
A qualitative analysis of crane safety incident causation in the Australian construction industry
”,
Safety Science
, Vol. 
133
, 105028, doi: .
Loosemore
,
M.
and
Andonakis
,
N.
(
2007
), “
Barriers to implementing OHS reforms–the experiences of small subcontractors in the Australian construction industry
”,
International Journal of Project Management
, Vol. 
25
No. 
6
, pp. 
579
-
588
, doi: .
Luo
,
H.
,
Wang
,
M.
,
Wong
,
P.K.Y.
and
Cheng
,
J.C.P.
(
2020
), “
Full body pose estimation of construction equipment using computer vision and deep learning techniques
”,
Automation in Construction
, Vol. 
110
, 103016, doi: .
Mehmood
,
I.
,
Li
,
H.
,
Qarout
,
Y.
,
Umer
,
W.
,
Anwer
,
S.
,
Wu
,
H.
,
Hussain
,
M.
and
Antwi-Afari
,
M.F.
(
2023
), “
Deep learning-based construction equipment operators’ mental fatigue classification using wearable EEG sensor data
”,
Advanced Engineering Informatics
, Vol. 
56
, 101978, doi: .
Mehmood
,
I.
,
Li
,
H.
,
Umer
,
W.
,
Ma
,
J.
,
Shakeel
,
M.S.
,
Anwer
,
S.
,
Antwi-Afari
,
M.F.
,
Tariq
,
S.
and
Wu
,
H.
(
2024
), “
Non-invasive detection of mental fatigue in construction equipment operators through geometric measurements of facial features
”,
Journal of Safety Research
, Vol. 
89
, pp. 
234
-
250
, doi: .
Mohandes
,
S.R.
,
Sadeghi
,
H.
,
Fazeli
,
A.
,
Mahdiyar
,
A.
,
Hosseini
,
M.R.
,
Arashpour
,
M.
and
Zayed
,
T.
(
2022
), “
Causal analysis of accidents on construction sites: a hybrid fuzzy Delphi and DEMATEL approach
”,
Safety Science
, Vol. 
151
, 105730, doi: .
Moon
,
S.
and
Seo
,
J.
(
2017
), “
Virtual graphic representation of construction equipment for developing a 3D earthwork BIM
”,
Journal of Civil Engineering and Management
, Vol. 
23
No. 
8
, pp. 
977
-
984
, doi: .
Moshtaghian
,
F.
and
Noorzai
,
E.
(
2023
), “
Integration of risk management within the building information modeling (BIM) framework
”,
Engineering Construction and Architectural Management
, Vol. 
30
No. 
5
, pp. 
1951
-
1977
, doi: .
Nelumdeniya
,
A.U.
,
Perera
,
B.
and
Gimhani
,
K.
(
2023
), “
Usage of digital technology in improving the mental health of workers on construction sites
”,
Construction Innovation
, Vol. 
25
No. 
3
, pp. 
931
-
971
, doi: .
Newaz
,
M.T.
,
Davis
,
P.R.
,
Jefferies
,
M.
and
Pillay
,
M.
(
2019
), “
Validation of an agent-specific safety climate model for construction
”,
Engineering Construction and Architectural Management
, Vol. 
26
No. 
3
, pp. 
462
-
478
, doi: .
O'Neill
,
C.
,
Gopaldasani
,
V.
and
Coman
,
R.
(
2022
), “
Factors that influence the effective use of safe work method statements for high-risk construction work in Australia–A literature review
”,
Safety Science
, Vol. 
147
, 105628, doi: .
Ocampo
,
L.A.
,
Tan
,
T.A.G.
and
Sia
,
L.A.
(
2018
), “
Using fuzzy DEMATEL in modeling the causal relationships of the antecedents of organizational citizenship behavior (OCB) in the hospitality industry: a case study in the Philippines
”,
Journal of Hospitality and Tourism Management
, Vol. 
34
, pp. 
11
-
29
, doi: .
Office of Parliamentary Counsel
(
2018
),
Work Health and Safety Act 2011
,
Office of Parliamentary Counsel
,
Canberra
.
Oswald
,
D.
,
Lingard
,
H.
and
Zhang
,
R.P.
(
2022
), “
How transactional and transformational safety leadership behaviours are demonstrated within the construction industry
”,
Construction Management and Economics
, Vol. 
40
No. 
5
, pp. 
374
-
390
, doi: .
Rashidi
,
A.
,
Woon
,
G.L.
,
Dasandara
,
M.
,
Bazghaleh
,
M.
and
Pasbakhsh
,
P.
(
2024
), “
Smart personal protective equipment for intelligent construction safety monitoring
”,
Smart and Sustainable Built Environment
, Vol. 
14
No. 
3
, pp. 
835
-
858
, doi: .
Rasmussen
,
J.
(
1997
), “
Risk management in a dynamic society: a modelling problem
”,
Safety Science
, Vol. 
27
Nos
2-3
, pp. 
183
-
213
, doi: .
Ren
,
J.
,
Jenkinson
,
I.
,
Wang
,
J.
,
Xu
,
D.
and
Yang
,
J.
(
2008
), “
A methodology to model causal relationships on offshore safety assessment focusing on human and organizational factors
”,
Journal of Safety Research
, Vol. 
39
No. 
1
, pp. 
87
-
100
, doi: .
Riaz
,
Z.
,
Edwards
,
D.J.
and
Thorpe
,
A.
(
2006
), “
SightSafety: a hybrid information and communication technology system for reducing vehicle/pedestrian collisions
”,
Automation in Construction
, Vol. 
15
No. 
6
, pp. 
719
-
728
, doi: .
Riaz
,
Z.
,
Edwards
,
D.J.
,
Holt
,
G.D.
and
Thorpe
,
T.
(
2011
), “
Data flow analysis of plant and equipment health and safety management
”,
Journal of Engineering, Design and Technology
, Vol. 
9
No. 
2
, pp. 
178
-
203
, doi: .
Rostamnezhad
,
M.
,
Nasirzadeh
,
F.
,
Khanzadi
,
M.
,
Jarban
,
M.J.
and
Ghayoumian
,
M.
(
2020
), “
Modeling social sustainability in construction projects by integrating system dynamics and fuzzy‐DEMATEL method: a case study of highway project
”,
Engineering Construction and Architectural Management
, Vol. 
27
No. 
7
, pp. 
1595
-
1618
, doi: .
Sadeghi
,
H.
,
Zhang
,
X.
and
Mohandes
,
S.R.
(
2023
), “
Developing an ensemble risk analysis framework for improving the safety of tower crane operations under coupled Fuzzy-based environment
”,
Safety Science
, Vol. 
158
, 105957, doi: .
Safe Work Australia
(
2021
), “
Excavation work code of practice 2021
”,
available at:
 https://www.worksafe.qld.gov.au/__data/assets/pdf_file/0018/72630/excavation-work-cop-2021.pdf
Safe Work Australia
(
2023
), “
Interactive data
”,
available at:
 https://data.safeworkaustralia.gov.au/interactive-data/industry/construction
Safe Work Australia
(
2024a
), “
Managing the risks of plant in the workplace, code of practice
”,
available at:
 https://www.safeworkaustralia.gov.au/sites/default/files/2024-11/model_code_of_practice-managing_the_risks_of_plant_in_the_workplace-nov24.pdf
Safe Work Australia
(
2024b
), “
Model work health and safety regulations
”,
The Parliamentary Counsel’s Committee, available at:
 https://www.safeworkaustralia.gov.au/sites/default/files/2024-08/consolidated_model_whs_regulations_-1_september_2024.pdf
Shehadeh
,
A.
,
Alshboul
,
O.
,
Tatari
,
O.
,
Alzubaidi
,
M.A.
and
Salama
,
A.H.E.-S.
(
2022
), “
Selection of heavy machinery for earthwork activities: a multi-objective optimization approach using a genetic algorithm
”,
Alexandria Engineering Journal
, Vol. 
61
No. 
10
, pp. 
7555
-
7569
, doi: .
Shieh
,
J.I.
and
Wu
,
H.H.
(
2016
), “
Measures of consistency for DEMATEL method
”,
Communications in Statistics – Simulation and Computation
, Vol. 
45
No. 
3
, pp. 
781
-
790
, doi: .
Si
,
S.-L.
,
You
,
X.-Y.
,
Liu
,
H.-C.
and
Zhang
,
P.
(
2018
), “
DEMATEL technique: a systematic review of the state‐of‐the‐art literature on methodologies and applications
”,
Mathematical Problems in Engineering
, Vol. 
2018
No. 
1
, 3696457, doi: .
Soltanmohammadlou
,
N.
,
Hon
,
C.K.
and
Drogemuller
,
R.
(
2024a
), “
Applying systems thinking to research into risk factors influencing earthmoving equipment operation safety in construction sites
”,
Buildings
, Vol. 
14
No. 
7
, p.
1978
, doi: .
Soltanmohammadlou
,
N.
,
Hon
,
C.K.
,
Drogemuller
,
R.
,
Sheikhkhoshkar
,
M.
and
Rahimian
,
F.
(
2024b
), “
An advanced exploration of technological functionalities addressing risk factors in earthmoving equipment operation on construction sites: a systematic literature review
”,
Smart and Sustainable Built Environment
, Vol.
ahead-of-print
No.
ahead-of-print
, doi: .
Sony
,
M.
and
Naik
,
S.
(
2020
), “
Industry 4.0 integration with socio-technical systems theory: a systematic review and proposed theoretical model
”,
Technology in Society
, Vol. 
61
, 101248, doi: .
Suri
,
H.
(
2011
), “
Purposeful sampling in qualitative research synthesis
”,
Qualitative Research Journal
, Vol. 
11
No. 
2
, pp. 
63
-
75
, doi: .
Taher
,
A.
,
Vahdatikhaki
,
F.
and
Hammad
,
A.
(
2019
), “
Integrating earthwork ontology and safety regulations to enhance operations safety
”,
36th International Symposium on Automation and Robotics in Construction, ISARC
.
Taher
,
A.
,
Vahdatikhaki
,
F.
and
Hammad
,
A.
(
2022
), “
Formalizing knowledge representation in earthwork operations through development of domain ontology
”,
Engineering Construction and Architectural Management
, Vol. 
29
No. 
6
, pp. 
2382
-
2414
, doi: .
Tang
,
N.
,
Hu
,
H.
,
Xu
,
F.
and
Zhu
,
F.
(
2019
), “
Personalized safety instruction system for construction site based on internet technology
”,
Safety Science
, Vol. 
116
, pp. 
161
-
169
, doi: .
Tzeng
,
G.-H.
,
Chiang
,
C.-H.
and
Li
,
C.-W.
(
2007
), “
Evaluating intertwined effects in e-learning programs: a novel hybrid MCDM model based on factor analysis and DEMATEL
”,
Expert Systems with Applications
, Vol. 
32
No. 
4
, pp. 
1028
-
1044
, doi: .
Wang
,
M.
,
Deng
,
Y.
,
Won
,
J.
and
Cheng
,
J.C.
(
2019
), “
An integrated underground utility management and decision support based on BIM and GIS
”,
Automation in Construction
, Vol. 
107
, 102931, doi: .
Wen
,
L.
,
Kim
,
D.
,
Liu
,
M.
and
Lee
,
S.
(
2023
), “
3D excavator pose estimation using projection-based pose optimization for contact-driven hazard monitoring
”,
Journal of Computing in Civil Engineering
, Vol. 
37
No. 
1
, 04022048, doi: .
Winge
,
S.
,
Albrechtsen
,
E.
and
Arnesen
,
J.
(
2019
), “
A comparative analysis of safety management and safety performance in twelve construction projects
”,
Journal of Safety Research
, Vol. 
71
, pp. 
139
-
152
, doi: .
Woolley
,
M.
(
2020
),
Development of a Systems Thinking–based Incident Analysis Method for Construction
,
University of the Sunshine Coast
,
Queensland
.
Woolley
,
M.J.
,
Goode
,
N.
,
Read
,
G.J.
and
Salmon
,
P.M.
(
2018
), “
Moving beyond the organizational ceiling: do construction accident investigations align with systems thinking?
”,
Human Factors and Ergonomics in Manufacturing and Service Industries
, Vol. 
28
No. 
6
, pp. 
297
-
308
, doi: .
Wu
,
H.-H.
and
Tsai
,
Y.-N.
(
2011
), “
A DEMATEL method to evaluate the causal relations among the criteria in auto spare parts industry
”,
Applied Mathematics and Computation
, Vol. 
218
No. 
5
, pp. 
2334
-
2342
, doi: .
Wu
,
H.-H.
and
Tsai
,
Y.-N.
(
2012
), “
Using AHP to evaluate the criteria of auto spare parts industry
”,
Quality and Quantity
, Vol. 
46
No. 
1
, pp. 
359
-
364
, doi: .
Wu
,
H.
,
Zhong
,
W.
,
Zhong
,
B.
,
Li
,
H.
,
Guo
,
J.
and
Mehmood
,
I.
(
2025
), “
Barrier identification, analysis and solutions of blockchain adoption in construction: a fuzzy DEMATEL and TOE integrated method
”,
Engineering Construction and Architectural Management
, Vol. 
32
No. 
1
, pp. 
409
-
426
, doi: .
Xiang
,
J.
,
Bi
,
P.
,
Pisaniello
,
D.
,
Hansen
,
A.
and
Sullivan
,
T.
(
2014
), “
Association between high temperature and work-related injuries in Adelaide, South Australia, 2001-2010
”,
Occupational and Environmental Medicine
, Vol. 
71
No. 
4
, pp. 
246
-
252
, doi: .
Yu
,
R.
and
Ma
,
L.
(
2024
), “
Risk evaluation of mega infrastructure construction supply chain in engineering-procurement-construction projects: an integrated fuzzy AHP and fuzzy DEMATEL approach
”,
Engineering Construction and Architectural Management
, Vol. 
32
No. 
5
, pp. 
3217
-
3235
, doi: .
Zadeh
,
L.A.
(
1965
), “
Fuzzy sets
”,
Information and control
, Vol. 
8
No. 
3
, pp. 
338
-
353
, doi: .
Zadeh
,
L.A.
(
1975
), “
The concept of a linguistic variable and its application to approximate reasoning—I
”,
Information Sciences
, Vol. 
8
No. 
3
, pp. 
199
-
249
, doi: .
Zamani
,
V.
,
Banihashemi
,
S.Y.
and
Abbasi
,
A.
(
2020
), “
How can communication networks among excavator crew members in construction projects affect the relationship between safety climate and safety outcomes?
”,
Safety Science
, Vol. 
128
, 104737, doi: .
Zhang
,
X.
,
Zhang
,
W.
,
Jiang
,
L.
and
Zhao
,
T.
(
2020
), “
Identification of critical causes of tower-crane accidents through system thinking and case analysis
”,
Journal of Construction Engineering and Management
, Vol. 
146
No. 
7
, 04020071, doi: .
Zhao
,
J.
,
Cao
,
Y.
and
Xiang
,
Y.
(
2024
), “
Pose estimation method for construction machine based on improved AlphaPose model
”,
Engineering Construction and Architectural Management
, Vol. 
31
No. 
3
, pp. 
976
-
996
, doi: .
Zhou
,
W.
,
Zhao
,
T.S.
,
Liu
,
W.
and
Tang
,
J.J.
(
2018
), “
Tower crane safety on construction sites: a complex sociotechnical system perspective
”,
Safety Science
, Vol. 
109
, pp. 
95
-
108
, doi: .
Zhu
,
R.
,
Hu
,
X.
,
Wei
,
A.
,
Yang
,
W.
and
Ji
,
F.
(
2024
), “
Measuring safety performance of construction employees using data envelopment analysis: a case in Australia
”,
Journal of Safety Research