A scheduling method for determining the critical path in linear projects is presented, that takes into account maximum time and distance constraints in addition to the commonly used minimum time and distance constraints. The maximum constraints, though often present in the specifications of a project, are not considered during the planning procedure, since no method existed to enable scheduling with them. The proposed method builds on the concept of the maximum constraints and expands on the necessary background for their implementation into the schedule. The introduced critical path algorithm allows for grouping linear activities into four categories regarding their critical status and their ability to influence project duration. The method is applied to a low‐pressure pipeline construction project and the results are presented.
Article navigation
1 June 2004
Research Article|
June 01 2004
Critical path determination by incorporating minimum and maximum time and distance constraints into linear scheduling Available to Purchase
Alexandros Kallantzis;
Alexandros Kallantzis
Senior Researcher, Department of Construction Management and Engineering, Faculty of Civil Engineering, National Technical University of Athens, Athens, Greece
Search for other works by this author on:
Sergios Lambropoulos
Sergios Lambropoulos
Assistant Professor, Department of Construction Management and Engineering, Faculty of Civil Engineering, National Technical University of Athens, Athens, Greece
Search for other works by this author on:
Publisher: Emerald Publishing
Online ISSN: 1365-232X
Print ISSN: 0969-9988
© Emerald Group Publishing Limited
2004
Engineering, Construction and Architectural Management (2004) 11 (3): 211–222.
Citation
Kallantzis A, Lambropoulos S (2004), "Critical path determination by incorporating minimum and maximum time and distance constraints into linear scheduling". Engineering, Construction and Architectural Management, Vol. 11 No. 3 pp. 211–222, doi: https://doi.org/10.1108/09699980410535813
Download citation file:
Suggested Reading
Impact of construction materials on project time and cost in Kuwait
Engineering, Construction and Architectural Management (April,2004)
Mobile agent technology and application for online global logistic services
Industrial Management & Data Systems (February,2004)
Improving future air traffic punctuality: “pinch‐and‐pull” target windows
Aircraft Engineering and Aerospace Technology: An International Journal (July,2010)
Minimizing logistics risk through real‐time vehicle routing and mobile technologies: Research to date and future trends
International Journal of Physical Distribution & Logistics Management (October,2004)
Time‐triggered Ethernet based on IEEE 1588 clock synchronisation
Assembly Automation (September,2004)
Related Chapters
We Can Fix it – Corruption in the Construction Industry
The Handbook of Business and Corruption: Cross-Sectoral Experiences
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.