The present investigation utilizes a bespoke methodology to analyse and compare the productivity rates of contractors' planning engineers for concrete placing operations amongst three European construction industries, namely Germany, France and the UK. An analysis of variance (anova) was used to investigate differences between the productivity rates. Based on such rates, the analysis shows that German contractors achieve the most efficient levels of labour productivity for this particular operation, whilst amongst the sample surveyed, British contractors are less productive than French and German companies. Although leading British contractors can compete with the best on the continent, the least productive companies in the UK sample were inferior to the least productive in France and Germany. Using national all‐in rates for labour, actual (labour) costs for this concrete operation were calculated to be lowest in France despite French wage rates being marginally higher than in the UK. This was because of the superior labour output of French contractors. The apparent lower productivity of British firms sampled in the present research concurs with the findings of two other international studies, indicating that the methodology utilized can provide meaningful and accurate productivity information.
Article navigation
1 February 1998
Review Article|
February 01 1998
A comparative evaluation of concrete placing productivity rates amongst French, German and UK construction contractors Available to Purchase
D.G. PROVERBS;
D.G. PROVERBS
School of Engineering and the Built Environment, University of Wolverhampton, Wulfruna Street, Wolverhampton WV1 1SB, UK
Search for other works by this author on:
G.D. HOLT;
G.D. HOLT
School of Engineering and the Built Environment, University of Wolverhampton, Wulfruna Street, Wolverhampton WV1 1SB, UK
Search for other works by this author on:
P.O. OLOMOLAIYE
P.O. OLOMOLAIYE
School of Engineering and the Built Environment, University of Wolverhampton, Wulfruna Street, Wolverhampton WV1 1SB, UK
Search for other works by this author on:
Publisher: Emerald Publishing
Online ISSN: 1365-232X
Print ISSN: 0969-9988
© MCB UP Limited
1998
Engineering, Construction and Architectural Management (1998) 5 (2): 174–181.
Citation
PROVERBS D, HOLT G, OLOMOLAIYE P (1998), "A comparative evaluation of concrete placing productivity rates amongst French, German and UK construction contractors". Engineering, Construction and Architectural Management, Vol. 5 No. 2 pp. 174–181, doi: https://doi.org/10.1108/eb021072
Download citation file:
Suggested Reading
A comparative evaluation of reinforcement fixing productivity rates amongst French, German and UK construction contractors
Engineering, Construction and Architectural Management (April,1998)
On productivity in project organizations
International Journal of Managing Projects in Business (September,2009)
Quality follows quality: add quality to the business and quality will multiply the profits
The TQM Journal (August,2009)
Proposal of a new National Innovation Capacity index: cross-country comparison of MENA countries and comparative insights with Europe
Journal of Islamic Accounting and Business Research (December,2025)
A comparative assessment of performance and productivity of health centres in Seychelles
International Journal of Productivity and Performance Management (December,2007)
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.