At White City in west London, the Hammersmith and City line runs on a high-level brick arch viaduct that crosses over both Wood Lane and the eastbound Central line. As part of the White City development, a section of this viaduct was removed and replaced with a new twin-track highly skewed bridge. This comprised a half-through bridge formed from three principal steel girders with connecting cross-beams and concrete infill. The deck was built off line, then slid into position during a four-day possession of the Hammersmith and City line, requiring part of the existing viaduct to be demolished; the Central line below remained open throughout. The piled substructure was constructed within the constraints of the existing viaduct arches. The existing early 1930s steel bridge deck over Wood Lane was strengthened in advance to provide new bearing positions. During the possession it was truncated by 2 m and supported on new piers.
Article navigation
March 2008
Research Article|
March 01 2008
London Underground bridge slide at White City viaduct, UK Available to Purchase
A. Karbassi, PhD, CEng, FIStrucE;
A. Karbassi, PhD, CEng, FIStrucE
Divisional Director
Waterman Civils
London, UK
Search for other works by this author on:
P. Knight, MA, CEng, MICE;
P. Knight, MA, CEng, MICE
Associate Director
Waterman Civils
London, UK
Search for other works by this author on:
D. Sharrocks, MA, CEng, FICE
D. Sharrocks, MA, CEng, FICE
Director
London Bridge Associates and Engineering Manager
Costain, London, UK
Search for other works by this author on:
Publisher: Emerald Publishing
Received:
July 18 2007
Accepted:
December 11 2007
Online ISSN: 1751-7664
Print ISSN: 1478-4637
© 2008 Thomas Telford Ltd
2008
Proceedings of the Institution of Civil Engineers - Bridge Engineering (2008) 161 (1): 11–20.
Article history
Received:
July 18 2007
Accepted:
December 11 2007
Citation
Karbassi A, Knight P, Sharrocks D (2008), "London Underground bridge slide at White City viaduct, UK". Proceedings of the Institution of Civil Engineers - Bridge Engineering, Vol. 161 No. 1 pp. 11–20, doi: https://doi.org/10.1680/bren.2008.161.1.11
Download citation file:
341
Views
Suggested Reading
Temporary works for demolition of Earls Court Exhibition Centre in London, UK
Proceedings of the Institution of Civil Engineers - Civil Engineering (April,2020)
Construction engineering at The Acre, UK: how innovative props facilitated building reuse
Proceedings of the Institution of Civil Engineers - Civil Engineering (January,2023)
The design and construction of the new Mizen Head Footbridge, Ireland
Proceedings of the Institution of Civil Engineers - Bridge Engineering (April,2013)
Temporary support of five-storey building by column clamping
Proceedings of the Institution of Civil Engineers - Structures and Buildings (December,2015)
Some structural aspects of top-down demolition of concrete buildings
Proceedings of the Institution of Civil Engineers - Forensic Engineering (January,2018)
Related Chapters
A large scale demolition in a densely populated urban area – a case study
Bridge Management 5: Inspection, maintenance, assessment and repair: Proceedings of the 5th International Conference on Bridge Management, organized by the University of Surrey, 11–13 April 2005
REMOVAL OF GYPSUM PLASTER BY THE USE OF MICROWAVES
Challenges of Concrete Construction: Volume 5, Sustainable Concrete Construction: Proceedings of the International Conference held at the University of Dundee, Scotland, UK on 9–11 September 2002
TOTAL RECYCLING OPPORTUNITIES – TASTING THE TOPICS FOR THE CONFERENCE SESSION
Challenges of Concrete Construction: Volume 5, Sustainable Concrete Construction: Proceedings of the International Conference held at the University of Dundee, Scotland, UK on 9–11 September 2002
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.