The M4 Elevated Section in west London is a 1·9 km concrete viaduct structure providing a major arterial route into London. An intervention model bringing together structural assessment, corrosion and crack monitoring data plus current and future predicted condition has been developed in a three-dimensional (3D) visual platform to enable structural rehabilitation of the substructure cross-head beams to be prioritised and planned on the network over the 30 years of the M25 design build finance and operate contract for Connect Plus. An initial assessment of the cross-heads undertaken to identify residual strength discovered a deficiency in capacity compared with current standards. Further assessment, including 3D strut and tie, non-linear finite-element analysis and plastic analysis, was undertaken to confirm public safety with continued trafficking of the structure and to determine strengthening requirements. Additionally, extensive monitoring of the cross-heads, including crack surveys and remote monitoring techniques, has been implemented to provide early warning of deterioration to prioritise interventions. The long-term maintenance strategy includes strengthening, cathodic protection concrete preservation and concrete repair. This paper discusses the development of the 3D model, the prioritisation process, including deterioration modelling, and the advanced structural analysis used to formulate the strengthening and maintenance programme for these substructures.
Article navigation
September 2017
Research Article|
January 24 2017
Management of the M4 Elevated Section substructures
Chris Hendy, MA, CEng, FICE, FREng;
Chris Hendy, MA, CEng, FICE, FREng
Head of Bridge Engineering
Atkins, Epsom, UK
Search for other works by this author on:
Chris Brock, MEng(Oxon), CEng, MICE;
Chris Brock, MEng(Oxon), CEng, MICE
Group Engineer
Atkins, Epsom, UK
Search for other works by this author on:
Tony Nicholls, BEng(Hons), CEng, MICE
Tony Nicholls, BEng(Hons), CEng, MICE
Professional Head Structures
Connect Plus, London, UK (corresponding author: tony.nicholls@connectplusm25.co.uk)
Search for other works by this author on:
Publisher: Emerald Publishing
Received:
January 29 2016
Accepted:
August 12 2016
Online ISSN: 1751-7664
Print ISSN: 1478-4637
ICE Publishing: All rights reserved
2017
Proceedings of the Institution of Civil Engineers - Bridge Engineering (2017) 170 (3): 159–167.
Article history
Received:
January 29 2016
Accepted:
August 12 2016
Citation
Hendy C, Brock C, Nicholls T (2017), "Management of the M4 Elevated Section substructures". Proceedings of the Institution of Civil Engineers - Bridge Engineering, Vol. 170 No. 3 pp. 159–167, doi: https://doi.org/10.1680/jbren.16.00006
Download citation file:
Suggested Reading
A benchmarked framework for geometric digital twinning of slab and beam-and-slab bridges
Proceedings of the Institution of Civil Engineers - Smart Infrastructure and Construction (August,2020)
Infrastructure information management of bridges at local authorities in the UK
Infrastructure Asset Management (May,2018)
Management of structural monitoring data of bridges using BIM
Proceedings of the Institution of Civil Engineers - Bridge Engineering (November,2016)
Innovative digital design delivery for the Ordsall Chord in Manchester, UK
Proceedings of the Institution of Civil Engineers - Bridge Engineering (April,2018)
Qualitative study of IT-driven strategies for improving road and bridge performance
Proceedings of the Institution of Civil Engineers - Smart Infrastructure and Construction (May,2026)
Related Chapters
Conclusion
BIM in Principle and in Practice
Building and virtual information modelling in intelligent buildings
Intelligent Buildings: Design, management and operation
BIM: the sustainability context
Sustainable Infrastructure: Sustainable Buildings
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.