The 42 km of tunnels constructed using soft-ground pressure-balance tunnel-boring machines for London’s new Elizabeth line were completed over a 3 year period. A single lining design solution was developed for all tunnels using a fully gasketed, steel-fibre-reinforced, concrete segmental lining suitable for use in all potential ground conditions anticipated along the alignment. The £14·8 billion Crossrail project faced many challenges, including dealing with significant quantities of different excavated material while minimising the environmental impact from transportation and disposal, minimising settlement effects and dealing with multiple tunnel-boring machine launches and receptions. This paper addresses how the issues were tackled and comments on the tunnel-boring machine design and the approach taken for survey control. Outline figures are also provided for the tunnelling rates. Finally, some conclusions and recommendations are made based on the observations and lessons learnt during the project.
Article navigation
May 2017
Research Article|
May 01 2017
Crossrail project: machine-driven tunnels on the Elizabeth line, London
Mike King, BSc, CEng, MICE;
Mike King, BSc, CEng, MICE
Technical and Compliance Director - Tunnels
CH2M, London, UK
Search for other works by this author on:
Ivor Thomas, BEng, LLB, CEng, FICE;
Ivor Thomas, BEng, LLB, CEng, FICE
Tunnel Manager
BAM Nuttall, London, UK
Search for other works by this author on:
Andy Stenning, BSc, PhD, CPEng, MIEAust, MHKIE, MASCE
Andy Stenning, BSc, PhD, CPEng, MIEAust, MHKIE, MASCE
Technical Director
Atkins Ltd, London, UK
Search for other works by this author on:
Publisher: Emerald Publishing
Received:
July 11 2016
Accepted:
December 16 2016
Online ISSN: 1751-7672
Print ISSN: 0965-089X
ICE Publishing: All rights reserved
2017
Proceedings of the Institution of Civil Engineers - Civil Engineering (2017) 170 (5): 31–38.
Article history
Received:
July 11 2016
Accepted:
December 16 2016
Citation
King M, Thomas I, Stenning A (2017), "Crossrail project: machine-driven tunnels on the Elizabeth line, London". Proceedings of the Institution of Civil Engineers - Civil Engineering, Vol. 170 No. 5 pp. 31–38, doi: https://doi.org/10.1680/jcien.16.00028
Download citation file:
New and popular articles
Suggested Reading
Design and construction of Sai Ying Pun station, Hong Kong
Proceedings of the Institution of Civil Engineers - Civil Engineering (February,2016)
Lin Au culvert, Hong Kong: taming the torrent
Proceedings of the Institution of Civil Engineers - Civil Engineering (May,2007)
Innovative excavation and support techniques for deep large foundations in soft ground
Proceedings of the Institution of Civil Engineers - Civil Engineering (November,2018)
Negotiation of poor ground in an undersea tunnel
Proceedings of the Institution of Civil Engineers - Forensic Engineering (February,2014)
Mobilised strength components in brittle failure of rock
Geotechnique (April,2003)
Related Chapters
Moorgate Shaft Base Slab, design, detailing and construction
Crossrail Project: Infrastructure design and construction
Ground and rock fragmentation – drilling and blasting
Civil Excavations and Tunnelling: A practical guide
Earth movers, excavators and open-cut excavations
Civil Excavations and Tunnelling: A practical guide
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.