In this study, based on the Kaihua section of the G205 (China) national highway reconstruction project, the construction area of the K4+550–K4+940 section was chosen to conduct settlement control research on the high-fill roadbed of the karst section within the construction area. The viability of using clayey gravel and tunnel slag as roadbed fill was evaluated through laboratory soil tests. The construction technology of grouting was used to manage the substructure of the karst section. After installing prestress anchors on the top of the foundation, a ‘layered’ filling scheme was utilised to fill the tunnel slag and clayey gravel. The Flac3D simulation software was used to contrast the deformation curves of key nodes on unanchored and anchored roadbeds. The test results indicate that the California bearing ratio satisfies the requirements of the specification and that the uniaxial compression strength of the tunnel slag satisfies the requirements of the specification when the clayey gravel is near the optimal moisture content and dry density and when the compaction is controlled within 94%. The use of prestress anchors can strengthen the rock and soil layers of the foundation and reduce the plastic zone distribution. This paper provides a corresponding engineering experience for the treatment of high-fill roadbeds in karst areas.
Article navigation
April 2025
Research Article|
May 10 2024
Research on the control of high-fill roadbed with tunnel slag in karst sections Available to Purchase
Hongsheng Ge, MEng;
Hongsheng Ge, MEng
MSc student, School of Civil and Architecture Engineering, Xi’an Technological University, Xian, China
Search for other works by this author on:
Liping Liu, PhD
Liping Liu, PhD
Professor, School of Civil and Architecture Engineering, Xi’an Technological University, Xian, China (corresponding author: xatu_liuliping@163.com)
Search for other works by this author on:
Publisher: Emerald Publishing
Received:
June 01 2023
Accepted:
May 06 2024
Emerald Publishing Limited: All rights reserved
2025
Environmental Geotechnics (2025) 12 (3): 208–225.
Article history
Received:
June 01 2023
Accepted:
May 06 2024
Citation
Ge H, Liu L (2025), "Research on the control of high-fill roadbed with tunnel slag in karst sections". Environmental Geotechnics, Vol. 12 No. 3 pp. 208–225, doi: https://doi.org/10.1680/jenge.23.00058
Download citation file:
Suggested Reading
Gray relational analysis and SBOA-BP for predicting settlement intervals of high-speed railway subgrade
Railway Sciences (February,2025)
Analysis of toughness on notched specimens by volumetric method
World Journal of Engineering (October,2013)
Improved uplift capacity design for overhead line equipment in granular soils
Proceedings of the Institution of Civil Engineers - Geotechnical Engineering (September,2025)
An optimised method for determining the plastic zone around a shallow circular tunnel
Geotechnique Letters (May,2026)
Sustainable overhead line equipment foundations with optimised shape and backfilling
Proceedings of the Institution of Civil Engineers - Geotechnical Engineering (February,2026)
Related Chapters
Explosive compaction: design, implementation and effectiveness
Ground and Soil Improvement
A constitutive model for partially saturated soils
The Essence of Geotechnical Engineering: 60 years of Géotechnique
Ground improvement: the interaction of engineering science and experience-based technology
Ground and Soil Improvement
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.