A detailed borehole investigation has recently been undertaken for an extension to the Thames Water ring main in north London. Results of this were presented in a preconstruction geological model. This formed the basis for tunnel designers to assess ground conditions prior to construction and implement mitigation design and/or contingency plans in the event of adverse geological conditions being encountered. Previous sections of the ring main were constructed using open-faced tunnelling techniques. These allowed for inspection and continuous record of ground conditions at the tunnel face, enabling an identification of the geology and prediction of potentially adverse ground ahead. In facilitating such close geological supervision, tunnelling benefited from significant programme savings – in particular, a reduction of risk to the health and safety of underground personnel. In constructing the tunnel extension, a closed-face tunnel boring machine was opted for; this largely concealed the exposure of geology in situ during the excavation cycle. Apart from a limited number of tunnel face inspections, an indication of the geology was formed from observation and logging the spoil arising from the tunnelling machine, aided by an assessment of the performance of the machine itself in response to changes in geology over the alignment. These activities were necessary in validating the preconstruction geological model and in providing assurances to the on-site design and construction teams.
Article navigation
June 2010
Research Article|
June 01 2010
Using tunnel boring data to augment the geological model
T. G. Newman, MSc, DIC, EurGeol, FGS, CEng, MIMMM;
T. G. Newman, MSc, DIC, EurGeol, FGS, CEng, MIMMM
Principal Engineering Geologist
Thames Water Utilities Ltd, Ashford, Middlesex, UK
Search for other works by this author on:
L. F. V. Yuan, BEng;
L. F. V. Yuan, BEng
Project Construction Engineer
Thames Water Utilities Ltd, Rickmansworth, Hertfordshire, UK
Search for other works by this author on:
L. C. O'Keeffe, MSc, FGS
L. C. O'Keeffe, MSc, FGS
Geotechnical Engineer
Thames Water Utilities Ltd, Ashford, Middlesex, UK
Search for other works by this author on:
Publisher: Emerald Publishing
Revision Received:
July 28 2009
Accepted:
November 05 2009
Online ISSN: 1751-8563
Print ISSN: 1353-2618
© 2010 Thomas Telford Ltd
2010
Proceedings of the Institution of Civil Engineers - Geotechnical Engineering (2010) 163 (3): 157–166.
Article history
Revision Received:
July 28 2009
Accepted:
November 05 2009
Citation
Newman TG, Yuan LFV, O'Keeffe LC (2010), "Using tunnel boring data to augment the geological model". Proceedings of the Institution of Civil Engineers - Geotechnical Engineering, Vol. 163 No. 3 pp. 157–166, doi: https://doi.org/10.1680/geng.2010.163.3.157
Download citation file:
Suggested Reading
The engineering properties of glacial tills
Geotechnical Research (July,2018)
Rapid determination of saline soil in the Xinjiang region in China
Geotechnical Research (January,2021)
King's Cross underground station, London: geotechnical aspects
Proceedings of the Institution of Civil Engineers - Transport (November,2004)
Characteristics of clay deposits in Saga Plain, Japan
Proceedings of the Institution of Civil Engineers - Geotechnical Engineering (June,2017)
Large-diameter piles in chalk – part 1, ground investigation
Proceedings of the Institution of Civil Engineers - Geotechnical Engineering (September,2018)
Related Chapters
Geotechnical variation of London Clay across central London
Stiff Sedimentary Clays: Genesis and Engineering Behaviour: Géotechnique Symposium in Print 2007
Towards reliable and effective site investigations
Risk and Variability in Geotechnical Engineering
Environmentally enhanced crack propagation in a chemically degrading isotropic shale
Bio- and Chemo-Mechanical Processes in Geotechnical Engineering: Géotechnique Symposium in Print 2013
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.