This is the first of two papers on a wide pile group. The geology and a geotechnical model of the site are presented, along with the design of a single pile, analysis of a static loading test, and some dynamic tests. Response of the piled foundations comprising 399 bored piles supporting three 70-storey towers on a common mat was monitored. Records consist of results of a static loading test, dynamic tests of four piles, the development of load in 15 piles, and settlement of 40 points during construction and nine years following. At end of construction, the perimeter piles received more load from the towers than did the interior piles and the mat settled on average 90 mm. By the end of the monitoring period, due to the general subsidence, the average settlement of the mat had increased by 50 mm. Most of the settlement is considered to originate from the compression of the soil layers below the pile toe level. A subsequent paper will present the analysis and design of the wide pile group, and the numerical analysis of the static loading test on a single pile and of the wide pile group.
Article navigation
October 2024
Research Article|
October 31 2024
A nine-year case history of monitoring a wide pile group part I
Stephen Buttling, BSc(Eng), ACGI, PhD;
Stephen Buttling, BSc(Eng), ACGI, PhD
Principal, National Geotechnical Consultants, Brisbane, Australia (corresponding author: stephen.buttling@ngconsult.com.au)
Search for other works by this author on:
Bengt H. Fellenius, MSc, DrTech, PEng;
Bengt H. Fellenius, MSc, DrTech, PEng
Consulting Engineer, Sidney, Ontario, Canada
Search for other works by this author on:
Naruedol Pinijpol, BEng, MEIT
Naruedol Pinijpol, BEng, MEIT
Senior Project Manager, NGC Thailand, Bangkok, Thailand
Search for other works by this author on:
Publisher: Emerald Publishing
Received:
January 04 2023
Accepted:
January 23 2024
Online ISSN: 1751-8563
Print ISSN: 1353-2618
Emerald Publishing Limited: All rights reserved
2023
Proceedings of the Institution of Civil Engineers - Geotechnical Engineering (2024) 177 (5): 435–447.
Article history
Received:
January 04 2023
Accepted:
January 23 2024
Citation
Buttling S, Fellenius BH, Pinijpol N (2024), "A nine-year case history of monitoring a wide pile group part I". Proceedings of the Institution of Civil Engineers - Geotechnical Engineering, Vol. 177 No. 5 pp. 435–447, doi: https://doi.org/10.1680/jgeen.23.00001
Download citation file:
New and popular articles
Suggested Reading
Piled raft foundations: design and applications
Geotechnique (March,2001)
Innovative monitoring of the response of a heritage masonry building to nearby tunnelling in London Clay
Geotechnique (December,2020)
Response of full-scale piles to EPBM tunnelling in London Clay
Geotechnique (July,2017)
Measured short-term ground surface response to EPBM tunnelling in London Clay
Geotechnique (November,2016)
Measured short-term subsurface ground displacements from EPBM tunnelling in London Clay
Geotechnique (July,2017)
Related Chapters
Measured short-term subsurface ground displacements from EPBM tunnelling in London Clay
Tunnelling in the Urban Environment: Géotechnique Symposium in Print 2017
Response of full-scale piles to EPBM tunnelling in London Clay
Tunnelling in the Urban Environment: Géotechnique Symposium in Print 2017
Seasonal changes in pore water pressure in a grass-covered cut slope in London Clay
Stiff Sedimentary Clays: Genesis and Engineering Behaviour: Géotechnique Symposium in Print 2007
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.