This paper describes the monitoring of the construction of a deep underground waste storage bunker for the PROTOS energy-from-waste facility in Chester, UK. A key element of the construction process was a 12 m deep excavation in soft clays and peats which was supported by a complex ‘combi-wall’ cofferdam comprising alternate tube and sheet piles, a reinforced concrete (RC) capping beam and two levels of internal bracing. The permanent bunker RC structure was constructed within the excavation using a bottom-up approach. The primary aim of this monitoring programme was to assess the performance of the composite support system through measured cofferdam wall deflections, bracing member loads, and site and bunker water levels. An additional objective of the monitoring was to provide the site team with real-time feedback to inform the construction process. Interpretation of the monitored data allows for a quantitative assessment of the influence of various construction activities on the responses of the support system. The monitored behaviour shows that the high stiffness and embedment depth of the supporting structure, combined with careful control of groundwater levels, significantly reduced risks associated with deep excavation construction in challenging ground conditions.

Rapid population growth in dense urban environments means that exploitation of underground spaces is often the only sustainable solution for the delivery of new infrastructure. Driven steel cofferdams are one of the most popular earth-retaining solutions for underground construction. Understanding the performance of a cofferdam structure, and its interaction with the soil, is critical to ensure safe and efficient construction. Robust and reliable construction monitoring is highly desirable to (a) verify and refine empirical design approaches (Clough & O'Rourke, 1990; Long, 2001; Moormann, 2004) and (b) provide live feedback to site personnel to reduce construction risks and optimise site activities.

The monitored performance of diaphragm and secant pile retaining walls has been a popular topic in the geotechnical literature and dominates deep excavation case histories – for example, Ou et al. (1993), Finno et al. (2002), Hewitt et al. (2003), Finno & Roboski (2005), Liu et al. (2005), Liu et al. (2011), Ng et al. (2012), Tan & Wei (2012), Wu et al. (2013), Finno et al. (2015) and Cheng et al. (2021). Individual case histories are valuable for their site-specific construction challenges, such as the complex excavation work for the construction of the Massachusetts Institute of Technology campus (Orazalin et al., 2015) and deep excavations in the historical centre of Rome (Masini et al., 2021). These studies also offer opportunities to collate results across many sites to achieve new insights and update design methods – for example, Peck (1969), Mana & Clough (1981) and Wang et al. (2010). Although the use of sheet pile retaining walls has been shown to lead to larger maximum wall displacements compared to diaphragm and secant pile walls, reported case histories are relatively scant (Long, 2001; Moormann, 2004). While recent research has significantly advanced understanding, insights are specific to Chicago (Finno et al., 1988, 1989, 2019; Finno & Roboski, 2005) and Gothenburg soft clays (Johansson & Sandeman, 2014; Langford et al., 2021; Tornborg et al., 2021).

Modern cofferdam installation techniques have also led to an increase in the use of ‘combi-wall’ cofferdam solutions, involving sheet piles interspersed with stiffer king (often tubular) piles, to increase lateral stiffness and bearing capacity. High-quality field data for this support system are much less common; for example, 16 of the 296 case studies reported in Long (2001) related to a combi-wall design, and only one involved a tube and sheet pile combination. There is also a general lack of reported case histories specific to the UK, which have been limited to diaphragm and secant pile walls in London Clay – for example, St John et al. (1992), Carder (1995) and Fernie & Sucking (1996). The literature points to a distinct lack of observations on the performance of combi-wall systems in UK soils.

This research gap is addressed in the current paper by describing the monitoring of a 12 m deep excavation supported using a combi-wall solution in soft clays and bands of organic peats in Chester, UK. The support structure was instrumented for the measurement of cofferdam wall deflections, bracing member forces, and site and excavation groundwater levels. Novel aspects of this work include: (a) new monitoring data for an unusual combi-wall support system in UK soft soils; (b) new insights into the effects of vibratory piling within the excavation on lateral wall displacements and support structure loads; and (c) new guidance on end fixity factors for temperature effects on prop loads.

The construction works described in this paper form part of the PROTOS energy-from-waste project in Chester, UK. The facility is designed to process over 400 000 t of non-recyclable waste per annum to produce up to 49 MW of electrical power. The proposed site is situated on marshland, close to the Manchester ship canal and the River Mersey, as shown in Fig. 1. A key aspect of the project involved the construction of a 40 m long, 18 m wide underground waste storage bunker. Construction of the underground bunker section began with a 12 m deep excavation in May 2021 and was completed in March 2022 by Ward and Burke Construction Ltd.

Fig. 1.

PROTOS energy-from-waste facility location in Chester, UK. Site boundary shown in black. A full-colour version of this figure can be found on the ICE Virtual Library (www.icevirtuallibrary.com)

Fig. 1.

PROTOS energy-from-waste facility location in Chester, UK. Site boundary shown in black. A full-colour version of this figure can be found on the ICE Virtual Library (www.icevirtuallibrary.com)

Close modal

The available site investigation included 13 cone penetration tests (CPTs), one of which was a seismic CPT (SCPT), geophysical testing, one borehole, cross-hole seismic testing and laboratory elemental testing. The CPTs and borehole were located around the perimeter of the bunker excavation. The CPTs were performed with a 17·9 t track truck mounted CPT unit (UK20) equipped with a 17·5 t capacity hydraulic ram.

The site investigation results and the inferred stratigraphy are shown in Fig. 2. A 1 m thick layer of made ground (MG) overlies tidal flat deposits (TF), which extend to 12 m below ground level (BGL). The TF deposits are predominantly very low-strength silty clay with two bands of low-strength fibrous peat (P) at 1·0–1·8 m and 9·6–10·3 m BGL. Below ∼12 m, there is a ∼7 m thick layer of glacial outwash (GO) deposits, which consist of medium dense sands with some gravels. Beneath the outwash deposits lies glacial till (GT) consisting of a 4 m thick layer of stiff, sandy clay (C) with localised silt bands, followed by dense, silty, fine sand containing bands of sandy clay.

Fig. 2.

Measured and inferred soil properties from the CPTs, SCPT and laboratory testing performed around the bunker excavation at PROTOS together with the best estimate of the soil stratigraphy. Grey lines indicate individual CPTs whereas black lines denote the mean of all CPTs (MG, made ground; TF, tidal flat deposits; P, peat; GO, glacial outwash; C, clay; GT, glacial till)

Fig. 2.

Measured and inferred soil properties from the CPTs, SCPT and laboratory testing performed around the bunker excavation at PROTOS together with the best estimate of the soil stratigraphy. Grey lines indicate individual CPTs whereas black lines denote the mean of all CPTs (MG, made ground; TF, tidal flat deposits; P, peat; GO, glacial outwash; C, clay; GT, glacial till)

Close modal

The measured pore water pressure, u, closely matches the estimated hydrostatic pore pressure profile, particularly in the coarse-grained soils. From 0–10 m BGL, measurements exceed the hydrostatic calculation, indicating the presence of normally to lightly overconsolidated clays. In contrast, measurements between 20 and 25 m BGL are indicative of moderately to highly overconsolidated materials.

The undrained shear strength, su, was determined using the relationship

1

where Nkt is the empirical cone factor. A value of Nkt = 20 was determined by fitting results from 14 unconsolidated, undrained (UU) triaxial compression tests. This value is in good agreement with those calibrated for other UK soft soils in Highbridge (Nkt = 19) (Royston, 2018) and in Hull (Nkt = 20) (Allievi et al., 2018). The internal angle of friction of the soil, ϕ′, was calculated using the empirical relationship in Kulhawy & Mayne (1990).

From the SCPT, the measured shear wave velocity, Vs, is compared to that inferred from the standard CPT measurements using the method in Robertson (2009), which estimates Vs as a function of qt and the soil behaviour type index, Ic. The measured data are also plotted using a three-interval linear regression (LR) model. The small-strain shear modulus is calculated according to

2

where ρ is the soil density.

Results from a series of laboratory density tests are compared to a depth profile of density inferred from the CPT data using the method in Robertson (2010). The index data are plotted on a combined linear–log scale to highlight the considerable variability observed in the TF layer, which is indicative of the presence of bands of organic peat. Density and index tests performed on samples taken from the lower clay layer suggest a higher degree of uniformity, with density and plasticity remaining approximately constant.

The site water level was measured to vary between 0 and 0·75 m BGL using four piezometers installed to a depth of 15 m; this was likely to be due to the proximity of the excavation to the River Mersey estuary.

The construction timeline is broken into 17 different construction stages, as summarised in Table 1; schematic illustrations of four of the key stages during construction are shown using sections through the bunker in Fig. 3. Prior to cofferdam installation, precast concrete piles were driven around the bunker area, to act as foundations for adjacent RC building slabs. A driven steel temporary works cofferdam was chosen for excavation support instead of in situ concrete owing to concerns over potential losses of cement fines in the weak clay and peat layers. To minimise ground movements, a combi-wall, comprising alternate tube and sheet piles, was used. The piles were driven to a depth of 21 m into the GT clay layer to minimise seepage into the excavation, with AZ28 sheet pile pairs subsequently driven between each tube (stage 2). The tube piles were then internally augered to 6·3 m BGL and filled with concrete to prevent local buckling at frame level 2, as shown in Fig. 3(a) (stage 3).

Table 1.

Summary of construction sequence

Construction worksStageActivityStart dateEnd dateDuration: days
Bunker excavation1Central frame assembly11 May 202118 May 20217
2Cofferdam installation18 May 20219 June 202122
3Excavate tube piles and concrete14 June 202117 June 20213
4Initial excavation below frame17 June 202120 June 20213
5Capping beam construction18 June 202109 Aug. 202152
6Dewatering well installation9 Aug. 202123 Aug. 202114
7Top prop installation15 Aug. 202131 Aug. 202116
8Excavation phase 11 Sept. 202110 Sept. 20219
9Central frame positioning10 Sept. 202121 Sept. 202111
10Excavation phase 221 Sept. 202129 Sept. 20218
Bunker piling11Piling bunker foundation slab8 Oct. 20212 Nov. 202125
Bunker construction12Bunker base construction2 Nov. 202125 Nov. 202123
13Central frame removal29 Nov. 20216 Dec. 20217
14Bunker wall pour 1 construction6 Dec. 202120 Dec. 202114
15Bunker wall pour 2 construction6 Jan. 202224 Jan. 202218
16Top prop removal31 Jan. 20223 Feb. 20224
17Bunker wall pour 3 construction3 Feb. 202225 Feb. 202222
  Underground waste bunker construction11 May 202125 Feb. 2022290
Fig. 3.

Typical section through excavation wall at key stages of the construction sequence: (a) stage 3; (b) stage 10; (c) stage 11; (d) stage 17

Fig. 3.

Typical section through excavation wall at key stages of the construction sequence: (a) stage 3; (b) stage 10; (c) stage 11; (d) stage 17

Close modal

A 1·2 m thick RC capping beam was constructed around the perimeter of the cofferdam (stage 5), connected to the cofferdam using UC members partially cast into each tube. The cofferdam was supported by two sets of internal bracing at the levels shown in Fig. 3(b); a plan view of the top level 1 bracing (0·6 m BGL) and lower level 2 bracing (5·75 m BGL) is shown in Figs 4(a) and 4(b), respectively. Table 2 presents key properties of each structural member of the cofferdam and support structures.

Fig. 4.

Schematic illustration of the plan view of the bracing arrangement and member labels for (a) level 1 (top) and (b) level 2 (lower)

Fig. 4.

Schematic illustration of the plan view of the bracing arrangement and member labels for (a) level 1 (top) and (b) level 2 (lower)

Close modal
Table 2.

Member properties for steel excavation components

Member typeLabelSection geometryLength: mCross-sectional area, A: cm2Elastic modulus, Z: cm3
Perimeter walerW1Double 914/419/343 UB15·8487427 452
W2Double 914/419/343 UB12·23, 2·50*87427 452
W3Double 914/419/343 UB18·3687427 452
Corner braceCCB1Double 914/419/343 UB6·6787427 452
TCB1Double 914/419/343 UB6·9087427 452
Central tubeP1Tube: OD = 1425 mm, t = 22 mm19·0297033 495
P2Tube: OD = 1220 mm, t = 20 mm19·0275422 255
TP1Tube: OD = 914 mm, t = 20 mm19·9456212 286
CofferdamTube: OD = 1220 mm, t = 22 mm, AZ28 sheet pile pairs21·009513

Note: OD denotes external diameter.

*

L-shaped waler, length of each section provided.

Combined tube and sheet pile Z.

Dewatering was carried out using internal wells, installed to a depth of 25 m BGL (stage 6), after which excavation commenced and the upper level 1 bracing was installed (stage 7). Excavation was paused to install the lower level 2 bracing frame at 5·75 m BGL (stage 9) before the second and final excavation phase (to a depth of 12 m BGL), was completed (stage 10). The formation depth ensured that the RC bunker base was founded on the GO silty sand deposits.

Construction of the 2 m thick RC base began by installing 156 13 m long, 350 mm dia. steel tubal piles (stage 11), driven vertically from formation depth over the plan area of the excavation (see Fig. 3(c)). The level 2 bracing structure was subsequently removed (stage 12/13) before the bottom-up (BU) construction of the 1·5 m thick RC bunker walls using a one-sided hydraulic climbing formwork structure. Each wall pour had a height of 3 m, with three wall pours required to complete the underground section of the bunker. The level 1 bracing was removed following the second wall pour.

Photographs of the excavation at six different construction stages are presented in Fig. 5.

Fig. 5.

Photographs of the excavation and bunker structure during construction: (a) stage 2; (b) stage 8; (c) stage 10; (d) stage 11; (e) stage 12; (f) stage 17

Fig. 5.

Photographs of the excavation and bunker structure during construction: (a) stage 2; (b) stage 8; (c) stage 10; (d) stage 11; (e) stage 12; (f) stage 17

Close modal

The adopted instrumentation set-up for the excavation and bunker construction processes are shown in Fig. 6 and are summarised in Table 3 along with their notation. The information obtained included cofferdam pile deflections, prop member axial loads and bending moments, and water level monitoring data. Video monitoring was undertaken using time-lapse cameras positioned around the site and drones, operating once a week. All data were displayed in real time on a bespoke online platform, accessible to site personnel by way of tablets. The monitored data were continuously compared to trigger early warning and work stoppage thresholds determined from the excavation design calculations. The performance of the support system was evaluated through comparisons to the excavation design and to published empirical guidelines and limits.

Fig. 6.

Plan layout of instrumentation used during excavation, taken through level 2 bracing

Fig. 6.

Plan layout of instrumentation used during excavation, taken through level 2 bracing

Close modal
Table 3.

Bunker instrumentation summary

MeasurementSensor typeQuantityNotation
Horizontal wall deflectionsPortable inclinometer4IC
Prop axial loads and bending momentsWeldable vibrating wire (VW) strain gauge8GW
Water levels – inside and outside of bunkerPiezometer4P

The lateral deflection of the cofferdam was monitored using a portable micro-electromechanical system inclinometer, in casings installed on four of the tube piles (IC1–IC4) as shown in Fig. 6. Each 15 m long casing was installed in a bespoke void formed by stitch welding a 100 mm square hollow section length with a tapered base to the tube piles before installation. Each casing was held within the void using a single size 1 mm filter sand. Measurements were taken in an axis both parallel and perpendicular to the cofferdam wall, at 0·5 m intervals starting from the bottom of the casing.

Only the loads in the level 2 bracing were monitored, as this level was considered the priority due to the more significant design loading. To obtain the axial loads and bending moments in the level 2 frame structure, two vibrating wire (VW) strain gauges were tack welded on opposite sides of each of the four instrumented members, as shown in Fig. 6. Measurements were transmitted to a central gateway located at the site office by wireless nodes in the excavation, at a period of 5 min. The average axial prop load, F, and bending moment, M, were calculated as

3
4

where Z, E and A are the elastic modulus, Young's modulus (taken as 210 GPa for steel) and cross-sectional area of the member considered, respectively, and μεA and μεB denote the microstrain measurement on either side of a given member.

Two inner piezometers (PI,1, PI,2) and two outer piezometers (PO,U, PO,L) were installed to monitor internal and external bunker water levels, respectively. A section showing the installation level of each of the monitoring wells is shown in Fig. 7. The external boreholes were positioned to determine whether groundwater was being drawn into the excavation by the internal pumps, and whether the GT clay layer achieved an effective seal between the GO and GT sand below.

Fig. 7.

Section through excavation showing piezometer installation levels. Perforated pipe lengths are indicated by the dashed lines. Plan locations are given in Fig. 6 

Fig. 7.

Section through excavation showing piezometer installation levels. Perforated pipe lengths are indicated by the dashed lines. Plan locations are given in Fig. 6 

Close modal

A time history of the maximum lateral displacement, δh,max, experienced by the four monitored tubes (IC1–IC4) is presented in Fig. 8. For reference, the average surveyed excavation level is plotted using a secondary axis and key construction activities are indicated using shaded regions. The development trends of δh,max for all four monitored tubes during construction are similar. The largest δh,max ( = 23·2 mm) during excavation was recorded for IC1, which was 1·4–1·7 times greater than those recorded for IC2–IC4 due to its position at the centre of the west wall and the presence of a plant access road, and therefore additional surcharging, on the west side. It is also likely that IC2 and IC4 experienced beneficial ‘corner effects’ (Roboski, 2004). A significant increase is observed for IC3 during the bunker piling, indicating a much greater effect of this activity on the long span of the support system. Negligible changes are observed following base construction.

Fig. 8.

Time history of instrumented tube pile maximum lateral displacements and average internal level

Fig. 8.

Time history of instrumented tube pile maximum lateral displacements and average internal level

Close modal

All tube piles around the perimeter of the cofferdam were surveyed before and after the initial 1·5 m deep excavation (stage 4 in Table 1) to monitor lateral deflection at the cantilever stage. The average ratio of cantilever deflection to maximum deflection for the four monitored tube piles δh,c/δh,max = 1·19 is significantly larger than the range of 0·3–0·6 reported in Gaba et al. (2017) for excavations in London Clay, indicating that the passive resistance provided by the soft TF layers following removal of the stiffer MG band is much less than that provided by the stiffer London Clay.

Figure 9 shows the horizontal displacement, δh, profiles with depth measured for IC1–IC4 at several stages during excavation together with (long-span) cross-sections of the corresponding excavation surface profile. It can be seen that the RC capping beam was highly effective at ‘anchoring’ the top of the cofferdam. Interestingly, negative lateral displacements initially develop at ∼1·5 m BGL for IC4 due to shallow excavation works (to a depth of ∼1 m) occurring behind the capping beam during the construction of a RC slab. As excavation depth, H, increases, there is a steady increase in both δh,max and its corresponding depth, to the point where δh,max occurs near the dig level at the end of excavation. The largest percentage increases in δh,max caused by excavation phase two were 210% and 136% for IC3 and IC4, respectively, on the east side of the bunker, whereas 82% and 95% increases were observed for IC1 and IC2, respectively. This may be attributed to the additional 0·5 m depth excavated on the east side, compared to the west side during this period.

Fig. 9.

(a) Horizontal displacement profiles for instrumented tube piles during bunker excavation. (b) Corresponding bunker excavation level surveys taken through section A–A in Fig. 6, and legend. Phase 1 excavation and phase 2 excavation indicated by black and grey lines, respectively

Fig. 9.

(a) Horizontal displacement profiles for instrumented tube piles during bunker excavation. (b) Corresponding bunker excavation level surveys taken through section A–A in Fig. 6, and legend. Phase 1 excavation and phase 2 excavation indicated by black and grey lines, respectively

Close modal

Figure 10 shows the profiles of δh with depth during bunker piling, which is broken into four different ‘piling weeks’ (WK1–WK4), as shown in the pile installation layout in Fig. 10(b). Bunker piling causes substantial increases in δh for all four monitored tube piles. In contrast, no appreciable changes to the corresponding depths to δh,max or the overall deflected shapes are observed. Measured displacements are strongly influenced by nearest proximity piling, whereas other piling has only a secondary effect. For example, WK1 piling causes a significant increase in IC4 displacements, which then show negligible changes during subsequent piling. In contrast, there is a steady increase in δh,max for IC2 and IC1 during this period as the piling progressed towards the west side of the bunker. The piling process had the greatest impact on the long-span IC3 measurements with an increase in δh,max of 111%, which is likely to be due to its closer proximity to the bunker piles.

Fig. 10.

(a) Measured δh profiles with depth for all four instrumented tube piles during internal piling works and RC bunker base construction (WK3 profiles omitted due to sensor fault); (b) corresponding weekly pile installation layout

Fig. 10.

(a) Measured δh profiles with depth for all four instrumented tube piles during internal piling works and RC bunker base construction (WK3 profiles omitted due to sensor fault); (b) corresponding weekly pile installation layout

Close modal

Following piling, the 2 m thick RC base is cast with all temporary propping still in place. From Fig. 10(a), base installation causes a small decrease in δh,max for IC1 and IC3 and a small increase in δh,max for IC2 and IC4. This suggests a competing influence of the outward concrete head and the subsequent concrete shrinkage during curing.

The maximum wall displacement and its corresponding depth BGL (z[δh,max]) are plotted as a function of the final excavation depth in Figs 11(a) and 11(b), respectively. Empirical relationships and data from previous case histories are also superimposed on these plots for comparison. The adopted selection of empirical design rules represents a mix of average expected displacements and recommended upper limits for design, and are defined in Table 4. From Fig. 11(a), present measurements span a relatively broad range. Fernie & Sucking (1996) (labelled [4] in the figure) recommended that an average of δh,max/H = 0·15% provides a reasonable fit to the data during the excavation process, whereas the upper limit of δh,max/H = 0·5% (Clough & O'Rourke, 1990) represents a safe design bound for the present data. Bunker piling and construction causes the displacements to increase above several average and bound lines at the end of construction, thus highlighting the importance of considering all stages of construction in design.

Fig. 11.

Comparison between present monitored data and empiricism reported elsewhere in the literature: (a) variation of δh,max with H both during excavation (denoted by E) and post bunker construction (denoted by PBC) (refer to Table 4 for empirical design rule definition and notation [1]–[6]); (b) variation of z[δh,max] with H. SS denotes sheet and soldier pile walls, CSD denotes contiguous, secant pile and diaphragm walls

Fig. 11.

Comparison between present monitored data and empiricism reported elsewhere in the literature: (a) variation of δh,max with H both during excavation (denoted by E) and post bunker construction (denoted by PBC) (refer to Table 4 for empirical design rule definition and notation [1]–[6]); (b) variation of z[δh,max] with H. SS denotes sheet and soldier pile walls, CSD denotes contiguous, secant pile and diaphragm walls

Close modal
Table 4.

Empirical δh,max/H ratios reported in the literature

ReferenceSupport system typeDesign rule notationδh,max/H: %DescriptionSoil conditions
Clough & O'Rourke (1990) SS, CSD[1]0·5MaximumSoft clays
[2]0·2MaximumStiff clays
Fernie & Sucking (1996) CSD[3]0·3MaximumStiff London Clay
[4]0·15Average
Long (2001) SS, CSD[5]0·39AverageRetaining soft soils, embedded in stiff soils (‘case 2’)
Moormann (2004) SS, CSD[6]0·27AverageLayered soils

Note: SS denotes sheet and soldier pile walls, CSD denotes contiguous, secant pile and diaphragm walls.

In Fig. 11(b), the present monitored data are compared with those reported by Moormann (2004) in layered soils representing either soldier or sheet pile walls (denoted ‘SS’) or contiguous, secant pile and diaphragm walls (denoted ‘CSD’). The present measurements are well described by the z[δh,max]/H = 1·0 guideline (Moormann, 2004), indicating that the point of maximum displacement is approximately located at the dig level during excavation. This is consistent with the reported behaviour of walls supporting soft clays in China, with maximum lateral wall deflections in stiff clays typically occurring further above the excavation level (Tan et al., 2018), highlighting the soft nature of the TF layers.

A time history of the overall axial and bending loads for each instrumented level 2 bracing member is shown in Figs 12(a) and 12(b), respectively; key construction stages are again identified using grey shading. The measured axial loads show similar trends for all four bracing members. The largest measured axial load is experienced by the corner brace on account of this member being at an angle to the cofferdam wall and having the largest tributary area (and vice versa for the perimeter waler). Predictably, there is a noticeable increase in axial loads during the excavation phase, due to stress redistribution from the internal soil to the support structure.

Fig. 12.

Level 2 instrumented frame member (a) axial load–time series and (b) bending moment–time series

Fig. 12.

Level 2 instrumented frame member (a) axial load–time series and (b) bending moment–time series

Close modal

Significant increases in axial loads are also caused by the vibratory piling. While WK1 and WK2 piling had little influence on the axial loads, significant increases occurred during WK3 and WK4 as piling progressed towards the instrumented members on the west side of the bunker (see Fig. 10(b)). These considerable load increases and the associated increases in lateral wall deflection in Fig. 10 are due to a loss of strength of glacial till clay (C) inside the excavation consequent upon remoulding and excess pore pressure generation caused by pile driving. The vibratory piling may have also induced liquefaction effects in the saturated GO layer. These results highlight the importance of considering the impact of the full construction process on the adopted support system.

Following the casting of the RC bunker base, a significant reduction in compressive axial load of 91%, 41%, 29% and 36% was observed for W1, CCB1, P1 and P2, respectively. This can be attributed to a redistribution of the bracing forces into the RC base, which undergoes thermal expansion during cement hydration. This behaviour is consistent with the reductions in prop loads of ∼10% and ∼20% following base slab installation reported in Powrie & Batten (2000) and Chambers et al. (2016), respectively. Finally, post-excavation removal of the frame caused notable increases in axial load, as removed frame member loads redistributed into adjacent members.

Similar findings may be deduced from an examination of the bending moments in Fig. 12(b). The largest bending moments developed in the corner brace, which may be attributed to the significant eccentricity of the applied cofferdam load. The two central tube props experience bending towards the west side of the bunker, which suggests the long-span waler on the north side of the bunker is exhibiting curvature towards the excavation, which is symmetric about the centre of the span. The magnitude of the bending moment measured in P1 is significantly larger than that in P2, owing to P2's closer proximity to the centre of symmetry on the north waler.

The maximum distributed prop load per unit tributary area (DPL) is calculated as 195, 152, 140 and 145 kN/m2 for W1, CCB1, P1 and P2, respectively. Of the values of DPL for over 300 prop members supporting deep excavations reported in Twine & Roscoe (1997), 86% fall below the smallest measured DPL of 140 kN/m2. This suggests a large proportion of lateral earth loads are transferred into the support structure, highlighting the low strength of the TF layers. The calculated DPL values are consistent with those reported for props supporting excavations in soft clays in Oslo, Norway (NGI, 1962), Chicago, USA (Swatek et al., 1972) and Rotterdam, the Netherlands (Tschebotarioff, 1973).

From Fig. 12(a), even though the VW strain gauges were verified to have negligible temperature effects, significant daily fluctuations are observed in the data, due to thermal (expansion) effects experienced by the props. Several methods for compensating for these temperature fluctuations have been reported in the literature (Richards et al., 1999; Powrie & Batten, 2000), which involve monitoring temperature fluctuations during downtime periods. By way of an example, Fig. 13 shows the measured microstrain, με, for gauge GW,3A (multiplied by EA to give an apparent load in kN) plotted against the temperature measured by the gauge thermistor during a downtime period between 1 November 2021 and 20 November 2021. An approximately linear relationship between temperature and measured strain is apparent, indicating strong temperature causation. By calculating the gradient of the assumed linear relationship, f, the prop end fixity factor, FF, can be calculated

5

where α is the coefficient of thermal expansion of the prop material, and ft is the theoretical thermally induced load assuming rigid end restraint. Table 5 summarises the calculation of FF for each of the level 2 frame gauges. There is good consistency between the values of FF for pairs of gauges on each frame member. The largest values of FF were calculated for waler W1, which is to be expected as the ends of this member are welded to those members adjacent. The smallest values of FF were calculated for the tube props P1 and P2, as these members were hung from the perimeter frame with no other method of connection applied to their ends. The proximity of the member to the corner of the excavation also influenced the calculated FF, indicating increased composite support structure stiffness at the excavation corners. This finding is consistent with the monitored lateral wall deflection behaviour. Except for W1, owing to its welded ends, the calculated FF values are reasonably consistent with the 10–25% range recommended in Twine & Roscoe (1997), based on previous sheet pile wall case histories. The current industry-adopted approach for incorporating prop temperature effects into design in Gaba et al. (2017) suggests using FF values of 30% and 50% for stiff walls in soft soils and in stiff soils, respectively. However, no guidance is provided for excavations supported by more flexible sheet pile walls and combi-walls. Although data from more cases will be necessary to verify or refine the calculated FF, the values from this project can be contributed towards this database to provide initial guidance on the selection of FF values for these more flexible wall types.

Fig. 13.

Typical relationship between temperature and apparent gauge load (gauge GW,3A) during a period of no construction activity in the bunker area

Fig. 13.

Typical relationship between temperature and apparent gauge load (gauge GW,3A) during a period of no construction activity in the bunker area

Close modal
Table 5.

Summary of the end fixity factor, FF, calculation for each level 2 frame member gauge

Level 2 frame memberGaugef: kN/°Cft: kN/°CFF: %
W1 walerGW,1A115·1247·346·5
GW,1B117·6247·347·5
CCB1 corner braceGW,2A82·2290·528·3
GW,2B81·0290·527·9
P1 tube propGW,3A29·9230·113·0
GW,3B30·7230·113·3
P2 tube propGW,4A29·5178·916·5
GW,4B31·5178·917·6

As the relationship between measured strain and temperature for each gauge is approximately linear, the measured prop loads can be adjusted to account for thermal expansion as follows

6

where Fadjusted are the loads that would have been recorded in each prop had the construction occurred without variation in temperature. Fig. 14 presents a comparison between F and Fadjusted for all four instrumented frame members. Although daily fluctuations in Fadjusted are considerably less than those in F, temperature fluctuations have not been eliminated completely. This is due to seasonal variations in differential temperature across the prop and to the member loads–temperature relationships not being truly linear. The largest difference between F and Fadjusted is observed for W1 (61·1%) due to the large FF combined with a period of seasonal cooling from September until December. In contrast, there is little difference between F and Fadjusted for props P1 and P2 owing to the reduced FF enabling almost uninhibited thermally induced movement. In contrast, temperature compensation had a negligible influence on bending moments due to compensated gauges cancelling each other out.

Fig. 14.

Comparison between axial load, F, and temperature-adjusted axial load, Fadjusted, for: (a) waler W1; (b) corner brace CCB1; (c) prop P1; (d) prop P2. The construction activities indicated by vertical lines and shaded regions are the same as those annotated in Fig. 12 

Fig. 14.

Comparison between axial load, F, and temperature-adjusted axial load, Fadjusted, for: (a) waler W1; (b) corner brace CCB1; (c) prop P1; (d) prop P2. The construction activities indicated by vertical lines and shaded regions are the same as those annotated in Fig. 12 

Close modal

The observed water level time series for all piezometers are shown in Fig. 15. For reference, the corresponding time history of the total pumped flow rate, q, is also plotted on a secondary axis. The site water table outside the excavation (PO,U) remained consistently high throughout construction, varying between 2 and 3 m above ordnance datum (AOD), due to the close proximity of the River Mersey. Initially three pumping wells were operational, with an average q = 5·5 l/s, reducing the water table within the bunker (PI,1, PI,2) to approximately −5·5 m AOD. This was still 0·7 m above the estimated formation depth, which led to the mobilisation of a fourth pumping well on 1 September 2021, which increased q to 7 l/s and reduced the level to −7 m AOD. During unexpected shutdowns of the pumping system (reflected by q = 0), the water level increased rapidly at a rate of 100 mm/min. To reduce the risk to personnel within the excavation and prevent damage to plant, the capacity of the pumping system was increased further by repurposing the PI,1 monitoring well for a fifth pumping well on 7 September 2021. This reduced the water level to −8·5 m AOD and increased q to 8 l/s.

Fig. 15.

Piezometer water level data and total pumped well flow rate

Fig. 15.

Piezometer water level data and total pumped well flow rate

Close modal

The internal (PI,2) and external (PO,L) water levels in the lower GT sands show very similar trends except PI,2 is consistently ∼1·5 m higher, indicating groundwater is being drawn into the bunker through seepage beneath the cofferdam toe. This behaviour is consistent with that reported in Pujades et al. (2014) where seepage occurred beneath the walls of a deep shaft for a high-speed train tunnel in Barcelona, through transmissive layers inside materials of low hydraulic conductivity. During a watertightness testing, the pumped flow rate of 7 l/s achieved a drawdown of ∼10 m, which again is consistent with the measured q for this project. This suggests flow through the lower GT layers behaves similarly to that through the Barcelona silty sand layers. The water level in the GO sand layer remains at the site water table level, indicating that the GT clay layer acts as a highly effective seal to prevent flow between the GO and GT granular layers. The mobilisation of bunker piling towards the monitoring well locations (early October 2021) caused an increase in water level of ∼2·2 m in both PI,2 and PO,L, despite no apparent change in system set-up and a constant q = 8 l/s. This reduction in performance may be due to the disturbance and restriction of flow passages in the ground adjacent to the monitoring wells caused by the vibratory piling equipment. The dewatering and water level monitoring schemes directly mitigated and helped manage the risks of flooding, excessive pumping rates and wall infiltration posed by the deep excavation and bunker construction.

This paper has described the observed performance of a deep excavation retaining soft clays and peats for the purpose of an energy-from-waste facility in the UK. To inform the construction process, a monitoring system was developed to provide real-time feedback to site personnel. The monitoring system enabled the measurement of cofferdam wall horizontal deflections, prop loads, and bunker and site water levels. The main findings of this study can be summarised as follows.

  • (a)

    Measured wall displacements were well represented by average values reported elsewhere in the literature and were close to lower bounds reported for deep excavations in soft clays; these results highlight the potential applicability of existing solutions and design methods to combi-wall design in soft soils in the UK.

  • (b)

    Vibratory piling internally within the excavation cause an increase to the horizontal wall displacements of up to 111%, revealing the importance of considering the full construction process on the support system performance.

  • (c)

    The axial loads measured in the bracing members increased steadily during excavation, with the largest load developed in the corner brace (2300 kN) owing to its relatively large tributary length and it being at an angle to the cofferdam wall. Internal bunker piling caused an increase in member loads of between 700 and 2100 kN.

  • (d)

    The monitored data showed that temperature-induced axial loads can account for a significant proportion of the total member load for frames installed at low temperatures. The present data reveal a degree of end restraint in the range of 10–30% to be appropriate for deep excavations in soft clays supported by driven steel cofferdams.

  • (e)

    Continuous groundwater pumping, with flow rates consistently above 7 l/s, was necessary to retain the internal excavation water level below formation level, owing to seepage occurring below the cofferdam toe. Piling within the excavation led to a reduction in the performance of the pumping system due to the introduction of additional flow paths.

Some or all data used in this paper are available from the corresponding author by request.

The authors gratefully acknowledge the technical guidance and financial support provided by Ward & Burke Construction Ltd for this research, as well as the efforts of the site team at PROTOS energy recovery facility. The authors also thank the team at WJ Groundwater for the installation of the dewatering and water level monitoring systems. This project was supported by the Royal Academy of Engineering under the Research Fellowship Scheme.

A

area

E

Young's modulus

F

axial load

Fadjusted

temperature adjusted axial load

FF

prop end fixity factor

f

prop temperature gradient

ft

theoretical thermally induced prop load – rigid end restraint

G0

small-strain shear stiffness

H

excavation depth

M

bending moment

Nkt

cone penetration test cone factor

q

flow rate

qt

cone penetration test corrected cone tip resistance

su

undrained shear strength

T

temperature

t

thickness

u

pore water pressure

Vs

shear wave velocity

w

water content

Z

elastic modulus

z[δh,max]

depth of position of δh,max

α

thermal expansion coefficient

γbulk

soil bulk unit weight

δh

lateral displacement

δh,max

maximum lateral displacement

ρ

soil density

σv0

in situ vertical stress

Φ

angle of friction

Allievi
,
L.
,
Curran
,
T.
,
Deakin
,
R.
&
Tyldsley
,
C.
(
2018
). On the use of CPT for the geotechnical characterization of a normally consolidated alluvial clay in Hull, UK. In
Cone penetration testing 2018
(eds
M. A.
Hicks
,
F.
Pisanò
and
J.
Peuchen
), pp.
73
78
.
Leiden, the Netherlands
:
CRC Press/Balkema
.
Carder
,
D. R.
(
1995
).
Ground movements caused by different embedded retaining wall construction techniques
, TRL Report 172.
Wokingham, UK
:
Transport Research Laboratory
.
Chambers
,
P.
,
Augarde
,
C.
,
Reed
,
S.
&
Dobbins
,
A.
(
2016
).
Temporary propping at Crossrail Paddington station
.
Geotech. Res.
3
, No.
1
,
3
16
.
Cheng
,
K.
,
Xu
,
R.
,
Ying
,
H.
,
Gan
,
X.
,
Zhang
,
L.
&
Liu
,
S.
(
2021
).
Observed performance of a 30.2 m deep-large basement excavation in Hangzhou soft clay
.
Tunn. Undergr. Space Technol.
111
,
103872
.
Clough
,
G. W.
&
O'Rourke
,
T. D.
(
1990
). Construction induced movements of in situ walls. In
Design and performance of earth retaining structures
(eds
P.
Lambe
and
L.
Hansen
), Geotechnical Special Publication no. 25, pp.
439
470
.
Reston, VA, USA
:
American Society of Civil Engineers
.
Fernie
,
R.
&
Sucking
,
T.
(
1996
). Simplified approach for estimating lateral wall movement of embedded walls in UK ground. In
Geotechnical aspects of underground construction in soft ground
(eds
R. J.
Mair
and
R. N.
Taylor
), pp.
131
136
.
Rotterdam, the Netherlands
:
Balkema
.
Finno
,
R. J.
&
Roboski
,
J. F.
(
2005
).
Three-dimensional responses of a tied-back excavation through clay
.
J. Geotech. Geoenviron. Engng
131
, No.
3
,
273
282
.
Finno
,
R. J.
,
Atmatzidis
,
D. K.
&
Nerby
,
S. M.
(
1988
).
Ground response to sheet pile installation in clay
. In
International conference on case histories in geotechnical engineering
, pp.
1297
1301
.
Rolla, MO, USA
:
Missouri University of Science and Technology
.
Finno
,
R. J.
,
Atmatzidis
,
D. K.
&
Perkins
,
S. B.
(
1989
).
Observed performance of a deep excavation in clay
.
J. Geotech. Engng
115
, No.
8
,
1045
1064
.
Finno
,
R. J.
,
Bryson
,
S.
&
Calvello
,
M.
(
2002
).
Performance of a stiff support system in soft clay
.
J. Geotech. Geoenviron. Engng
128
, No.
8
,
660
671
.
Finno
,
R. J.
,
Arboleda-Monsalve
,
L. G.
&
Sarabia
,
F.
(
2015
).
Observed performance of the one museum park west excavation
.
J. Geotech. Geoenviron. Engng
141
, No.
1
,
04014078
.
Finno
,
R. J.
,
Kim
,
S.
,
Lewis
,
J.
&
Van Winkle
,
N.
(
2019
).
Observed performance of a sheetpile-supported excavation in Chicago clays
.
J. Geotech. Geoenviron. Engng
145
, No.
2
,
05018005
.
Gaba
,
A.
,
Hardy
,
S.
,
Doughty
,
L.
,
Powrie
,
W.
&
Selemetas
,
D.
(
2017
).
Guidance on embedded retaining wall design
.
London, UK
:
Ciria
.
Hewitt
,
R. D.
,
Haley
,
M. X.
&
Kinner
,
E. B.
(
2003
).
Case history of deep excavation on an urban campus
. In
Proceedings of the 12th panAmerican conference on soil mechanics and geotechnical engineering
(eds
P. J.
Culligan
,
H. H.
Einstein
and
A. J.
Whittle
), pp.
1997
2004
.
Essen, Germany
:
Verlag Glückauf GmbH
.
Johansson
,
E.
&
Sandeman
,
E.
(
2014
).
Modelling of a deep excavation in soft clay a comparison of different calculation methods to in situ measurements
.
Master's thesis
, Chalmers University of Technology, Gothenburg, Sweden.
Kulhawy
,
F. H.
&
Mayne
,
P. W.
(
1990
).
Manual on estimating soil properties for foundation design
,
no. EPRI-EL-6800
(prepared by
Cornell University
,
Ithaca, NY, USA
).
Palo Alto, CA, USA
:
Electric Power Research Institute
.
Langford
,
J.
,
Karlsrud
,
K.
,
Bengtsson
,
E.
,
Hof
,
C.
&
Oscarsson
,
R.
(
2021
). Comparison between predicted and measured performance of a deep excavation in soft clay in Gothenburg, Sweden. In
Geotechnical aspects of underground construction in soft ground
(eds
M.
Elshafie
,
G.
Viggiani
and
R.
Mair
), pp.
83
90
.
Leiden, the Netherlands
:
CRC Press/Balkema
.
Liu
,
G. B.
,
Ng
,
C. W.
&
Wang
,
Z. W.
(
2005
).
Observed performance of a deep multistrutted excavation in Shanghai soft clays
.
J. Geotech. Geoenviron. Engng
131
, No.
8
,
1004
1013
.
Liu
,
G. B.
,
Jiang
,
R. J.
,
Ng
,
C. W.
&
Hong
,
Y.
(
2011
).
Deformation characteristics of a 38 m deep excavation in soft clay
.
Can. Geotech. J.
48
, No.
12
,
1817
1828
.
Long
,
M.
(
2001
).
Database for retaining wall and ground movements due to deep excavations
.
J. Geotech. Geoenviron. Engng
127
, No.
3
,
203
224
.
Mana
,
A. I.
&
Clough
,
G. W.
(
1981
).
Prediction of movements for braced cuts in clay
.
J. Geotech. Engng Div.
107
, No.
6
,
759
777
.
Masini
,
L.
,
Gaudio
,
D.
,
Rampello
,
S.
&
Romani
,
E.
(
2021
).
Observed performance of a deep excavation in the historical center of Rome
.
J. Geotech. Geoenviron. Engng
147
, No.
2
,
05020015
.
Moormann
,
C.
(
2004
).
Analysis of wall and ground movements due to deep excavations in soft soil based on a new worldwide database
.
Soils Found.
44
, No.
1
,
87
98
.
Ng
,
C. W. W.
,
Hong
,
Y.
,
Liu
,
G. B.
&
Liu
,
T.
(
2012
).
Ground deformations and soil–structure interaction of a multi-propped excavation in Shanghai soft clays
.
Géotechnique
62
, No.
10
,
907
921
, .
NGI (Norwegian Geotechnical Institute)
(
1962
).
Measurements at a strutted excavation, Oslo subway, Vaterland 1
, Technical Report 7.
Oslo, Norway
:
NGI
.
Orazalin
,
Z. Y.
,
Whittle
,
A. J.
&
Olsen
,
M. B.
(
2015
).
Three-dimensional analyses of excavation support system for the Stata Center basement on the MIT campus
.
J. Geotech. Geoenviron. Engng
141
, No.
7
,
05015001
, .
Ou
,
C. Y.
,
Hsieh
,
P. G.
&
Chiou
,
D. C.
(
1993
).
Characteristics of ground surface settlement during excavation
.
Can. Geotech. J.
30
, No.
5
,
758
767
.
Peck
,
R. B.
(
1969
).
Deep excavation & tunnelling in soft ground: state of the art report
. In
Proceedings of the 7th international conference of soil mechanics and foundation engineering
, pp.
225
281
.
Mexico City, Mexico
:
Sociedad Mexicana de Mecanica
.
Powrie
,
W.
&
Batten
,
M.
(
2000
).
Comparison of measured and calculated temporary-prop loads at Canada Water Station
.
Géotechnique
50
, No.
2
,
127
140
, .
Pujades
,
E.
,
Vàzquez-Suñé
,
E.
,
Carrera
,
J.
&
Jurado
,
A.
(
2014
).
Dewatering of a deep excavation undertaken in a layered soil
.
Engng Geol.
178
,
15
27
.
Richards
,
D. J.
,
Holmes
,
G.
&
Beadman
,
D. R.
(
1999
).
Measurement of temporary prop loads at Mayfair car park
.
Proc. Instn Civ. Engrs Geotech. Engng
137
, No.
3
,
165
174
, .
Robertson
,
P. K.
(
2009
).
Interpretation of cone penetration tests—a unified approach
.
Can. Geotech. J.
46
, No.
11
,
1337
1355
.
Robertson
,
P. K.
(
2010
).
Soil behaviour type from the CPT: an update
. In
CPT '10: 2nd international symposium on cone penetration testing, conference proceedings
(eds
P. K.
Robertson
and
P. W.
Mayne
), vol.
2
, pp.
575
582
.
Huntington Beach, CA, USA
:
CPT '10 Organizing Committee
.
Roboski
,
J. F.
(
2004
).
Three-dimensional performance and analyses of deep excavations
. PhD thesis,
Northwestern University
, Evanston, IL, USA.
Royston
,
R.
(
2018
).
Investigation of soil–structure interaction for large diameter caissons
.
Doctoral thesis
,
University of Oxford
,
Oxford, UK
.
St John
,
H. D.
,
Higgins
,
K. G.
,
Potts
,
D. M.
&
Jardine
,
R. J.
(
1992
).
Prediction and performance of ground response due to construction of a deep basement at 60 Victoria embankment
. In
Predictive soil mechanics: proceedings of the Wroth memorial symposium held at St Catherine's College, Oxford, 27–29 July 1992
(eds
G. T.
Houlsby
and
A. N.
Schofield
), pp.
581
608
.
London, UK
:
Thomas Telford Publishing
.
Swatek
,
E. P.
,
Asrow
,
S. P.
&
Seitz
,
A. M.
(
1972
). Performance of bracing for deep Chicago excavation. In
Proceedings of the specialty conference on performance of earth and earth-supported structures
, vol. 1, part 2, pp.
1303
1322
.
New York, NY, USA
:
American Society of Civil Engineers
.
Tan
,
Y.
&
Wei
,
B.
(
2012
).
Observed behaviors of a long and deep excavation constructed by cut-and-cover technique in Shanghai soft clay
.
J. Geotech. Geoenviron. Engng
138
, No.
1
,
69
88
.
Tan
,
Y.
,
Lu
,
Y.
&
Wang
,
D.
(
2018
).
Deep excavation of the Gate of the Orient in Suzhou stiff clay: composite earth-retaining systems and dewatering plans
.
J. Geotech. Geoenviron. Engng
144
, No.
3
,
05017009
.
Tornborg
,
J.
,
Karlsson
,
M.
,
Kullingsjö
,
A.
&
Karstunen
,
M.
(
2021
).
Experience from short- and long-term performance of deep excavations in soft sensitive clays
.
IOP Conf. Ser.: Earth Environ. Sci.
710
, 012053.
Tschebotarioff
,
G.
(
1973
).
Foundations, retaining and earth structures – the art of design and construction and its scientific bases in soil mechanics
.
London, UK
:
McGraw-Hill Education
.
Twine
,
D.
&
Roscoe
,
H.
(
1997
).
Temporary propping of deep excavations – guidance on design
.
London, UK
:
Construction Industry Research and Information Association
.
Wang
,
J. H.
,
Xu
,
Z. H.
&
Wang
,
W. D.
(
2010
).
Wall and ground movements due to deep excavations in Shanghai soft soils
.
J. Geotech. Geoenviron. Engng
136
, No.
7
,
985
994
.
Wu
,
S. H.
,
Ching
,
J.
&
Ou
,
C. Y.
(
2013
).
Predicting wall displacements for excavations with cross walls in soft clay
.
J. Geotech. Geoenviron. Engng
139
, No.
6
,
914
927
.

Discussion on this paper closes 01 April 2025; for further details see p. ii.

Published with permission by Emerald Publishing Limited under the CC-BY 4.0 license. (http://creativecommons.org/licenses/by/4.0/)

or Create an Account

Close Modal
Close Modal